Page 1: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees
Page 2: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Portfolio

Version: Jun-2017

Page 3: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

History

Construction & Design Company ‘Constec’, an Egyptian

joint stock company, established in 1989 and has been

providing fully integrated contracting solutions since then.

Currently, Constec is one of Egypt’s leading construction

companies that ranks “1st Class General Contracting &

Finishes” with rich experience in implementing industrial,

residential, commercial and tourist projects including

Infrastructure, Electromechanical works and Management.

Page 4: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Mission Statement

Client satisfaction is our principal objective.

To achieve that, we perform any undertaking assigned to us

on time, within the allocated budget and within the

specification set for the job; to assure all expectations are

met.

Page 5: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Scope Of Activities

We execute and manage turnkey projects through performing

a variety of construction works and related services. Our

experience covers the following sectors:

– Residential Buildings & Compounds

– Industrial & Warehouses Buildings

– Commercial Buildings

– Hotels & Resorts

– Landscape and Urban Development

– Treatment Plants

– Infrastructure

Page 6: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Partners in Success

Page 7: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Chairman & Board

ExecutiveManager

HR Manager

Admin Off

Recruitment & Development

IT Manager

Programing & Development

Networks

Tech Support

Procurement Manager

Contracts Manager

Owner Contracts

S/C Contracts

Purchasing Manager

Buyers

Technical Manager

Projects Follow Up

Shop Drawings

Projects Invoices

Q.S.

Projects Manager

HSE Manager

Projects Controls

Quality Control

Sr. Planning Engineer

Planning Engineers

Cost Control

Project Managers

Construction Managers

Site Engineers

Tech. Office Engineer

Electro-Mechanic

Site Supervisors

Surveyors

Asset Manager

Assets

Drivers

LogisticsTendering Manager

Tendering

Sr. Tendering Engineer

Estimators

Quantity Surveyors

Electrical Mechanical

Financial Manager

Document Control

General Accounting

Banks and Treasury

Treasury

Banks

Contractors Accounts

Customer Accounts

Site Accountants

Warehouse

Organization Chart

Internal Audit & Quality Assurance

Business Development

E.M. Secretary

Page 8: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

ISO 90001 Certificate

Page 9: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Overview

Authorized Capital 100 Million EGP

Issued Capital 20 Million EGP

Assets 20 Million EGP

Staff Strength 172 Employees

Supplementary Staff 500 Employees

Page 10: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Personnel

Management Team 9

Office Engineers 15

Office Administration & Financing 16

Projects Managers 6

Site Managers 6

Site Engineers 20

Technical Site Helpers and Foreman 100

Page 11: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

PROJECTS AND CLIENTS

Success story extends for more than 28 years

Page 12: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

I. RESIDENTIAL BUILDINGS

& COMPOUNDS

Success story extends for more than 28 years

Page 13: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

I. Residential Buildings & Compounds

SODIC Projects 270 Million EGP

Pyramids Heights – SamCrete in 6th October city 65 Million EGP

Green 3 in Zayed 60 Million EGP

Royal City compound in Zayed 70 Million EGP

Green Waves in Zayed 65 Million EGP

Green Residence 1 in Zayed 28 Million EGP

Green Residence 2 in Zayed 28 Million EGP

Green Hills Compound in Zayed 19 Million EGP

Page 14: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

SODIC Projects

Gaining the company’s trust

Start of Journey

SODIC Spine Block 28, 29 & 33

Over Achiever

SODIC Spine Block 32

Gaining Trust

SODIC Phase 10 Block 4

Remote Projects

Caesar Bay Phase 1

Client Satisfaction

Caesar Bay Phase 2

New Challenge

Villette – East Town

30 M EGP 75 M EGP

Total Projects 270 Million EGP

Page 15: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

SODIC Spine - West Town

Construction of Blocks 28, 29, 32, 33 compromising a total of

59 Core & Shell Villas of different Models and areas

Location: Zayed (West Town)

Consultant: Al Amar (AMG)

Owner: SODIC

Duration : 1 Year

Contract Date : 2015

Project Value 30 Million EGP

Page 16: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

SODIC Spine - West Town

Page 17: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

SODIC Phase 10 Block 4 - West Town

Residential Compound comprises 17 Multi Story Semi

finished Buildings of different Models and areas, in addition

to the construction of an electrical room

Location: Zayed (West Town)

Consultant: Al Amar (AMG)

Owner: SODIC

Duration : 18 Months

Contract Date : 2015

Project Value 70 Million EGP

Page 18: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

SODIC Phase 10 Block 4 - West Town

Page 19: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

SODIC Caesar in Ras El Hekma

Construction of Zone A,B & C consisting of 45 Core & Shell

villas in addition to the external finishes

Location: Ras El Hekma – North Coast

Consultant: Active Brains

Owner : SODIC (Tabrook

for Development)

Duration : 18 Months

Contract Date : 2015

Project Status: Under

Construction

Project Value 75 Million EGP

Page 20: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

SODIC Caesar in Ras El Hekma

Page 21: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

SODIC Villette – East Town

Residential Compound comprises 22 Semi Finished Town

Houses and 17 Semi Finished Twin Houses, of different

Models and areas.

Location : New Cairo (East Town)

Consultant: EHAF

Owner: SOREAL for Real Estate

Investment (SODIC)

Duration : 18 Months

Contract Date : 2017

Project Status: Under Construction

Project Value 95 Million EGP

Page 22: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Pyramids Heights – SamCrete in 6th

October city

Residential Compound comprises 40 Villas, of different

Models and areas.

Location: Six October City.

Consultant: PhD. Eng. Sameh Milad

Owner: SamCrete

Duration : 18 Months

Contract Date : 2016

Project Status: Under Construction

Project Value 65 Million EGP

Page 23: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Pyramids Heights – SamCrete in 6th

October city

Page 24: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Green 3 in Zayed

Turnkey residential compound comprising of 35 Twin Houses

and 110 Apartment Units in several Multistory Buildings

Location: Zayed

Area: 54,600 m2

Consultant: El Gabaly Consultant

Owner: Mabany for Real Estate Investment

Duration : 2 Years

Contract Date : 2010

Project Value 60 Million EGP

Page 25: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Royal City Compound in Zayed

Turnkey residential compound comprising the construction of

two phases of 45 and 21 villas of different models and size

Location: Zayed

Consultant: Mohram Bakhoum Infrosefk

Owner: Al-Babtain Group “Kuwait”

Duration : 2 Years

Contract Date : 2008

Project Value 70 Million EGP

Page 26: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Green Waves Compound in Zayed

Turnkey residential compound comprises the construction of

two phases of 10 Multi Story Buildings & 4 Villas then 5

Multi Story Buildings of different models and sizes

Location: Zayed

Consultant: Urban Projects Office

Owner: Mabany Real Estate Co.

Duration : 3 Years

Contract Date : 2010

Project Value 65 Million EGP

Page 27: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Green Residence 1 in Zayed

Turnkey residential compound comprising of 120 Apartment

Units in 7 Multistory Buildings

Location : Zayed

Area: 20,000 m2

Consultant: Engineer M. Omar Ghazal

Owner: Mabany for Real Estate Investment

Duration : 2 Years

Contract Date : 2005

Project Value 28 Million EGP

Page 28: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Green Residence 2 in Zayed

Turnkey residential compound comprising of 115 Apartment

Units in 7 Multistory Buildings

Location: Zayed

Area: 20,000 m2

Consultant: PhD. Eng. M. Omar Ghazal

Owner: Mabany for Real Estate Investment

Duration : 2 Years

Contract Date : 2007

Project Value 28 Million EGP

Page 29: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Green Hills Compound in Zayed

Residential compound comprising 4 multistory buildings and

45 residential villas of different models and size

Location: Zayed

Consultant: En. Integrated

Consulting Group (JADE)

PhD Eng. Ayman Meselhy

Owner: Egypt Real Estate

Development

Duration : One Year

Contract Date : 2007

Project Value 19 Million EGP

Page 30: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

II. INDUSTRIAL & WAREHOUSES

Success story extends for more than 28 years

Page 31: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

II. Industrial & Warehouses

Jushi Fiberglass Factory 85 Million EGP

Abou Rawash Warehouse 77 Million EGP

Infofort Warehouse in 6th October City 38 Million EGP

Aramex Warehouse in Borg El Arab City 24 Million EGP

F2 Factory in Sokhna 16 Million EGP

F5 Factory in Sokhna 16 Million EGP

F3 Factory in Sokhna 12 Million EGP

Aramex Warehouse in 6th October City 10 Million EGP

Page 32: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Jushi Fiberglass Factory

Construction and finishing of 45,000 m2 reinforced concrete

industrial facility

Location: Industrial Zone - Sokhna

Area:45,000 m2

Consultant: Building Consulting Group

“Benaa” Dr. Alaa El Sayed

Owner : Jushi Egypt for Fiber Glass

Industry S.A.E

Duration : 2 Years

Contract Date : 2012

Project Value 85 Million EGP

Page 33: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Abou Rawash Warehouse

Construction of 5 Warehouses on a total area of 100,000 m2

Location : Abou Rawash

Area:100,000 m2

Consultant: Egyptian House

Engineer-Ph.D. Hany El Gamal

Owner : Egyptian Company

for Storage Services

Duration : 3 Years

Contract Date : 2005

Project Value 77 Million EGP

Page 34: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Infofort Warehouse

Construction of steel structure warehouse with a total area of

23,000 m2 and reinforced administration building

Location : 6th October City

Area:23,000 m2

Consultant: MA Consulting Office-

Dr. Moamen Afify

Owner : Infofort Company

Duration : 2 Years

Contract Date : 2010

Project Value 38 Million EGP

Page 35: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Aramex Warehouse – Borg El Arab

Construction of Aramex Company Warehouse, consisting of a

steel structure warehouse with a total area of 2,500 m2 and

reinforced administration building

Location : Borg El Arab City

Area: 2,500 m2

Consultant: MA Consulting Office-

Dr. Moamen Afify

Owner : Aramex –Masharek Company

Duration : One Year

Contract Date : 2012

Project Value 24 Million EGP

Page 36: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

F2 Factory

Construction of steel truss of 4,000 m2 area and two story

reinforced concrete administration buildings with an area of

800 m2

Location: Sokhna

Area: 4,800 m2

Consultant: Building Consulting Group

“Benaa” Dr. Alaa El Sayed

Owner : Egypt TEDA Investment Company

Duration : One Year

Contract Date : 2004

Project Value 16 Million EGP

Page 37: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

F5 Factory

Construction of F5 factory comprising 2 story concrete

structure with an area of 5,400 m2

Location: Sokhna

Area: 5,400 m2

Consultant: Building Consulting Group

“Benaa” Dr. Alaa El Sayed

Owner: Egypt’s Suez China

Real Estate Development

Duration: One Year

Contract Date: 2008

Project Value 16 Million EGP

Page 38: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

F3 Factory

Construction of F3 factory comprising 2 story concrete

structure with an area of 5,400 m2

Location: Sokhna

Area: 5,400 m2

Consultant: Building Consulting

Group “Benaa” Dr. Alaa El Sayed

Owner : Egypt’s Suez China

Real Estate Development

Duration : 9 Months

Contract Date : 2008

Project Value 12 Million EGP

Page 39: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Aramex Warehouse – 6th October

Construction of Aramex Company Warehouse, consisting of a

steel structure warehouse with a total area of 2,500 m2 and

reinforced administration building

Location: 6th October City

Consultant: MA Consulting Office-

Dr. Moamen Afify

Owner : Aramex-Masharek Company

Duration : One Year

Contract Date : 2012

Project Value 10 Million EGP

Page 40: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

III. INFRASTRUCTURE

Success story extends for more than 28 years

Page 41: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

III. Infrastructure Projects

Water Desalination Plant in Sokhna 35 Million EGP

Rehabilitation and renovation of

Luxor Cornish , City Gates and Roundabouts 10 Million EGP

Aircraft Engines Industry 8 Million EGP

Water Tank in Sokhna 6 Million EGP

Main Substation of Phosphate Factory – Sokhna 4 Million EGP

Waste Water Treatment Plant in Wadi Hof 4 Million EGP

Waste Water Treatment Plant in El Mahala El Kobra 3 Million EGP

Page 42: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Water Desalination Plant

Construction of 4500 m3/day including all A/M, tanks, pumps

and administration buildings and RO System (Severn Trent

Service Company)

Location : Sokhna

Consultant: Moharam Bakhoum

Owner : Egyptian Fertilizers

Company

Duration : One Year

Contract Date : 2005

Project Value 35 Million EGP

Page 43: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Water Desalination Plant

Page 44: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Rehabilitation and renovation of Luxor

Cornish ,City Gates and roundabout

Rehabilitation and renovation of 3.5 Km Luxor Cornish ,

City Gates and roundabouts

Location : Luxor City

Distance: 3.5 Km

Consultant: Eng. Hassan

Dahrouj

Owner : Luxor City Council

Duration : One Year

Contract Date : 2001

Project Value 10 Million EGP

Page 45: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Rehabilitation and renovation of Luxor

Cornish ,City Gates and roundabout

Page 46: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Aircraft Engines Factory

Construction of inspection chamber nutrition , sewage

network and roads

Location: Cairo-Helwan

Consultant: Benaa Consultant

Dr. Alaa El Sayed

Owner : Arab Organization

for Industrialization

Duration : One Year

Contract Date : 2004

Project Value 8 Million EGP

Page 47: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Water Tank in Sokhna

Construction of TEDA city Under ground Water Tank with a

capacity of 1500 m3

Location: Sokhna

Consultant: Building Consulting Group PhD. Alaa El Sayed

Owner : Egypt Suez China Real Estate Development

Duration: 18 Months

Contract Date : 2009

Project Value 6 Million EGP

Page 48: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Water Tank in Sokhna

Page 49: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Main Substation of Phosphate &

compound fertilizers complex in Sokhna

Civil and finishing works of the Main Substation. The

substation consists of transformer room, Ring Main Unit,

MDB, Generator and Switch gear

Location : Sokhna

Consultant: Enppi

Owner : NCIC

Duration : 3 Months

Contract Date : 2016

Status: Under Construction

Project Value 4 Million EGP

Page 50: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Waste Water Treatment Plant in Wadi

Hof

Construction of 3000 m3/day Waste

Water Treatment Plant

Location: Wadi Hof

Consultant: Arab Organization for

Industrialization

Owner : El Nasr Automotive

Manufacturing

Duration : One Year

Contract Date : 2002

Project Value 4 Million EGP

Page 51: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Waste Water Treatment Plant in El

Mahla El Kobra

Construction of 3600 m3/day

Waste Water Treatment Plant

Location: El Mahla El Kobra

Consultant: Arab Organization

for Industrialization

Owner : Tanta for oil and soap

Duration : One Year

Contract Date : 1999

Project Value 3 Million EGP

Page 52: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

IV. HOTELS AND RESORTS

Success story extends for more than 28 years

Page 53: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

IV. Hotels and Resorts

Royal Palm Beach Hotel in Hurghada 200 Million EGP

Amer Group Projects 175 Million EGP

Movenpick Hotel in Al Haram 45 Million EGP

Multi Purpose Building in Suez City 24 Million EGP

Palm Beach Hotel 12 Million EGP

Mubarak Hotel in Siwa Oasis 6 Million EGP

Pyramisa Village in Hurghada 4 Million EGP

Page 54: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Royal Palm Beach Hotel in Hurghada

Construction of the hotel comprising 350 rooms on an area of

60,000 m2 , including the main building , swimming , soft and

hard scape

Location of the project: Hurghada City

Area: 60,000 m2

Consultant: ASA Consultant-

Eng. Omar Zatoun

Owner : