Powering Seattle through the 21st Century
Denny Substation Program
WHAT’S NEXT? In the third quarter of 2018, crews will continue to restore neighborhood streets and sidewalks as duct bank installation nears completion. Other upcoming visible work in and around the substation includes completing alley concrete paving on the east side of the substation, wrapping up work on the elevated walkway and installing project art. We will also continue to advance the Cascade Neighborhood Street Improvements.
CONSTRUCTION SCHEDULE
2016 2017 2018 2019 2020
Denny Substation
Substation Energized
Denny Network
VISIT OUR WEBSITE:www.seattle.gov/light/dennysub
SEND US AN EMAIL:[email protected]
CALL OUR HOTLINE:(206) 257-2142
Denny Substation and Denny Network Construction Map
5
8TH AVE
9TH AVE
BOREN AVE
TERRY AVE
7TH AVE
7TH AVE
6TH AVE
9TH AVE
BOREN AVE
8TH AVE 7TH AVE
6TH AVE 5TH AVE
PINE ST
PIKE ST
STEW
ART ST
VIRGIN
IA ST
BLANCHARD ST
BELL ST
OLIVE WAY
MERCER ST
MERCER ST
REPUBLICAN ST
HARRISON ST
DENNY WAY
THOMAS ST
FAIRVIEW
AVE N
ROY ST
ROY ST
WESTLA
KE AVE N
9TH AVE N
8TH AVE N
TERRY AVE N
BOREN
AVE N
YALE AVE N
MINOR AVE
YALE AVE
DENNY PARK
MIN
OR AVE N
MELRO
SE AVE E
PON
TIUS AVE N
CASCADEPLAYGROUND
CASCADEP-PATCH
HOWELL
ST
JOHN ST
DENNYSUBSTATION
WESTLA
KE AVE
LENORA ST
STEWART ST
Ramps to and from I-5
Key
Planned Duct Bank
Completed Duct Bank
Completed Duct Bank and Roadway Restoration
Completed Duct Bank, Roadway Restoration, and Final Driving Surface
Vault
DENNY NETWORK ONGOING CONSTRUCTION
DV-08
DV-09
DV-10
DV-11
DV-05
DV-06
DV-07
DV-12
HV-02
HV-01
DV-13
DV-21 DV-22 DV-23
DV-40
DV-31
DV-20
DV-33
DV-27 DV-28 DV-29 DV-30
DV-34 DV-35 DV-36
DV-37 DV-39 DV-26
DV-24
DV-25
DV-32
DV-38
DV-41
HV-03
Veer Lofts
Via 6
Larned Apts. Westlake
Hotel
WestinNorth
WestinSouth
StewartCourtHotel
Max
Cosmopolitan
DekkoApts.
Aspira Apts.
BalfourApts.
HarborHouse
JulieApts.
502Minor
CascadeApts.
AMLI
Stack House
AlcyoneApts.
Mirabella
CasaPacifca
LakeviewApts.
Brewster Co
lwell A
pts.
Alley 24 Apts.
Alley 24North
SCCA
215Pontius
219PontiusMinor
AveChildren’s
Metropolitan
Project map showing progress of work for Denny Substation and Denny Network construction.
Powering Seattle through the 21st Century
Denny Substation Program
QUARTERLY REPORT 2 N D Q UA R T E R | 2 0 1 8
THE FINISH LINE IS IN SIGHT!With two quarters of 2018 already behind us, it’s hard to contain our excitement. Every day brings us closer to project completion! Recent noteworthy milestones include: starting the energization process in the substation, restoring and re-opening John Street, and installing new sidewalks and curb ramps throughout the Cascade Neighborhood. Community benefits that took take shape this quarter include the off-leash areas, handrails, and the waterproof membrane for the elevated walkway.
If you’ve followed along since the beginning of the project, the most anticipated times are yet to come. Let’s hear it for the sprint to the finish line!
Keepin’ it green: In May, we
installed solar panels atop the
substation. These will provide
electricity to the community spaces
and interior buildings and will help
us live up to our reputation as the
nation’s greenest utility.
INSIDE THE SUBSTATION:
STEPPIN’ UP OUR GAME…Stairs have been installed at the southwest corner of the substation to provide pedestrian access through the site. The stairs lead to Denny Way, where a new signalized crosswalk will improve connections between the Denny Triangle and Cascade neighborhoods.
The wooden forms constructed by crews in the first picture are stripped away after the concrete is poured. The second picture shows the freshly formed stairs, which will soon be ready for the public to walk on.
Denny Substation ProgramPowering Seattle through the 21st Century
ENERGIZATION PROGRESS REPORTRemember these? In late April, crews began the energization process by bringing high-voltage electricity into the substation’s three transformers and testing them under electrical load. This is a crucial step in “turning on” the substation and making sure it can safely deliver power to customers.
The substation’s three transformers have undergone extensive testing and will soon be transforming high voltage electricity into voltages that can be used by customers.
RESTORE GALORERepaving is a good sign —it means the underground work is wrapping up and the end of construction is near. Who doesn’t love the ride of a smooth freshly paved road?
An asphalt paving crew restores the roadway on Pontius Ave N near John Street after a network distribution line was installed near the substation.
After duct bank installation, the concrete crew restored the roadway in the intersection of 9th Ave N and Thomas Street.
AROUND THE SUBSTATION:
A LUSH CASCADE NEIGHBORBOODCommunity improvements continued in the Cascade Neighborhood. In addition to the new street lighting, sidewalks, and curb ramps, landscaping and trees were recently installed. Improvements still to come include more landscaping during the fall planting season. Crews prepare to plant a tree
in the planting strip next to the Cascade Playground.
Landscaping and a rain garden in the Cascade Neighborhood are among the improvements being made to make the neighborhood greener and a more inviting place to walk.