Project Name: Lake Gardens (Violation Case) PFR Promoter: Shree Stambh Colonizers PRE FEASIBILITY REPORT

Upload: others

Post on 29-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

PRE FEASIBILITY REPORT

Page 2: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

Table of Contents 1. EXECUTIVE SUMMARY .................................................................................... 1

1.1 EXECUTIVE SUMMARY: ........................................................................................ 1

2. INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION ... 3

2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT: ........................... 3

2.2 BRIEF DESCIPTION OF NATURE OF THE PROJECT: ........................................... 3

2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY OR

REGION: ............................................................................................................................... 3

2.4 DEMAND SUPPLY GAP: .......................................................................................... 3

2.5 IMPORTS VS. INDIGENOUS PRODUCTION: ......................................................... 4

2.6 EXPORT POSSIBILITY:............................................................................................ 4

2.7 DOMESTIC/EXPORT MARKETS: ............................................................................ 4

2.8 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE

PROJECT DIRECT EMPLOYMENT: ................................................................................... 4

3. PROJECT DESCRIPTION ................................................................................... 5

3.1 EMPLOYMENT TYPE OF PROJECT INCLUDING INTERLINKED AND

INTERDEPENDENT PROJECTS, IF ANY: .......................................................................... 5

3.2 LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC LOCATION

AND PROJECT BOUNDARY & PROJECT SITE LAYOUT) WITH COORDINATES: ..... 5

3.3 DETAILS OF ALTERNATE SITES CONSIDERED AND THE BASIS OF

SELECTING THE PROPOSED SITE, PARTICULARLY THE ENVIRONMENTAL

CONSIDERATIONS GONE INTO SHOULD BE HIGHLIGHTED: ...................................... 6

3.4 SIZE OR MAGNITUDE OF OPERATION ................................................................ 6

3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS (A SCHEMATIC

DIAGRAM/ FLOW CHART SHOWING THE PROJECT LAYOUT, COMPONENTS OF

THE PROJECT ETC. SHOULD BE GIVEN .......................................................................... 6

3.6 RAW - MATERIAL REQUIRED ALONG WITH ESTIMATED QUANTITY,

LIKELY SOURCE, MARKETING AREA OF FINAL PRODUCT/S, MODE OF

TRANSPORT OF RAW MATERIAL AND FINISHED PRODUCT ...................................... 7

3.7 RESOURCE OPTIMIZATION/ RECYCLING AND REUSE ENVISAGED IN THE

PROJECT, IF ANY, SHOULD BE BRIEFLY OUTLINED .................................................. 8

3.8 AVAILABILITY OF WATER ITS SOURCE, ENERGY/ POWER REQUIREMENT

AND SOURCE SHOULD BE GIVEN ................................................................................... 8

Page 3: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

3.9 AVAILABILITY QUANTITY OF WASTES TO BE GENERATED (LIQUID AND

SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ................................... 8

3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS OF THE FEASIBILITY

DRAWING GIVING INFORMATION FOR EIA PURPOSE:................................................ 9

4. SITE ANALYSIS ................................................................................................. 10

4.1 CONNECTIVITY: .....................................................................................................10

4.2 LANDFORM, LAND - USE AND LAND OWNERSHIP: .........................................10

4.3 TOPOGRAPHY (ALONG WITH MAP):...................................................................11

4.4 EXISTING LAND- USE PATTERN (AGRICULTURE, NON-AGRICULTURE,

FOREST, WATER BODIES (INCLUDING AREA UNDER CRZ), SHORTEST

DISTANCES FROM THE PERIPHERY OF THE PROJECT TO PERIPHERY OF THE

FORESTS, NATIONAL PARK, WILD LIFE SANCTUARY, ECO SENSITIVE AREAS,

WATER BODIES (DISTANCE FROM THE HFL OF THE RIVER),CRZ. IN CASE OF

NOTIFIED INDUSTRIAL AREA, A COPY OF THE GAZETTE NOTIFICATION SHOULD

BE GIVEN): ..........................................................................................................................11

4.5 EXISTING INFRASTRUCTURE: .............................................................................12

4.6 SOIL CLASSIFICATION: .........................................................................................13

4.7 CLIMATIC DATA FROM SECONDARY SOURCES: .............................................13

4.8 SOCIAL INFRASTRUCTURE AVAILABLE: ..........................................................13

5. PLANNING BRIEF ............................................................................................. 15

5.1 PLANNING CONCEPT (TYPE OF INDUSTRIES, FACILITIES, AND

TRANSPORTATION ETC.) TOWN AND COUNTRY PLANNING/ DEVELOPMENT

AUTHORITY CLASSIFICATION: ......................................................................................15

5.2 POPULATION PROJECTION: .................................................................................15

5.3 LAND USE PLANNING (BREAKUP ALONG WITH GREEN BELT ETC.): ..........15

5.4 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL & SOCIAL): ......15

5.5 AMENITIES/ FACILITIES: ......................................................................................16

6. PROPOSED INFRASTURECTURE .................................................................. 17

6.1 INDUSTRIAL AREA (PROCESSING AREA): .........................................................17

6.2 RESIDENTIAL AREA (NON PROCESSING AREA): ..............................................17

6.3 GREEN BELT: ..........................................................................................................17

6.4 SOCIAL INFRASTRUCTURE: .................................................................................17

6.5 CONNECTIVITY (TRAFFIC AND TRANSPORTATION ROAD/ RAIL/ METRO/

WATER WAYS ETC.): ........................................................................................................17

6.6 DRINKING WATER MANAGEMENT (SOURCE & SUPPLY OF WATER): .........17

Page 4: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

6.7 SEWERAGE SYSTEM: ............................................................................................18

6.8 INDUSTRIAL WASTE MANAGEMENT: ................................................................18

6.9 SOLID WASTE MANAGEMENT: ...........................................................................18

7. REHABILITATION AND RESETTLEMENT (R&R) PLAN .......................... 19

7.1 POLICY TO BE ADOPTED (CENTRAL/STATE) IN RESPECT OF THE PROJECT

AFFECTED PERSONS INCLUDING HOME OUSTEES, LAND OUSTEES AND

LANDLESS LABORERS (A BRIEF OUTLINE TO BE GIVEN): ........................................19

8. PROJECT SCHEDULE & COST ESTIMATES ............................................... 20

8.1 LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF

COMPLETION (TIME SCHEDULE FOR THE PROJECT TO BE GIVEN): ........................20

8.2 ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF

ECONOMIC VIABILITY OF THE PROJECT ......................................................................20

9. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS) ..................... 21

9.1 FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS ON THE

BENEFIT TO THE LOCAL PEOPLE INCLUDING TRIBAL POPULATION, IF ANY, IN

THE AREA: ..........................................................................................................................21

LIST OF TABLES

TABLE 1: BRIEF DETAILS OF THE PROJECT ...................................................................... 1

TABLE 2: BRIEF DETAILS OF THE PROJECT .....................................................................10

TABLE 3: BRIEF DETAILS OF THE PROJECT .....................................................................10

TABLE 4: DISTANCE OF THE PROJECT SITE FROM SENSITIVE AREAS ........................12

TABLE 5: INFRASTRUCTURE FACILITIES .........................................................................13

LIST OF FIGURES

FIGURE 1: LOCATION MAP ................................................................................................... 5

FIGURE 2: PROJECT LAYOUT MAP .................................................................................. 7

FIGURE 3: EIA PROCESS ..................................................................................................... 9

FIGURE 4: LAND USE BREAK UP OF THE PROJECT SITE ..........................................11

FIGURE 5: WATER BALANCE CHART .............................................................................18

Page 5: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

P a g e | 1

1. EXECUTIVE SUMMARY

1.1 EXECUTIVE SUMMARY:

The project “Lake Gardens” is an existing project. The project Promoter is Shree

Stambh Colonizers, Udaipur. The project is located at Plot no 1 of Khasra No 411

to416, 418 to 432 and 435, Goverdhan Vilas Udaipur (Raj). Construction of

complete project has been completed at the site without taking prior

environmental clearance. Hence, the project is a violation case. All the technical

details related to project has been summarized in the following table.

TABLE 1: BRIEF DETAILS OF THE PROJECT

S.NO PARTICULAR DETAILS

1. Name of the Project

Lake Gardens

2. Name of Promoter Shree Stambh Colonizers

3. Category 8 (b) of Schedule to the EIA Notification, 2006.

4. Project Address Plot no 1 of Khasra No 411 to416, 418 to 432 and 435,

Goverdhan Vilas Udaipur (Raj)

5. Geographical

Coordinate

Latitude - 24°32’41.20”N and

Longitude - 75°41’18.1”E

6. Type of Project Residential

7. Constructions status Construction of the complete project has been completed. The

details of construction area on site is as under:

Plot Area: 17,975.03 Sq.m.

Built up Area: 42,090.74 Sq.m.

FSI area: 3,0004.58 Sq.m. (1.669)

8. Project Cost Rs 85.38 Cr

9. Project Details Built up Area 42,090.74 Sq.m.

FSI area 3,0004.58 Sq.m. (1.669)

Building Height

Block Up to

Terrace

Up to

Mummty

I 28 m 31 m

II 25 m 28 m

Page 6: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

III 28 m 31 m

Type and No of

Flats and facilities

1 BHK: 16 nos;

2BHK: 88 nos;

3 BHK:200 nos;

Total: 304 nos

Commercial Area: 182.74 Sq.m. and

Club House Area- 897.53 Sq.m

Ground Coverage 5,401.24 Sq.m. (30.05%)

Landscape Area 2,696.25 Sq.m. (15%)

Parking Area Open Surface: 330 ECU

Stilt Surface: 120 ECU

Paved/ Open Area 1,618.54 Sq.m. (9%)

10. Parking Details Require: 401 ECU

Provided: 450 ECU

Location ECU Area

Open 330 8,259 Sq.m.

Stilt 120 3,603 Sq.m.

Total 450 11,862 Sq.m.

11. Water requirement

and Source

Total: 168 KLD

Fresh: 136 KLD

Recycled: 32 KLD

Source: Existing Bore well, 3 nos

12. Wastewater

Treatment

STP Capacity: 120 KLD

STP Technology: MBBR Technology

13. Rain Water

Harvesting

RWH Structure no : 1

Capacity: 35 Cu.m.

14. Power Requirement

and Supply

Connected Load: 1183 KW

Transformer No: 2

Transformer Capacity: 1000 kVA

Supply: Udaipur Vidyut Vitran Nagar Limited

15. Power Backup DG Set Capacity : 180 kVA

Number: 1

16. Solid Waste

Generation

600 Kg/Day (Approx)

Being collected in dustbins and sent to municipal vendor.

Page 7: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

2. INTRODUCTION OF THE PROJECT/ BACKGROUND

INFORMATION

2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT:

Project name is Lake Gardens and it is promoted by Shree Stambh Colonizers,

Udaipur, Rajasthan. The project is located at Plot no 1 of Khasra No 411 to416,

418 to 432 and 435, Goverdhan Vilas Udaipur (Raj)

The permission of construction of the project was granted by UIT, Udaipur n two

phases vide letter number 1. B- PLAN/UIT/2009/3282 dated 30.12.2009 and 2.

F7 B- PLAN/MISC./2011/1597 dated 03.06.2011.

2.2 BRIEF DESCIPTION OF NATURE OF THE PROJECT:

The project is a residential project. Complete construction of the project has been

completed at the site hence, it is a violation case. The total plot area of the project

is 17,975.03 Sq.m., Built up Area is 42,090.74 Sq.m.and FSI Area of 3,0004.58

Sq.m. (1.669). The project consists of total 304 nos of flats comprising of 16 no 1

BHK flats, 88 nos 2 BHK flats and 200 nos 3 BHK flats.

2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE

COUNTRY OR REGION:

The residential projects are needed as population is increasing. A census 2011,

released by Directorate of Census Operations in Rjasthan showed a population

growth of 23.69% in the population of district Udaipur compared to population as

per 2001 (Total population is 3,068,420 compared to 2,480,657 of 2001).

