PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI UNDER EIA NOTIFICATION 2006 PRE-FEASIBILITY REPORT (Under the Guidelines of Ministry of Environment and Forest in terms of the provisions of EIA notification 2006 and specifically in circular No J-11013/41/2006-IA.II (I) dated 30 th December, 2010) Minor Mineral – Rough stone Mining Project – Category “B2” Lease Area – 4.00.0Ha (less than 5Ha) S.F.No. – 629 Part-1 Village – Nagamangalam Taluk – Denkanikottai District – Krishnagiri State – Tamilnadu PROJECT PROPONENT Faldu Chimanlal Mohanbhai, S/o. Mohanbhai, Door No.2/198C, Varaganapalli Village, Nagamangalam Post, Denkanikottai Taluk, Krishnagiri District - 635113

Upload: others

Post on 20-Mar-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

PRE-FEASIBILITY REPORT

(Under the Guidelines of Ministry of Environment and Forest in terms of the provisions of

EIA notification 2006 and specifically in circular No J-11013/41/2006-IA.II (I) dated 30th December, 2010)

Minor Mineral – Rough stone

Mining Project – Category “B2”

Lease Area – 4.00.0Ha (less than 5Ha)

S.F.No. – 629 Part-1

Village – Nagamangalam

Taluk – Denkanikottai

District – Krishnagiri

State – Tamilnadu

PROJECT PROPONENT

Faldu Chimanlal Mohanbhai,

S/o. Mohanbhai,

Door No.2/198C, Varaganapalli Village,

Nagamangalam Post,

Denkanikottai Taluk,

Krishnagiri District - 635113

Page 2: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

1. EXECUTIVE SUMMERY

Faldu Chimanlal Mohanbhai has been obtained permission from District collector

Krishnagiri to quarry Rough stone for over an extent of 4.00.0Ha in Survey No: 629

Part-1 at Nagamangalam Village, Denkanikottai Taluk, Krishnagiri District and

Tamilnadu state by District Collector Krishnagiri, Rc.No: 82/2012 (Mines – 2) Dated:

15.04.2015, for a period of Ten years subjected to submission of Environmental

clearance from MoEF / SEIAA, consent for Establishment and Consent for operation

from TNPCB.

SALIENT FEATURES OF THE PROJECT

S.NO PARTICULAR DETAILS

1. Name of the Proponent Faldu Chimanlal Mohanbhai

2. Type of Project Rough stone

3. Location Survey No. 629 Part-1

Nagamangalam Village,

Denkanikottai Taluk,

Krishnagiri District,

Tamilnadu State.

4. Mining lease area 4.00.0Ha

5. Type of land

Patta/forest/PWD

It is a Government land (Hilly terrain) the applicant

has obtained tender from the Government - Non

forest

6. Precise area communication

approved by the District

collector

The Precise area communication letter was issued by

the District Collector, Krishnagiri District vide

Rc.No: 82/2012 (Mines – 2) Dated: 15.04.2015.

7. Mining plan approved by the

Deputy/Assistant Director of

the District

The mining plan was approved by the Deputy

Director, Department of Geology and Mining,

Krishnagiri vide Rc.No: 82/2012/Mines – 2 Dated:

22.04.2015.

8. Life of period Life of the quarry is Ten years only.

9. Latitude 12034’15’’ N to 12

034’26’’ N

10. Longitude 77054’48’’ E to 77

054’53’’ E

11. Topo sheet No. 57 H/14

12. Topography of MSL area 830m from MSL

13. Method of Mining The quarrying operation will be carried out by Semi

Mechanized Opencast Method in conjunction with

conventional method of mining using Jack hammer

Page 3: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

drilling and blasting, hydraulic excavators are used

for loading the Rough stone from pithead to the

needy crushers.

14 Ultimate depth of Mining Proposed depth of mining is 60m (40m above the

ground level + 20m below the ground level) for a

period of Ten years.

15. Production capacity The proposed quantity of reserves is 851195m3 (or)

150388 Lorry Loads of Rough stone up to a depth

for 60m (40m above the ground level + 20m below

the ground level) for a period of Ten years.

Description Rough stone

in m3

Geological Resources 1716275

Available Mineable reserves 851195

Ten years plan period

As in the approved mining plan 851195

16. Overburden/Waste There is no overburden anticipated. The area has

been quarrying operation earlier. The entire quarried

out Rough stone will be sold to needy crushing units

hence wastage is not anticipated.

17. Land use classification It is a New Proposal Rough stone quarry project in

Nagamangalam village.

