PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
PRE- FEASIBILITY
REPORT
PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
EXECUTIVE SUMMARY
1.1 Introduction
The proposed mining lease of 19.80ha in survey no. 345 was granted to
M/s. Rock Sand Minerals Pvt Ltd, for a period of 15 years by Asst.
Director of Mines and Geology, Hyderabad.
The mining lease is located in survey no. 345 in Girmapur Village,
Medchal Mandal, Ranga Reddy district, Telangana.
1.2 Salient features of the project
Environmental setting
Project name Proposed Stone & Metal Mine
Of M/s. Rock Sand Minerals Pvt Ltd
Mining Lease Area 19.80 ha.
Location of mine Girimapur Village,
Medchal Mandal,
Ranga Reddy district,
Telangana.
Latitude 17 0 36' 06'' N
Longitude 780 02' 51'' E
Toposheet number 57 K/16
Minerals of mine Stone & Metal Mining
Proposed production of mine 9,00,000 TPA
Method of mining Opencast semi mechanized mining
Drilling/Blasting No blasting is proposed. Line Drilling and
offset cutting is proposed
No of working days 300 days
Water demand 7.0 KLD
Sources of water Water will be supplied from bore wells of the
nearby area
Man power 30
Solid Waste No waste is generated
Nearest railway station Shankarpalli Railway station- 13.8 km
Nearest airport RGIA Airport – 42.3 km
PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
Proposed planning
Mining method - Open Cast - Semi mechanized
Project cost - Rs. 70 lakh
Production - 9,00,000 TPA
2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION
2.1 Identification of Project and Project Proponent
The project is proposed by M/s. Rocksand Minerals Pvt Ltd. The lease
documents of mine are attached as Annexure II. The details of the
project are given below:
Name of the applicant M/s. Rocksand Minerals Pvt Ltd.
Name & Address of
Applicant
Sri. P. Purnachand
Joint partner
# 203, Vijaya Enclave,
Plot No. 32, Srinagar Colony,
Hyderabad – 500073
Mineral Stone & Metal
Area (ha) 19.80 HA
Postal Address Sri. P. Purnachand
Joint partner
# 203, Vijaya Enclave,
Plot No. 32, Srinagar Colony,
Hyderabad – 500073
Status of Mine Fresh application for Environmental Clearance
PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
2.2 Brief Information about the Project
The mining lease area of 19.80 ha is located in Government land, near
Girimapur Village, Medchal Mandal, Ranga Reddy district, Telangana.
It has been proposed to produce approximately 9,00,000 TPA of Stone
& Metal.
Mining:
The mining operations are proposed to be carried out by opencast
semi-mechanized method. Stone & Metal is exposed on the surface.
2.3 Need for the Project and Its Importance to the Country or Region
In the context of depleting natural sand resources in many parts of
the world due to sterilisation of reserves and environmental concerns,
concrete producers, construction engineers, builders and suppliers of
sand are of the firm view that crushed stone sand is a substitute to
natural river sand.
2.4 Demands-Supply Gap
The use of the crushed stone sand although not new was at one time
negligible as the natural river sand was abundantly available. But now
the situation has changed. The quantum of fine aggregate available is
same but the requirement of natural sand increased several hundreds
of times since 1970. The government and the construction industry
feels that to meet the ever increasing demand for the fine aggregate
there is no other alternative except going for crushed stone sand.
Crushed stone, one of the most accessible natural resources, is a major
basic raw material used for construction. For centuries crushed stone
coarse aggregates were being used for the production of various types of
concrete in construction.
PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
2.6 Employment Generation
Proposed mining is semi-mechanized method and this project operation
will provide livelihood to the 30 workers. It will provide employment to
the people residing in vicinity.
3.0 PROJECT DESCRIPTION
3.1 Type of Project Including Interlinked and Interdependent Projects,
If Any.
The proposed Stone & Metal mine is of 19.80 ha. No interlinked
projects were associated with this project.
3.2 Location
The mining lease area is located in Survey No. 345 of Girimapur
Village, Medchal Mandal, Ranga Reddy district, Telangana. The
mining lease area falls in Survey of India
Toposheet No. : 56 K/2
Latitude : 17 0 36' 06'' N
Longitude : 780 02' 13.6'' E
Location of the mining lease in Ranga Reddy District is shown in Fig –
1.
Topo Map Showing 10 km Radius of Mine lease area is Enclosed as
Annexure – I.
PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
FIG – 1
LOCATION MAP
PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
3.3 Details of Alternate Sites
No alternate site was considered as the project is mineral specific and
site specific.
3.4 Size or magnitude of operation
The proposed mine has lease over an area of 19.80 ha and the
production rate is 9,00,000 TPA.
3.5 Geology and Reserves
3.5.1 Regional Geology
The quarry lease area constitutes a part of Granite and Granitic Gneissic
terrain of Archean age. Pink and Grey Coloured Granites, Pink Alkali -
Feldspar Granites are the important litho units in the area. Grano –
Diorites with basic enclaves of Supra - Crystals like Horneblende Schists,
Biotite Schists also occupy the area. These rock types are exhibiting
various landforms like Domes, Inselbergs, Castle - Koppies, Whalebacks
and Linear Ridges.
Pink Alkali Feldspar is the most dominant rock type in the area with
variations in grain size, scattered outcrops of Migmatites containing
Neosomes of medium to Coarse - Grained Grey Alkali Feldspar Granites
occurs at many places. A number of Quartz, Grey and Pink Pegmatites
and Epidote Veins Criss crossing the host rock. Basic dykes of Dolerite,
Gabbro & Pyroxenitic Composition traverse the granites in NW-SE, NNW-
SSE, E-W & NE-SW directions. Thin veneer of alluvium is found limited
to streams.
3.5.2 Local Geology
Entire quarry lease area is covered with colour granite which is rising up
to 25M above ground level trending E-W, the strike length of the
formation measured 500M in the area with an average width of 175M
PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
BRIEF DESCRIPTION OF LITHO UNITS:
a) Texture and Grain size : Texturally the rock in the lease area is
Porphyritic Texture with fine to medium grained.
b) Colour and aesthetic beauty of the stone: The rock is light black with
green shade. The rock is aesthetically good looking.
c) Hardness :Mohr’s Scale : 6 – 7
d) Mineralogical composition :
The main litho unit is Dolerite Mineralogical the Black Granite
consists of Pyroxene and Plagioclase feldspar as essential mineral and
other mafic Biotite, Mica, hornblende, etc., as accessory mineral with
fine to medium grain. The mafic minerals are observed in more
content hence the rock is melaocratic. The Granite available in the
demarcated area is useful for Granite Cutting and polishing purpose.
e) Density /specific gravity: 2.776 g/cm3
f) Water absorption capacity: 0.138 % (kg/cm2)
g) Porosity: 0.36
h) Compression strength: 687kg/cm2 (in dry state)
i) Abrasiveness: 6 - 7
j) Permeability: Negligible
k) Rock Quality designation: The Rock Quality designation is
estimated to be good with RQD % between 84 and 95.
l) Young modulus of elasticity : 7 725 (105 kg/ cm2)
m) Degree of weathering under Hand lenses/Microscope: Fresh rock
surface is un-weathered and it is categorized as Grade 'A'.
n) Glossiness: The rock takes good polishing.
The Granite available in the demarcated area is useful for
Granite Cutting and Polishing purpose.
3.6 PROJECT DESCRIPTION WITH PROCESS DETAILS
3.6.1 Method of Mining
Mining will be carried out by opencast semi mechanized mining
method. Overburden will be (weathered rock portion) is removed by
line drilling.
PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
Drilling will be done with compressors and jack hammers. Excavators,
cranes, chain-pulley blocks and winch will be used for dislodging
lifting and loading the blocks.
The dislodged blocks from the sheet rock will be dressed by chisel
men to the maximum possible size and then loaded by cranes or
chain-pulley block or winch into the trucks for dispatch to the
destination.
The following machinery is being deployed in the leasehold area to
carry out the mining operations:
Mining Machinery
S.
No.
Machinery No.s
1. Excavator (Tata Hitachi 45 Lc) 2
2 Tipper (Leyland 17 tonnes)
3
3. Compressors (CFM-50) 1
4. Jack Hammers 4
Minor tools : Chisels, crowbars, pick of axes spades and hammers of
different sizes.
3.7 Raw Material Required Along With Estimated Quantity, Likely
Source, Marketing Area of Final Product/S, Mode of Transport of
Raw Material and Finished Product
No raw material will be required in the proposed project. The
operation involves the extraction of black granite and dumping in
stock yard. The dressed dimensional granite will be transported
through hired trucks to the granite market or sea port.
PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
3.7.1 Use of Mineral
The government and the construction industry feels that to meet the
ever increasing demand for the fine aggregate there is no other
alternative except going for crushed stone sand.
Crushed stone, one of the most accessible natural resources, is a major
basic raw material used for construction. For centuries crushed stone
coarse aggregates were being used for the production of various types of
concrete in construction.
3.7.2 Processing
Processing of Rock Sand is not involved
3.8 Resource Optimization/ Recycling and Reuse
Not envisaged.