2.4 DEMAND SUPPLY GAP:

The housing demand estimations are done by Udaipur Municipal Council for

municipal limits, as housing statistics are available for census year 2001. Housing

needs for entire municipal town is estimated excluding poor population, which is

Page 8: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

dealt separately. The city presently needs around 35,000 housing units; this

includes requirements for city poor of around 17,500 units.

Stakeholder consultations also reveal that residents in inner core of the city, have

concerns regarding loosing out on close knit community structures they have

lived in for generations. A closer engagement is required between citizens and

UIT, to emerge with innovative solutions to resolve this gap. Residential Group

housings apartments with common amenities could be a better solution to this

problem.

2.5 IMPORTS VS. INDIGENOUS PRODUCTION:

Not Applicable

2.6 EXPORT POSSIBILITY:

Not Applicable

2.7 DOMESTIC/EXPORT MARKETS:

Not Applicable

2.8 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO

THE PROJECT DIRECT EMPLOYMENT:

Total employment in the project will be approximately 50 people. The local

persons will be given employment.

**********

Page 9: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

3. PROJECT DESCRIPTION

3.1 EMPLOYMENT TYPE OF PROJECT INCLUDING INTERLINKED AND

INTERDEPENDENT PROJECTS, IF ANY:

The project is an independent project. There is no interlinked project.

3.2 LOCATION (MAP SHOWING GENERAL LOCATION, SPECIFIC

LOCATION AND PROJECT BOUNDARY & PROJECT SITE LAYOUT)

WITH COORDINATES:

FIGURE 1: LOCATION MAP

Page 10: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

3.3 DETAILS OF ALTERNATE SITES CONSIDERED AND THE BASIS OF

SELECTING THE PROPOSED SITE, PARTICULARLY THE

ENVIRONMENTAL CONSIDERATIONS GONE INTO SHOULD BE

HIGHLIGHTED:

The project is an existing project. No alternative site was examined.

3.4 SIZE OR MAGNITUDE OF OPERATION

Project Type: Group Housing Complex

Project Plot Area: 17,975.03 Sq.m

Project Capacity:

No of Blocks: 3 no

Built Up Area: 42,090.74 Sq.m.

Flats no and Type:

1 BHK- 16 nos

2 BHK – 88 nos

3 BHK – 200 nos

Other Facility:

Commercial Area – 182.74 Sq.m.

Club House Area – 897.53 Sq.m

3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS (A SCHEMATIC

DIAGRAM/ FLOW CHART SHOWING THE PROJECT LAYOUT,

COMPONENTS OF THE PROJECT ETC. SHOULD BE GIVEN

3.5.1 PROCESS:

No process involved as it is a residential project.

3.5.2 PROJECT LAYOUT:

The project layout plan is given in following figure 2.

Page 11: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

FIGURE 2: PROJECT LAYOUT MAP

3.6 RAW - MATERIAL REQUIRED ALONG WITH ESTIMATED

QUANTITY, LIKELY SOURCE, MARKETING AREA OF FINAL

PRODUCT/S, MODE OF TRANSPORT OF RAW MATERIAL AND

FINISHED PRODUCT

The project construction has bee completed hence no raw material will be

required.

Page 12: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

3.7 RESOURCE OPTIMIZATION/ RECYCLING AND REUSE ENVISAGED

IN THE PROJECT, IF ANY, SHOULD BE BRIEFLY OUTLINED

Not envisaged.

3.8 AVAILABILITY OF WATER ITS SOURCE, ENERGY/ POWER

REQUIREMENT AND SOURCE SHOULD BE GIVEN

3.8.1 Water Requirement and Source:

The total water requirement of the project is 168 KLD including 136 KLD fresh

water requirements and 32 KLD treated waste water requirement. The fresh water

is being supplied through 3 existing bore wells in the premises.

3.8.2 Power Requirement and Source:

The total connected load requirement of the project is 1183 KW. Power supply is

being taken by Udaipur Vidyut Vitran Nagar Limited.

3.9 AVAILABILITY QUANTITY OF WASTES TO BE GENERATED

(LIQUID AND SOLID) AND SCHEME FOR THEIR MANAGEMENT/

DISPOSAL

Solid waste: Approximately 600 kg/day solid waste will be generated by the

project at 100% occupancy. The waste is being collected in dustbin and finally

being disposed off to municipal vendors.

Waste Water: Approximately 108 KLD wastewater will be generated by the

project at 100% occupancy. Presently the wastewater is being treated in the STP

based on MBBR technology with capacity 120 KLD.

Page 13: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS OF THE

FEASIBILITY DRAWING GIVING INFORMATION FOR EIA

PURPOSE:

The proposed unit is categorized under Item 8 (a) Category A (“Building and

Construction Project” having built up area > 20,000 sq. m.) of Gazette Notification

dated Sep 14th, 2006 and subsequent amendments thereafter.

The process for obtaining Environmental Clearance for the proposed projects as per

EIA Notification–2006 is as under:

FIGURE 3: EIA PROCESS

**********

Page 14: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

4. SITE ANALYSIS

4.1 CONNECTIVITY:

The project site is having sector roads on two sides. It is very well connected with

State highways and National Highways. The approximate distance and direction

of the project site from national and state highways is given under:

TABLE 2: BRIEF DETAILS OF THE PROJECT

Name Distance (aerial*) Direction

NH-927 A 0.15 km W

NH- 8 1.6 Km S

SH- 32 1.9 km E

4.2 LANDFORM, LAND - USE AND LAND OWNERSHIP:

4.2.1 Landform:

The general topography of the site is slightly undulating. The highest elevation is

589.18 m whereas lowest is 582.48 m. The slope is tending towards SE from NW.

4.2.2 Land Use:

The proposed land is duly converted for residential purposes. However, the

internal land use specific to project site is given as under:

TABLE 3: BRIEF DETAILS OF THE PROJECT

Particulars Area Percentage

Total Plot Area 17,975.03 Sq.m.

Ground Coverage 5,401.24 Sq. m. 30.05%

Landscape Area 2,696.25 Sq. m. 15%

Parking Area 8,259 Sq. m. 45.95%

Paved Area 1,618.54 Sq.m. 9.00%

Page 15: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

FIGURE 4: LAND USE BREAK UP OF THE PROJECT SITE

4.2.3 Land Ownership:

The project land has been duly allotted and transferred on the name of Shree

Stambh Colonizers,Udaipur vide letter number N.Vi.

Pr/BHu.Ru/Niyaman/09/1461 dated 13.11.2009.

4.3 TOPOGRAPHY (ALONG WITH MAP):

The general topography of the site is slightly undulating. The highest elevation is

589.18 m whereas lowest is 582.48 m. The slope is tending towards SE from NW.

4.4 EXISTING LAND- USE PATTERN (AGRICULTURE, NON-

AGRICULTURE, FOREST, WATER BODIES (INCLUDING AREA

UNDER CRZ), SHORTEST DISTANCES FROM THE PERIPHERY OF

THE PROJECT TO PERIPHERY OF THE FORESTS, NATIONAL PARK,

WILD LIFE SANCTUARY, ECO SENSITIVE AREAS, WATER BODIES

(DISTANCE FROM THE HFL OF THE RIVER),CRZ. IN CASE OF

NOTIFIED INDUSTRIAL AREA, A COPY OF THE GAZETTE

NOTIFICATION SHOULD BE GIVEN):

Ground

Coverage

30.05%

Landscape

Area

15%

Parking

Area

45.95%

Paved

Area

9.00%

LAND USE DETAILS

Page 16: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

4.4.1 Existing Land Use Pattern:

The project is an existing project hence the existing and proposed land use pattern

are same. The same has been given at point no 4.2.2.