18. Ground water level The Ground water occurrence in this area is 45mt

depth from general ground profile (45m in summer

and at 40m in rainy season)

19. Climatic condition Rainfall – 850/annum

Temperature - 42ºC - 23ºC

20. Land use pattern

Description Present

area in

Ha,

Area at the end of

the lease period

Ha

Area under quarrying Nil 3.13.6

Infrastructure Nil 0.01.0

Roads Nil 0.01.0

Green belt Nil 0.28.0

Unutilized 4.00.0 0.56.4

Grand total 4.00.0 4.00.0

21. Nearest habitation Periyanagaithunai - 2.0km – South western side

22. Nearest Town Denkanikottai -14km – South western side

23. Nearest Railway station Periyanagaithunai Railway station - 1km – South

western side

24. Nearest Airport Bangalore Airport - 74km – North western side

Page 4: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

25. Nearest National Highways &

State Highways

NH 7 – Salem - Bangalore - 13km - North western

side.

SH85 – Rayakotttai – Attipalle – 1km - Southern

side

26. Nearest Hospital Periyanagaithunai - 2.0km – South western side

27. Aerial distance to the nearest

Eco sensitive areas, CRZ,

forest, wild life sanctuary,

Interstate boundary, critically

polluted area if the quarry site

is within 500m of these areas.

More than 500m from Eco sensitive areas, CRZ,

forest, wild life sanctuary, Interstate boundary,

critically polluted area.

28. Details of other quarries for a

radius of 500m around the

quarry site

There are few other quarries within 1km radius from

the periphery of the quarry site.

29. Man power About 16 employees

30. Water requirement & source Total water requirement for 1.0KLD

Purpose Quantity

KLD

Source

Drinking 0.3KLD Water vendors

Domestic purpose 0.3KLD Bore wells

Dust suppression

and Afforestation

0.4KLD Bore wells

31. Cost of the project The Project cost:

A. Fixed asset cost = Rs. 37,90,000/-

B. Operational cost = Rs. 1,03,00,000/-

C. EMP cost = Rs. 7,60,000/-

Total project cost = Rs. 1,48,50,000/-

The Prefeasibility report preparing for following condition of Government of India Ministry of Environment

and Forests (No.L-11011/47/2011 –IA-II (M) Dated: 24th June, 2013) Udedurgam reserved forest is situated 5km away from the South Eastern side of the area.

The Western Ghats region is situated 4km away from the Southern side of the area.

Laxmi Goundan tank is situated within the radius of 4km away from the south eastern side

There is no interstate boundary within 15km radius.

There is no CRZ within the radius of 15km.

The project area does not fall in ‘HACA’ region.

There are no Bird sanctuaries, wild life sanctuary or National parks as per Wild life protection

Act 1972, within the radius of 15kms. Locality

There are few other quarries situated within 1km radius.

Page 5: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

The following information provided by the applicant I have applied for Environmental Clearance to SEIAA, Tamilnadu for quarry lease for quarrying

of Rough stone over an extent of 4.00.0Ha in S.F.No: 629 Part-1 at Nagamangalam Village,

Denkanikottai Taluk and Krishnagiri District.

I will not deploy any child labors below 18 years for any type of quarrying operation. All labours

engaged for quarrying operation will be insured till the end of life of quarry period.

I will sincerely follow and execute the Afforestation and Green belt during the course of

quarrying operation and maintain Afforestation after the expiry of quarrying lease.

All type of safety / protective equipment’s will be provided to all the labourers working in my

quarry site.

The quarry operation has not been commenced and will likely to operate after grant of

environmental clearance and grant of quarry lease.

I ensure to involve and participate in the corporate social responsibilities of the local community

as declared in the report.

I solemnly declare & affirm that there are following quarries within 1km radius from the

periphery of the quarry site.

S.No. Name of the owner Lease Granted

area.

Extent in

Ha

Lease

period

Lease Status Name of

the

Mineral

1. Tvl. Global Trading

Company, 53rd

Floor, Rosy

Tower, 7,

Nungambbakkam High

road, Chennai-34

Denkanikottai

Taluk,

Nagamangalam

S.F.No. 629(P)

2.02.5 1995-

2005

(Operated

under court

order)

Multi

color

Granite

2. Tvl. Indira Granites, No.7,

Cause way road, Lakshmi

Mansion, Gugai, Salem-

636006

Denkanikottai

Taluk,

Nagamangalam

S.F.No. 629(P)

0.81.0 1995-

2005

(Operated

under court

order)

Multi

color

Granite

3. Thiru.M.D.Anandam,

No.73,Gowdiyamutt

road,Rayapettai, Chennai-

14

Denkanikottai

Taluk,

Nagamangalam

S.F.No. 629(P)

0.81.0 1996-

2006

(Operated

under court

order)

Multi

color

Granite

4. J.Premalatha,

Tvl.R.V.Granites,

77A,Ramnagar,Rani

Illam,Kumarasamypettai,

Salem-636007

Denkanikottai

Taluk,

Nagamangalam

S.F.No. 629(P)

0.81.0 1995-

2005

(Operated

under court

order)

Multi

color

Granite

5. A.Rajamani,

Tvl.Mahalakshmi

Enterprises, 7, 1st

Street,

North Gopalapuram,

Chennai-86

Denkanikottai

Taluk,

Nagamangalam

S.F.No. 629(P)

2.02.5 1995-

2005

(Operated

under court

order)

Multi

color

Granite

Page 6: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

6. Rani Granites,

33, 1st

Pulikuthi Street,

Gugai, Salem

Denkanikottai

Taluk,

Nagamangalam

S.F.No. 629(P)

4.05.0 1993-

2003

(Operated

under court

order)

Multi

color

Granite

7. Jayendira Kumar, Bavan

Bai Patel, 2/198B,

Varganapalli,

Nagamangalam post,

Denkanikottai Taluk,

Denkanikottai

Taluk,

Nagamangalam

S.F.No. 1249(P)

5.00.0 2008-

2018

Operating Rough

stone

8. Thiru. K.Amrish,

Krishnappa 2-56,

Varaganapalli Village,

Nagamangalam post,

Denkanikottai Taluk

Denkanikottai

Taluk,

Nagamangalam

S.F.No. 629(P-II)

4.00.0 Ten

years

Proposed Rough

stone

9. Thiru. Faldu Chinmanlal,

Mohanbhai, S/o

Mohanbhai, Door No.

2/198C, Varaganapalli

Village, Nagamangalam

post, Denkanikottai Taluk,

Krishnagiri District.

Denkanikottai

Taluk,

Nagamangalam

S.F.No. 629(P-I)

4.00.0 Ten

years

Instant

proposed

Rough

stone

Total 23.53.0Ha

Besides I wish to state that the approach road belong to me only and no other patta roads are

encountered.

No habitations/Village is located within 500 meters radius from the periphery of my quarry.

The quarrying operation will not cause any hindrance to the nearby public and also it will not

cause any hindrance to nearby villagers and human settlements during transportation of mineral.

I wish to state there is no protected areas notified within the radius of 10km from the proposed

quarry site under the wildlife (Protection) Act 1972.

No critically polluted areas as identified within the radius of 10km from the quarry site by CPCB

constituted under water (Presentation and control of pollution) Act, 1974.

No Eco sensitive areas as identified within the radius of 10km from the proposed quarry site.

There is no Interstate and international boundary within 5km radius from the boundary of the

quarry site.

Page 7: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

2.0 INTRODUCTION OF THE PROJECT OR BACKGROUND INFORMATION

(i) Identification of project and project proponent: In case of mining project, a copy of mining

lease/letter of intent should be given

Identification of Project

Name of the Project Nagamangalam Rough stone Quarry

Lease area 4.00.0Ha (Government land)-Non forest

Location Survey No.629 Part-1 at Nagamangalam Village, Denkanikottai

Taluk, Krishnagiri District, Tamilnadu State.

Background information of the Project

Nagamangalam Rough stone quarry of Faldu Chimanlal Mohanbhai has applied for

Mining lease for over an area of 4.00.0Ha in the Survey No. 629 Part-1 at Nagamangalam

Village, Denkanikottai Taluk and Krishnagiri District. The area falls in GSI Topo sheet No. 57

H/14. The lease applied area is Government land the applicant has obtain tender from the

Government. The lease applied area exhibits hilly terrain topography.

Project Proponent Name with Address

Faldu Chimanlal Mohanbhai,

S/o. Mohanbhai,

Door No.2/198C, Varaganapalli Village,

Nagamangalam Post,

Denkanikottai Taluk,

Krishnagiri District - 635113

Mobile No: 9444895079

E-mail id: [email protected]

In case of mining project, a copy of mining lease/letter of intent should be given

I. The precise area communication letter was issued by the District Collector, Krishnagiri

passed an order vide Rc.No: 82/2012 (Mines – 2) Dated: 15.04.2015.

II. The mining plan was approved by the Deputy Director, Department of Geology and

Mining Krishnagiri vide Rc.No: 82/2012/Mines – 2 Dated: 22.04.2015

Page 8: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

(ii) Brief description of nature of the project

The Rough stone quarrying operation is proposed to carry out by conventional opencast

Semi mechanized method by formation of benches. Twelve benches are proposed with a height

of 5mts on Rough stone. The width of each bench is proposed not less than the height. The

quarry operation involves jackhammer drilling; Slurry blasting and excavators are used for

loading of Rough stone to needy crushers.

The proposed quantity of reserves is about 851195m3 of Rough stone for a period of Ten

years, there is no overburden anticipated. The area has been quarrying operation earlier. The

entire quarried out Rough stone will be sold to needy crushing units hence wastages is not

anticipated. The quarry operation is proposed up to depth for 60m (40m above the ground level +

20m below the ground level) for a period of Ten years.

