SEQ Stabling ProgramWoombye CRG – July 2016
Project update – July 2016
Construction activities underway:
• Drainage and culverts• Earthworks• Capping placement• Security fence footings• Installing of electrical conduits• Concrete foundations for overhead line
equipment (OHLE) and signals
CCulvert outfall - west 91111CONTRACTORS
CCulvert backfill 91111CONTRACTORS
CPBOHLE foundations ee11CONTRACTORS
COHLE footing concrete pour 91111CONTRACTORS
CSecurity fence footing formwork ee11CONTRACTORS
CSecurity fence footing formwork ee11CONTRACTORS
CSite overview looking north ee11CONTRACTORS
CSecurity fence panels 91111CONTRACTORS
CPBEarthworks 91111CONTRACTORS
CPBEarthworks ee11CONTRACTORS
CPBEarthworks 91111CONTRACTORS
CPBEarthworks ee11CONTRACTORS
_ J-
CTurnout rail construction ee11CONTRACTORS
CTurnout railconstruction 91111CONTRACTORS
Project update – July 2016
Upcoming construction activities:
• Security fence – footings, posts and panels• Capping import and placement• Access road and car park works• Inground services including hydraulics• Track install – rescheduled due to weather