4.4.2 Various Distances:

The distance of the project from forest, national parks, wild life sanctuaries, eco

sensitive areas and water body is given in the following table:

TABLE 4: DISTANCE OF THE PROJECT SITE FROM SENSITIVE AREAS

NAME DISTANCE (AERIAL*) DIRECTION*

FORESTS

Ekling Garh Machhala RF 1.03 Km N

Banki Ka Magra RF 2.5 Km W

ARNIA Magra RF 6.6 Km SW

Hora RF 4.3Km E

Sajjan Garh RF 7.0 Km NW

WATER BODIES

Goverdhan Sagar Lake 0.25 Km W

Pichola Lake 1.7 Km NW

Fateh Sagar Lake 5.2 Km NNW

Bari Ka Talab 9.5 Km NW

Ahar Nadi 5.2 Km NE

Uday Sagar Lake 12.8 Km NE

Kotra Nadi 4.7 Km W

Amarlok Nadi 5.3 Km NW

*Aerial distance and directions taken from Google earth.

4.5 EXISTING INFRASTRUCTURE:

Nearest Railway Station: 2.72 Km NNE

Nearest Airport: Maharana Pratap Airport 21.87; NE

Page 17: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

Nearest Road Infrastructure: As mentioned in table 2.

4.6 SOIL CLASSIFICATION:

Most of the soil of Udaipur district has developed in situ. It varies from clay loam

to heavy clay. Girwa district has heavy clay type soil.

4.7 CLIMATIC DATA FROM SECONDARY SOURCES:

The climate of the district is dry except SW monsoon season. The cold season is

from December to February and is followed by summer from March to June.

Period from mid of September to end of November constitutes post monsoon

season. The droughts are in general of mild or normal type. However, severe type

of droughts has been recorded at Udaipur, Gogunda, Kherwara, Jharol, Kotra and

Vallabhnagar. Very severe type of drought has been recorded in the year 1987 at

Kotra.

Average annual rainfall of the district is 637.0mm. However normal rainfall for

the period 1901 to 1970 is 633.50mm. The southern part of the district receives

slightly more rainfall.

4.8 SOCIAL INFRASTRUCTURE AVAILABLE:

The site is within the city limits. All the basic infrastructure facility is available

nearby. The list of the same is tabulated in the following table.

TABLE 5: INFRASTRUCTURE FACILITIES

Particulars Distance

in KM

Direction

Education Facilities

Springdale’s School 0.7 S

Dream India School 0.4 NE

Alok Sr. Secondary School 1.3 NE

Euro Kids 1.4 NE

National Institute of Fire Engineering & Safety

Management 1.3

NE

Hospitals

Page 18: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

Rajasthan Hospital & Research Centre 0.5 SE

Jeevan Jyoti Hospital 3.06 NE

Jivnata Children Hospital 3.6 NE

Aravali Hospital 4.7 NW

ASG Eye Hospital 5.6 N

Worship places

Maszid E Gousia 1.9 E

Bohra Ganeshji Temple 6.3 NE

Jain Swetamber Temple 5.4 NE

Shri Mansapuran Karni Mata Temple 2.3 N

Jagdish Temple 3.9 NW

**********

Page 19: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

5. PLANNING BRIEF

5.1 PLANNING CONCEPT (TYPE OF INDUSTRIES, FACILITIES, AND

TRANSPORTATION ETC.) TOWN AND COUNTRY PLANNING/

DEVELOPMENT AUTHORITY CLASSIFICATION:

The project is an existing project and in the purview of UIT, Udaipur. The project

is a residential project with total plot area: 17,975.03 Sq.m and built up area of

42,090.74 Sq.m. There are total 304 nos of flats.

5.2 POPULATION PROJECTION:

The project is an existing project. Total number of population in the project

premises at 100% occupancy will be 1488 nos with approximately 220 nos of

anticipated visitors. The club house, commercial area and staff population will

add approximately 300 nos to the total population.

As per Census of India “2011” population of the immediate nearby villages is

with 623531 households. The requirement of approx 50 workers for the project is

being met through the recruitment of local workers.

5.3 LAND USE PLANNING (BREAKUP ALONG WITH GREEN BELT

ETC.):

The project is an existing project. The proposed and existing land use is same.

The same is elaborated at Table no 3 and Figure no 4.

5.4 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL &

SOCIAL):

On the basis of the preliminary site visit, the infrastructure demand in the villages

will be assessed on the basis of need and priority. Job opportunities are limited

and newer avenues of skill development for income generation are required. The

Page 20: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

assessment will be identified in the socio economic survey, after the grant of TOR

and will be submitted at the time of final presentation regarding EC.