(iii) Need for the project and its importance to the country and or region

The Rough stone is important building material to our country and Region, it’s a vital

material for construction industries and the Rough stone quarrying project falls in the area of

Krishnagiri District, where plenty of Road widening projects are been carried Salem - Bangalore

(NH - 7), Rayakottai - Attipalle (SH–85) is being under massive development hence a lot of

Rough stone is required for Granular sub base (GSB) and also for the culverts and bridges.

Besides catering domestic construction project.

Other infrastructure projects like building, Bridges are also under progress hence there is

a huge demand of Rough stone for public sector companies and local private sector projects.

The earning source in the targeted area is limited, most of the people in and around the

area depend upon the seasonal agriculture, much of the people migrate to nearby towns where

good, and industries and factories are growing up. Through this project will give employment

opportunities to 16 employees directly and 6 people indirectly.

Mineral Industries of the state of Tamil Nadu provides employment opportunities for the

people of the state as well as in the specific project area. The Quarrying is one among the major

core sector for industries, which plays a vital process of country’s economic development.

(iv) Demand and supply gap

There is a huge demand of Rough stone in Krishnagiri District as many National Road

projects (NH-7) connecting Salem - Bangalore is under massive development for its widening

and strengthening operation apart from this many bridges and fly overs are also being under

Page 9: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

construction. There is a huge demand of Rough stone for infrastructure development of the state;

hence the project is significant to the state.

The Railway line from Kelamangalam - Periyanagai is also under progress where huge

Rough stone is required as Ballast. Other internal panchayat Roads, State Highway roads and

Major District Roads are also under progress, besides all these public works projects the Rough

stone is widely used for domestic construction project like Hospital, School, Government

Building and Housing, Construction. It is worth mentioning that the Rough stone of Krishnagiri

District.

(v) Imports vs indigenous production

There is no import of Rough stone at present in India.

(vi) Export Possibility

There are no possibilities for export.

(vii) Domestic/Export Markets

The applicant after obtaining the lease will fetch a domestic market as mentioned earlier.

It is propose to sell Rough stone domestic needy crushers for roads project and other

infrastructure development projects for public and private sector companies.

(viii) Employment Generation (Direct and Indirect) due to the project

It is proposed to deploy about 16 employees directly and 6 persons will be indirectly

Benefited .The tentative man power required for the proposed Rough stone quarry shall be as

follows.

a. Skilled labor

Mines foreman/

Permit Mines Manager - 1

Excavator operator - 2

Co- operator - 2

Jack hammer operator - 6

Blaster/ mate - 1

b. Semi-skilled

Watchman - 1

c. Unskilled - 3

Total - 16

The above man power is adequate to meet out the production schedule and the machinery

strength envisaged in the mining plan and also to comply with the stationary provisions of quarry

safety regulation.

Page 10: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

It is been ensured that the labours will not be deployed less than 18 years, No Child

labours will engaged or entertained for any kind of quarrying operations. All the labours

engaged for quarrying operations will be insured till the end of life of quarry.

3.0 PROJECT DESCRIPTION

(i) Type of project including interlinked and interdependent projects, if any

The Nagamangalam Rough stone quarry; it is an opencast semi mechanized quarry.

There is no interlinked & interdependent project.

(ii) Location (map showing general location, specific location, and project boundary & project

site layout) with coordinates

� The project is proposed for the quarrying of Rough stone at proposed capacity of

851195m3

from the Rough stone quarrying is about 4.00.0Ha in Nagamangalam

Village, Denkanikottai Taluk, and Krishnagiri District.

� The entire quarry lease area falls in the Government land the applicant has obtain

tender from the Government.

� The Altitude of the area is above 830m (Maximum) from MSL.

� The area is mentioned in GSI Topo sheet No. 57 H/14

� The Latitude between of 12°34’15”N to 12o34’26” N

� The Longitude between of 77°54’48” E to 77°54’53’’ E on WGS 1984 datum

Page 11: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

LOCATION MAP OF THE PROJECT AREA WITH CO ORDINATES

PROJECT AREA 12034’15’’ N to 12034’26’’ N

77054’48’’ E to 77

054’53’’ E

Page 12: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

(iii) Details of alternate sites considered and the basis of selecting the proposed site, particularly

the environmental considerations gone into should be highlighted

There is no alternative sites examined, the entire Rough stone will be transported to the

needy crusher. This Rough stone quarry project is site specific.

(iv ) Size or magnitude of operation

The total area of the project is about 4.00.0Ha. It is proposed quantity is 851195m3 of

Rough stone for a period of Ten years. The quarry proposed up to depth of 60m (40m above the

ground level + 20m below the ground level) by conventional open cast semi mechanized

quarrying operation involves jackhammer drilling, slurry explosives blasting, hydraulic

excavator attached with bucket are used for loading the Rough stone from pithead to crushing

site.

(v) Project description with process details (a schematic diagram/flow chart showing the

project layout, components of the project etc. should be given)

The project is mineral for Rough stone and the lease area comprises of 4.00.0Ha of

Government land. The quarrying operation is involved open cast semi mechanized mining with

5.0m vertical bench with a bench width is not a less than the bench height. The quarry operation

involves jackhammer drilling, slurry explosives blasting; Hydraulic excavators are used for

loading of Rough stone to needy crushers. It is proposed quantity is 851195m3 of Rough stone.

The period of quarry is Ten years.

Topography:

The lease applied area exhibits hilly terrain, the massive Rough stone formation is clearly

visible right from surface. The slope is gentle towards south western side. The altitude of the area

is above 830m (Maximum) from MSL.

Regional geology:

The peninsular gneiss forms the oldest rock formations, in which the massive formation

of Charnockite lies over with rich accumulation of recent quaternary formation. On regional

scale the Charnockite body trends N10°E – S10°W with dipping towards SE 40°.

Regional stratigraphic sequence:

AGE FORMATION

Recent – Quaternary weathered formation

------------Unconformity------------

Archaean–Charnockite

Peninsular Gneiss

Page 13: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

Method of Mining:

Open cast-Semi mechanized method with 5.0m vertical bench with a bench width is not a

less than the bench height, the quarry operation involves jack hammer drilling, slurry blasting.

Hydraulic excavators are used for loading of Rough stone to needy crushers.

Machinery Required:

S.No Description Number

1. Tractor mounted compressor attached with

Jackhammer

1

2. Excavator 1

3. Tipper 1

Reserves:

Description Rough stone

in m3

Geological Resources 1716275

Available Mineable reserves 851195

Ten years plan period As in the approved

mining plan 851195

SCHEMATIC DIAGRAM OF THE MINING PROCESS

Mining

Excavation Blasting Drilling

Rough stone

Loading and transportation

to the needy crusher

Page 14: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

(vi) Raw material required along with estimated quantity, likely source, marketing area of final

products, Mode of transport of raw Material and Finished Products

This is a quarrying project for exploiting of Rough stone; hence, there is no requirement

for raw material.

Uses:

The excavated Rough stone will be directly loaded into tipper to the needy crusher.

(vii) Resource optimization/recycling and reuse envisaged in the project, if any, should be

briefly outlined

Water will be accumulated in the excavated quarry out pit area during rainy season.

The water collected in the sump will be used in various purposes at quarry like plantation and

dust suppression etc.

(viii) Availability of water its source, Energy/power requirement and source should be given

This Rough stone quarry project does not require huge water and Electricity for the

project.

Purpose Quantity Sources

Drinking &

Domestic Purpose

0.3KLD Water purchase from Approved water

vendors available in Periyanagaithunai (2Km

– South western side).

Dust suppression 0.3 KLD From Existing Borehole on nearby the

quarry.

Green belt 0.4 KLD From Existing Borehole on nearby the

quarry.

Used only for drinking purpose for

operational workers

Dust Suppression in the Haul Roads to

prevent Dust emission and plantation.

0.3KLD of Drinking water &

Domestic purpose

0.3 KLD for Dust suppression

0.4 KLD for Green belt development

WATER

(1 KLD)

WATER BALANCE CHART

Page 15: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

Energy

Electricity for Mines office and Lights only at nights (working is restricted on day time

only between 9Am to 5Pm). Diesel (HSD) will be used for quarrying machineries around

680960 Liters of HSD will be used for the entire project life. Diesel will be brought from nearby

diesel pumps. No power is required for the project. Lightings on the Night will be taken from

nearby electric poles after obtaining permission from concerned authorities.

1. For Rough stone:

Per hour Excavator will consume = 16 liters / hour

Per hour Excavator will excavate = 20m3of Rough stone

For 851195m3

= 851195/20

= 42560 hours

Diesel consume 42560 working hours = 42560 hours x 16 liters

Total diesel consumption = 680960 Liters of HSD will be utilized for Rough

Stone

Total diesel consumption is around = 680960 Liters of HSD for the entire period of life.

(ix) Quantity of wastes to be generated (liquid and solid) and scheme for their

management/disposal

Top soil: There is no top soil

Overburden/Waste: There is no overburden or waste anticipated during the rough stone

quarrying operation, the entire quarried out material will be sold to required customers at

different categories.

Waste water: There will not be any process effluent generation from the quarry lease area.

Domestic effluent from the mine office is discharged in septic tank and soak pit.

There is no toxic effluent expected to generate in the form of solid, liquid and gases and the no

requirement of treatment of waste.

Page 16: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

(x) Schematic representations of the feasibility drawing which give information of EIA purpose

4.0 SITE ANALYSIS

(i) Connectivity

Mode Description

Road connectivity

1. There is a metal road on the southern side of the area this

road connecting in the Attipalle – Rayakottai road on the

southern side at a distance of1km.

2. Nearest National Highway (NH-7) Salem - Bangalore -

13km- North western side.

3. Nearest State Highway (SH-85) Rayakottai - Attipalle -

1km- Southern side.

Railway station &

Railway line

1. Railway station is Periyanagaithunai - 1km- South western

side.

2. Railway line is Kelamangalam - Periyanagai -1km- South

western side

Air port 1. Nearest Airport is Bangalore Airport - 74km – North

western Side.

(ii) Land Form, Land use and Land ownership

The quarry lease applied area is 4.00.0Ha. The area falls in GSI Topo sheet No.57 H/14.

No forest land involved in this lease area. The applied area exhibits hilly terrain. It is a

Government land (Hilly terrain) the applicant has obtained tender from the Government.

(iii) Topography (along with map)

The lease applied area exhibits hilly terrain, the massive Rough stone formation is clearly

visible right from surface. The slope is gentle towards south western side. The altitude of the area

is above 830m (Maximum) from MSL. The Water table is found at a depth of 45Mts in summer

and at 40Mts in rainy seasons. Average annual rainfall is about 850mm during NE monsoon.

Form – 1

Along with pre-feasibility report

&

Approved Mining plan with Annexure

To Submit SEIAA

Final Presentation

Page 17: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

(iv) Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including area

under CRZ), shortest distances from the periphery of the project to periphery of the forests,

national park, wild life sanctuary, eco sensitive areas, water bodies (distance from the HFL of

the river), CRZ. In case of notified industrial area, a copy of the Gazette notification should be

given.

The quarry lease applied area exhibits hilly terrain. The area is a dry barren land devoid

of Agriculture and Habitations. The land is not used for any specific vegetation. No major water

bodies in the vicinity of the area, Ground water occurrence in this area are 45mt depth. The

quarrying is restricted up to 60m (40m above the ground level + 20m below the ground level) for

a period of Ten years. The region experiences semi – humid climate and there is scanty growth

of vegetation in and around the lease applied area (seasonal vegetation is mostly practiced).

� Udedurgam reserved forest is situated 5km away from the South Eastern side of the area.

� The Western Ghats region is situated 4km away from the Southern side of the area.

� Laxmi Goundan tank is situated within the radius of 4km away from the south eastern

side

� There is no CRZ within the radius of 15km.

� The project area does not fall in ‘HACA’ region.

� There are no Bird sanctuaries, wild life sanctuary or National parks as per Wild life

protection Act 1972, within the radius of 15kms. Locality

� There is no interstate boundary within 15km radius.

� There are few other quarries situated within 1km radius.

(v) Existing Infrastructure

There is no existing infrastructure present in the applied area. A permanent mine office

has been proposed in the lease area. A well-equipped first aid facility will be made available.

Permanent rest shelter is proposed. At the quarry site, urinal and latrine are proposed.

Water for drinking purpose be supplied form the approved water vendors. A small water

tank is also proposed which will be used for water sprinkling, plantation etc.

(vi) Soil Classification

The lease applied area exhibits hilly terrain, The Rough stone formation is clearly visible

right from the surface. This land does not sustain any type of vegetation or Agriculture.

Page 18: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

(vii) Climatic data form secondary sources

The area receives rainfall of about 850mm/ annum and the rainy season is mainly from

Oct - Jan during North East, monsoon. The summer is hot with maximum temperature of 42°C

and winter encounters a minimum temperature of 23°C.

(viii) Social infrastructure available

There is no social infrastructure within the radius of 1Km like schools, universities,

hospitals, prisons and community housing etc.

5. PLANNING BRIEF

(i) Planning Concept (type of industries, facilities, transportation etc) Town and Country

Planning/Development authority Classification

The total area of the project is about 4.00.0Ha. The proposed quantity is around

851195m3 for a period of Ten years. Conventional Open cast semi mechanized quarrying the

quarry operation involves jackhammer drilling, slurry explosives blasting, excavator are used for

loading of Rough stone through tippers to the needy crusher.

There are no habitations or villages en-route between the quarry sites the loaded vehicles

are allowed to move only below 40Kms per hour on the roads. The haul roads are sprinkled

periodically to prevent dust.

Other facilities such as power, transportation and communication, social infrastructure

facilities are locally available near project site. Nearest town is Rayakottai, facilities like

Dispensary, post office are available in Rayakottai - 24km on South Eastern side.

(ii) Population projection

There are few villages located in this area within 5km radius; the approximate distance

and population are given below.

S.No Name of the Village

Approximate distance

& Direction from lease

applied area

Approximate

population

1. Uddanapalli 3km-NE 800

2. Irudhalam 2km-NW 600

3. Anusonai 3km-SW 700

4. Periyanagaithunai 2km-SW 850

Basic human welfare Amenities such as Health Center, Schools, Communication

Facilities, and Commercial Centers etc are available at Rayakottai located at a distance of 24km

on the South Eastern side of the area.

Page 19: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

(iii) Land use planning (breakup along with green belt etc.)

The land use planning of the quarry area of the total extent of 4.00.0Ha is given below

Description Present Area

(Ha.)

