possible beam measurements during 2014 sector tests
DESCRIPTION
Possible beam measurements during 2014 sector tests. W. Bartmann, M. Giovannozzi, S. Redaelli, R. Tomas, J. Wenninger Aperture Polarities Optics Collimation Acknowledgements: B. Goddard - PowerPoint PPT PresentationTRANSCRIPT
Sector Test Meeting - MG 1
Possible beam measurements during 2014 sector tests
W. Bartmann, M. Giovannozzi, S. Redaelli, R. Tomas, J. Wenninger
•Aperture •Polarities•Optics•Collimation
Acknowledgements: B. Goddard
General comment: most of these measurements can be performed more efficiently with circulating beams. An early detection of possible issues is the justification for beam measurements during the sector tests.
22/05/2014
Aperture measurements• Regions:
– Injection– Arcs– IRs– Dump channel
• Arcs and IRs:– Create betatron oscillations along the sector(s)– Possibly fix amplitude to the expected required
aperture at injection.– Scan over the phase
22/05/2014 Sector Test Meeting - MG 2
Already covered by W. Bartmann on 8/5/2014
Polarity measurements - I• Elements to be probed (priority list):
1. BPM and orbit correctors
2. Circuits affected by LS1 activities• Skew correctors in sector 3-4: put back in operation
during LS1 -> not available for sector tests• RQTF.A81.B1: four magnets removed from circuit ->
not available for sector tests• RCOs: some magnets by-passed during LS1
– RCO.A78B2: 2 out of 77 magnets are bypassed -> available for sector test
– RCO.A81B2: 2 out of 77 magnets are bypassed -> not available for sector test
• Q5L8: new magnet installed during LS1 -> not available for sector tests
22/05/2014 Sector Test Meeting - MG 3
Polarity measurements - II• Elements to be probed:
3. Skew quadrupoles (usually have polarity issues)
4. Circuits not fully tested during Run I• …
5. Sample test of circuits, e.g.,• MQTs• MQTLs
22/05/2014 Sector Test Meeting - MG 4
Optics• Combined transfer line + LHC ring studies
(extension of tests proposed by W. Bartmann on 8/5/2014):– Kick response– Dispersion measurement
22/05/2014 Sector Test Meeting - MG 5
Remember TL and ring matching puzzles in 2008
Ring Collimation• See details in Belen’s talk on 08-05-2014 on
how to stop the beams • Envisage two dedicated measurements:
– Parasitic: check acquisition of BPM signal of new collimators, when applicable.
– Dedicated: BLM response with different collimator settings (“splash” events for different collimators in cleaning insertions – if reachable during the sector test) – BI request
– Note: no need of special controls setup in LSA, manual movements and adjustment of interlocks.
22/05/2014 Sector Test Meeting - MG 6
Possible plans: list of measurements/sector test
• Group measurements in four blocks:– 1 shift:
• arcs and IRs aperture• magnet polarities
– 2×1/4 shift (spare time):• BPMs and orbit correctors polarities• Collimation measurements (splashes)
– 1 shift: • Kick response measurements in TL and LHC ring.• Dispersion measurement in TL and LHC ring
22/05/2014 Sector Test Meeting - MG 7
Possible synergies between the two types f measurements: trajectory excursion can be used to probe non-linear magnets