5.5 AMENITIES/ FACILITIES:

The project has 304 nos of flats; Common garden area, Commercial Area: 182.74

Sq.m. and Club House Area- 897.53 Sq.m.

**********

Page 21: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

6. PROPOSED INFRASTURECTURE

6.1 INDUSTRIAL AREA (PROCESSING AREA):

None. Project is a residential project. No industrial area is proposed.

6.2 RESIDENTIAL AREA (NON PROCESSING AREA):

No additional residential area is proposed. The existing area comprises of total

304 no of flats (1,2 and 3 BHK)

6.3 GREEN BELT:

No additional green belt is proposed. The existing area is 15% of the total plot

area i.e.2,696.25 Sq. m.

6.4 SOCIAL INFRASTRUCTURE:

The promoter may commit for health and medical development facilities like

medical van cum ambulance with certified doctor after details social survey.

6.5 CONNECTIVITY (TRAFFIC AND TRANSPORTATION ROAD/ RAIL/

METRO/ WATER WAYS ETC.):

None. Project is a residential project and basic road facilities are well developed

in the area.

6.6 DRINKING WATER MANAGEMENT (SOURCE & SUPPLY OF

WATER):

The total water demand of the project is 168 KLD inclusive 136 KLD fresh water

demand and 32 KLD recycled water demand. The fresh water demand is being

met by 3 existing bore wells whereas the recycled water after treatment in STP.

Page 22: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

FIGURE 5: WATER BALANCE CHART

Total water Demand

168 KLD

Fresh water

136 KLD

Recycled water

32 KLD

Commercial

(4 KLD)

Flats

(128 KLD)

Staff &Visitors

(4 KLD)

Landscaping

(14 KLD)

S

T

P

108 KLD

Waste water

Capacity

120 KLD

Re

use

fo

r flu

sh

ing

, L

an

dsca

pin

g &

Ge

ne

ral w

ash

ing

8 KLD

Sludge & Evaporation

108 KLD

Filter Backwash

(8 KLD)

General

Washing

(10 KLD)

3KLD3 KLD102 KLD

32 KLD

68 KLD

Will be discharged in nearby

Nalla

6.7 SEWERAGE SYSTEM:

Total waste water generation at 100% occupancy of the project will be 108 KLD.

The waste water is being treated in the STP with capacity 120 KLD based on

MBBR technology.

6.8 INDUSTRIAL WASTE MANAGEMENT:

Not applicable.

6.9 SOLID WASTE MANAGEMENT:

Approximately 600 kg/day solid waste will be generated by the project at 100%

occupancy. The waste is being collected in dustbin and finally being disposed off

to municipal vendors.

**********

Page 23: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

7. REHABILITATION AND RESETTLEMENT (R&R) PLAN

7.1 POLICY TO BE ADOPTED (CENTRAL/STATE) IN RESPECT OF THE

PROJECT AFFECTED PERSONS INCLUDING HOME OUSTEES, LAND

OUSTEES AND LANDLESS LABORERS (A BRIEF OUTLINE TO BE

GIVEN):

R & R is not applicable.

**********

Page 24: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

8. PROJECT SCHEDULE & COST ESTIMATES

8.1 LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE

OF COMPLETION (TIME SCHEDULE FOR THE PROJECT TO BE

GIVEN):

The project is an existing project.

8.2 ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS

OF ECONOMIC VIABILITY OF THE PROJECT

The total project cost of the project is Rs 85.38 Cr.

**********

Page 25: PRE FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/27...SOLID) AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL ..... 8 3.10 AVAILABILITY SCHEMATIC REPRESENTATIONS

Project Name: Lake Gardens (Violation Case) PFR

Promoter: Shree Stambh Colonizers

9. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)

9.1 FINANCIAL AND SOCIAL BENEFITS WITH SPECIAL EMPHASIS ON

THE BENEFIT TO THE LOCAL PEOPLE INCLUDING TRIBAL

POPULATION, IF ANY, IN THE AREA:

**********