3.9 Availability of Water Its Source, Energy/ Power Requirement and
Source
Water Requirement
Description Quantity (KLD)
Dust suppression 3.0
Green Belt 2.0
Domestic 2.0
Total water required 7.0
PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
3.10 QUANTITY OF WASTES TO BE GENERATED (LIQUID AND SOLID)
AND SCHEME FOR THEIR MANAGEMENT/ DISPOSAL
3.10.1 Solid Waste Generation & its Disposal
The solid waste generated is minimal
3.10.2 Liquid Effluent
No liquid effluent will be generated at the mine site. The domestic
wastewater generated will be sent to septic tanks followed by soak
pits.
PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
3.11 SCHEMATIC REPRESENTATIONS OF THE FEASIBILITY DRAWING
WHICH GIVEN INFORMATION OF EIA PURPOSE
Form-I, Pre-feasibility project report with
proposed TOR to MoEF (EAC)
TOR approved by EAC
Draft EIA report to SPCB
by project proponent
Public consultation
process by SPCB
Proceedings of public
consultation
Appraisal and
recommendation by EAC
Approval by MoEF
Rejected Approved
Display
on the
MoEF
website
TOR rejected by MoEF on the
recommendation of EAC
Summary EIA and Form-I display
on the website by SPCB
Display at Panchayat, ZP, DM/DC/Dy.
Com & on the SPCB website
To proponent for submission of final
EIA report/Supplementary report to
draft EIA
Referred back to EAC under
communication to the project
proponent
Display on MoEF website & project
proponent website
Post EC monitoring Submission of half
yearly compliance
report to MoEF/RO-
MoEF
Display of
compliance report on
MoEF website
Project Concept and Site identification
PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
4. SITE ANALYSIS
4.1 Connectivity
4.1.1 Nearest Railway Station
Shankarpalli railway station at a distance of 21 km from the project
site
4.1.2 Nearest Airport
RGI Airport is the nearest airport at 56 km.
4.2 LANDFORM, LANDUSE AND LAND OWNERSHIP
The mining lease is located in Government Land and the entire area is
barren with granite exposures.
4.3 Topography
The area is located on Topo sheet No.57 K/16 in Survey of India and
falls on Latitude13°05'40.1" and Longitude 78° 50'13.6". The Lease
area is a mound. The area is devoid of any forest or tree cover. It
comprises shrubs only. There are no prominent natural drainage
channels in the area. In general the area is plain studded with
isolating hillocks. Sometimes they may raise gently as continuous
hills, presenting a rugged topography..
4.4 Climatic data from secondary sources
The highest temperature of 41° C is recorded in the area during the
month of May and the lowest temperature of 18° C is recorded. The
aridity is characterized by low annual precipitation of 600mm.
PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
5.0 PLANNING BRIEF
5.1 Planning Concept
It is proposed to produce 9,00,000 TPA of Stone & Metal from the
proposed mining lease.
5.2 Population projection
The project will employ mostly workers from nearby villages. There will
not be any increase in population due to the project.
5.3 Land use planning
The project is located in 19.80 ha of Government land. There will be
change in land use as the granite will be excavated and pits will be
formed to a depth of 7 m. during the life of the mine.
5.4 Assessment of Infrastructure Demand (Physical & Social)
On the basis of the preliminary site visit, the infrastructure demand in
the villages was assessed on the basis of need and priority.
5.5 Amenities/Facilities
Site Services like office cum rest shelter is already constructed over an
area of 90 m2.
6.0 PROPOSED INFRASTRUCTURE
6.1 Industrial Area (Processing Area)
No infrastructure is proposed.
PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
6.2 Residential Area (Non Processing Area)
As the local persons will be given employment, no residential area/
housing is proposed within the mining lease area.
6.3 Green Belt
Green belt will be developed along the boundaries of mine lease area.
6.4 Water Management
Description Quantity (KLD)
Dust suppression 3.0
Green Belt 2.0
Domestic 2.0
Total water required 7.0
6.5 Sewerage System
The domestic wastewater generated will be sent to septic tanks
followed by soak pits.
6.6 Industrial Waste Management
Not applicable.
6.7 Solid Waste management
About 88% of the material from granite production is going to be
generated as solid waste.
The waste will be dumped temporarily in the 7.5 m barrier zone all
along the mining lease area and will be backfilled into the minedout
pit at the end of the mining.
PROJECT: Rock Snad Mining Project PRE-FEASIBILITY REPORT APPLICANT: M/s. Rock Sand & Minerals Pvt Ltd
7 REHABILITATION AND RESETTLEMENT (R&R) PLAN
Not Applicable.
8 PROJECT SCHEDULE & COST ESTIMATES
The Total cost of project would be around Rs. 70 lakhs.
9.0 ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
9.1 Financial and Social Benefits with Special Emphasis on the
Benefit to the Local People Including Tribal Population, If Any, In
the Area.
Although granite is a minor mineral, it is a major contributor in
foreign exchange earnings. India is the second largest exporter of raw
granite after China and ahead of Brazil and South Africa.
This project will also provide employment to local people helping them
earn livelihood.
***********