Area at the end of

lease period (Ha.)

Area under Quarrying Nil 3.13.6

Infrastructure Nil 0.01.0

Roads Nil 0.01.0

Green Belt Nil 0.28.0

Unutilized 4.00.0 0.56.4

Grand Total 4.00.0 4.00.0

(iv) Assessment of Infrastructure Demand (Physical & Social)

The existing road facilities are already available which shall be used and maintained.

The labors requirement is drawn from the nearest villages. The labors will be brought by jeeps

and vans to the quarry site, Medical facilities are available near the project site, Government and

private hospitals and other basic amenities and infrastructure facilities like communication

center, school supermarket, bus stand are also available in Rayakottai at a distance of 24kms

(SE). This quarry project will provide employment for about 16 persons directly.

(v) Amenities/Facilities

The simple methods adopted and the limited scale of activities involved in Rough stone

quarrying does not require High Tension Electric Power supply or huge worship facilities. The

quarrying work is restricted to one general shift during daytime 9.00am to 5.00pm with 1.00pm -

2.00pm lunch break. Major Machinery repair works are attended at Hosur minor repairs are

carried out by the nearby mechanics. All facilities and amenities are available in Krishnagiri

which is 33Km on the South eastern side of the area.

Packaged drinking water will be brought from approved vendors. Mine office, storeroom,

toilet and first-aid room will be provided on permanent structures within the lease area after the

grant of lease.

6. PROPOSED INFRASTRUCTURE

(i) Industrial Area (Processing area)

There is no processing area proposed within the lease applied area.

(ii) Residential area (Non processing area)

There is no residential area within 500mts of the lease applied area.

Page 20: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

(iii) Green Belt

All along the boundary barrier is selected for Green belt development by planting and

maintaining native species. The total area for proposed for Green belt is around 0.28.0Ha out of

4.00.0Ha. The estimated budget for plantation and maintenance of Green belt development

would be around Rs. 10,000/-

(iv) Social infrastructure

About 16 employees will be directly benefited and 6 persons will be indirectly benefited,

the lease ensure to share all responsible for special benefits like water, health care, Education

benefits, and promotion of socio cultural activities of the nearby villages.

(v) Connectivity (traffic and transportation road/ Rail/ Metro/ Water ways etc.,)

Mode Description

Road connectivity 1. There is a metal road on the southern side of the area

this road connecting in the Attipalle – Rayakottai road

on the southern side at a distance of1km.

2. Nearest National Highway (NH-7) Salem - Bangalore -

13km- North western side.

3. Nearest State Highway (SH-85) Rayakottai - Attipalle -

1km- Southern side.

Railway station &

Railway line

1. Railway station is Periyanagaithunai - 1km- South

western side.

2. Railway line is Kelamangalam - Periyanagai -1km-

South western side

Air port 1. Nearest Airport is Bangalore Airport - 74km – North

western Side.

(vi) Drinking Water management (Source & Supply of water)

This proposed Rough stone quarry project does not require huge water either for

beneficiation or processing. Water required for drinking domestic consumption for labors is

around 0.3KLD. The packaged Drinking water for this will be brought from approved water

vendors is available in Periyanagaithunai on 2km south western side.

(vii) Sewerage System

Toilets will be constructed on permanent structure and sewage will be discharged once in

three months. The sewage waste will be collected in soak pit and discharged as manure for Green

belt development.

Page 21: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

(viii) Industrial Waste Management

No industrial waste will be generated from the project.

(ix) Solid Waste Management

The waste generated during quarrying activity is negligible rock mass during handling

and re handling. Hence, there is no waste in this quarrying operation. There is no solid waste

generation during the quarrying operation.

(x) Power Requirement & Supply / source

The proposed Rough stone quarrying does not required any power supply for the

quarrying operation. It is proposed to operate in day time only from 9 Am to 5Pm with 1 Hour

lunch interval between 1Pm to 2Pm.

7. REHABILITATION AND RESETTLEMENT (R & R PLAN)

(i) Policy to be adopted (Central/State) in respect of the project affected persons including home

oustees, land oustees and landless laborers (a brief outline to be given)

The lease applied area is a Government land in Nagamangalam village, Denkanikottai

Taluk, Krishnagiri District hence there is no Rehabilitation and resettlement is involved. The

deployed labours will be insured as per the Government norms till the end of the life of the

quarry. Periodical medical test will be conducted for the labors to monitor the occupational

disease. The salaries and benefits will be paid as specified by the instruction given by the labor

enforcement officers.

8. PROJECT SCHEDULE & COST ESTIMATES

(i) Likely date of start of construction and likely date of completion (Time schedule for the

project to be given)

The Rough stone quarrying project is likely to get commenced after the execution of

quarrying lease. The proposed quantity is around 851195m3 of Rough stone for the period of Ten

years.

Page 22: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

(ii) Estimated project cost along with analysis in terms of economic viability of the project

A. Fixed Asset Cost: Land cost = Rs. 34, 90,000/-

Labours shed = Rs. 1, 00,000/-

First aid room & Accessories = Rs. 1, 00,000/-

Sanitary facilities = Rs. 1, 00,000/-

Total Fixed assets cost = Rs. 37, 90,000/-

B. Operation cost:

Machineries to be used = Rs. 1, 02, 00,000/-

Fencing cost = Rs. 1, 00,000/-

Total operation = Rs. 1, 03, 00,000/-

C. (I). EMP Estimation:

Air Quality Sampling = Rs. 1, 00, 000/-

Water quality sampling = Rs. 50, 000/-

Noise monitoring = Rs. 40, 000/-

Ground vibration test = Rs. 40, 000/-

Total EMP Estimation cost = Rs. 2, 30,000/-

(II). Expenditure and maintenance:

Drinking water facility for the labors = Rs. 1, 00,000/-

Sanitary arrangement = Rs. 1, 00,000/-

Safety kits = Rs. 20,000/-

Water sprinkling = Rs. 2, 00,000/-

Afforestation cost = Rs. 10,000/-

CSR cost

(Schools, worship places etc,) = Rs. 1, 00,000/-

Total Expenditure and maintenance cost = Rs. 5, 30,000/-

Grand Total (I + II) = Rs. 7, 60,000/-

The total project cost:

A. Fixed Asset cost = Rs. 37,90,000/-

B. Operational cost = Rs. 1,03,00,000/-

C. EMP cost = Rs. 7,60,000/-

Total cost = Rs. 1, 48, 50,000/-

� The total project cost including EMP cost is about Rs.1,48,50,000/- (Rupees One Crore

forty eight lakhs fifty thousand only

� The total EMP cost is around Rs. 7,60,000/- (Rupees Seven lakhs Sixty thousand only)

Page 23: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

Population Benefit

The applicant ensures to take social responsibilities like providing School Note books,

Uniforms to the Students below poverty level beside if the villages require any borehole for

public use the applicant ensure to do so.

The applicant will also take part and contribute the native cultural activities in the nearby

villages. During summer seasons packaged drinking water will be kept will be kept in the village

for public and for tress passers. The applicant will involve and contribute all the socio cultural

allocation in and around the area. The budget provisions and allocation for all the above

activities will be around Rs 40,000 for the period of Ten years.

MINE CLOSURE PLAN:

Steps proposed for phased restoration, reclamation of already mined out areas:

� After the exploitation the Rough stone fencing will be constructed around the pit to

prevent inherent entry of public.

� The pit will be allowed to collect water which will act as a temporary Reservoir which

will enhance the Ground water level of the nearby areas.

� There is no proposal for back filling, reclamation and re habitation. The quarry pit will be

fenced to prevent inherent entry of public.

Measures to be under taken on mine closure as per Act & Rules:

Measure will be taken as per Act & Rules.

Mitigation measure to be undertaken for safety and restoration / reclamation of the already mined

out area:

� Drilling will be carrying out by wet drilling to control the dust into the air.

� Blasting will be carrying out on limited scale.

� Mist spray on haul road will be proposed to prevent the dust propagation into the air.

� The plantation will be carried out on the safety barriers to prevent Noise, besides wet

drilling will be practiced to prevent dust.

� All the machineries will be maintained in good conditions as per RTO and TNPCB

Norms to prevent Noise, Smoke and vibration.

� Machineries will be periodically maintained by experienced mechanic to minimize noise,

Smoke and ground vibration.

Page 24: PRE-FEASIBILITY REPORTforestsclearance.nic.in/.../12112312161211YA2TNPrefeasibility-FalduChimanlal.pdfPRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL

PRE FEASIBILITY REPORT OF NAGAMANGALAM ROUGH STONE QUARRY Mr. FALDU CHIMANLAL MOHANBHAI

UNDER EIA NOTIFICATION 2006

9. ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)

(i) Financial and social benefits with special emphasis on the benefit to the local people

including tribal population, if any, in the area

The lease applied area is Nagamangalam Village, Denkanikottai Taluk and Krishnagiri

District. There are no tribal populations in and around the area about 16 personals directly will

be benefited by these projects, besides the government. The proposed quarry will bring economic

benefits to the state by the way of royalty for mineral, surface rent, sale tax/VAT, income tax etc.

The socio- Economic conditions of the village and distance will enhance due to the

project, hence, the project should be allowed after considering all the parameters. The detail

furnished in this mining plan is based on information provided by the State Government and the

lessee. By considering the merit of the project the permission may be granted.

Date :

Place : Krishnagiri

1. Signature of the Applicant

Faldu Chimanlal Mohanbhai

2. Signature of the Recognized qualified persons

S. Ilavarasan, M.Sc.,

RQP/MAS/253/2013/A