Page 1: PowerPoint presentation Template · expander and the micro DHN pipelines: design of Design phase (Apr.2013-Apr.2015) •Design and tender to procure the turbo expander •Design of

Speaker

Carolina Ferrando (D’Appolonia S.p.A.- RINA Group)

Contributors

Roberto Milanesio (Genova Reti Gas –IREN Group)

Fabio Sagnelli (D’Appolonia S.p.A.- RINA Group)

GENOA DEMONSTRATOR Energy recover from the natural gas distribution network

Page 2: PowerPoint presentation Template · expander and the micro DHN pipelines: design of Design phase (Apr.2013-Apr.2015) •Design and tender to procure the turbo expander •Design of

Location & Team

Genova Reti Gas as Project Responsible

Genoa Municipality as the Local

Authority

University of Genoa as the R&D

Partner

D’Appolonia S.p.A. to

Monitor&Evaluate all CELSIUS demonstrators

Page 3: PowerPoint presentation Template · expander and the micro DHN pipelines: design of Design phase (Apr.2013-Apr.2015) •Design and tender to procure the turbo expander •Design of

Genova Reti Gas – IREN Group The demonstrator is owned and operated by Genova Reti Gas that is part of

the IREN Group, the first operator in Italy in DH. IREN is an Italian multi-

utility company operating in Reggio, Piacenza, Parma, Genova

Heated volume: 3.4 mln m³

Network length: 20 km N° of DH sub-stations: 39 Served inhabitants:

30,000 Total thermal capacity: 67

MWt

Heated volume: 1.1 mln m³

Network length: 20 km N° of DH sub-stations:

120 Served inhabitants:

10,000 Total thermal capacity: 39

MWt

Heated volume: 5.3 mln m³

Network length: 91 km N° of DH sub-stations:

710 Served inhabitants:

50,000 Total thermal capacity:

175 MWt

Heated volume: 13.2 mln m³

Network length: 217 km N° of DH sub-stations:

1,954 Served inhabitants:

130,000 Total thermal capacity:

309 MWt

Reggio Emilia Parma Piacenza Genova

Page 4: PowerPoint presentation Template · expander and the micro DHN pipelines: design of Design phase (Apr.2013-Apr.2015) •Design and tender to procure the turbo expander •Design of

Motivation of the project

Complex territorial

morphology Urban areas are

concentrated along the coast and two

inland valleys

Complex urban

texture One of the biggest historical centre in

Europe

Mediterranean climate

Mild and short winters

High development

of NG distribution

network

Page 5: PowerPoint presentation Template · expander and the micro DHN pipelines: design of Design phase (Apr.2013-Apr.2015) •Design and tender to procure the turbo expander •Design of

What is the project about?

CONDENSED CONCEPT

• To exploit the NG pressure drop between the NG transmission and distribution network for generating electric and thermal energy to serve a micro-DHN

TECHNICAL DETAILS

• TURBO-EXPANDER [550kW] to exploit the NG pressure drop at a main gas distribution substation, generating electric energy

• GAS-FIRED COGENERATION PLANT [526 kWh] 1.To provide the heat required to compensate for the decrease of temperature occurring during NG expansion 2.To serve a Micro-DHN 3.To produce additional electricity

• REMOTE CONTROL SYSTEM

Page 6: PowerPoint presentation Template · expander and the micro DHN pipelines: design of Design phase (Apr.2013-Apr.2015) •Design and tender to procure the turbo expander •Design of

Project timeline

Design phase (Apr.2013-Apr.2015)

• Design and tender to procure the turbo expander

• Design of the CHP and related size of the micro DHN

• Civil works for preparing the area to install the turbo-expander and the micro DHN pipelines: design of underground works and foundations

• Authorizations procedures

Installation phase (May 2015- Sep.2015)

• Finalization of the civil works

• Installation of TE, CHP and pipelines

Operation phase & Monitoring (from Oct.2015)

Page 7: PowerPoint presentation Template · expander and the micro DHN pipelines: design of Design phase (Apr.2013-Apr.2015) •Design and tender to procure the turbo expander •Design of

Installation phase

Page 8: PowerPoint presentation Template · expander and the micro DHN pipelines: design of Design phase (Apr.2013-Apr.2015) •Design and tender to procure the turbo expander •Design of

Environmental benefits

Lower direct emissions to the atmosphere with respect to the current situation will be achieved. The project will make it possible to deliver both electricity and thermal energy to nearby buildings enabling savings of approx. 800 ton CO2/year. Monitoring phase over a 18 months-period.

Technical KPIs

Environmental KPIs

Economic KPIs

Social KPIs

Page 9: PowerPoint presentation Template · expander and the micro DHN pipelines: design of Design phase (Apr.2013-Apr.2015) •Design and tender to procure the turbo expander •Design of

Condensed Business Model: Partners&Benefits

Utility company Self-production of electricity for internal use. Additional clients. Opportunity of recovering waste energy.

Technology providers Higher penetration into the market &

development of new applications

Local Authority Development of a sustainable technology at city level for energy production with decreased GHG emissions. Connection of public buildings with reduced fees. Visibility for the city.

R&D Partner Opportunities for creating new SMEs (spin-off)

Consultant Set-up and sell new services

Page 10: PowerPoint presentation Template · expander and the micro DHN pipelines: design of Design phase (Apr.2013-Apr.2015) •Design and tender to procure the turbo expander •Design of

Thank you for your attention!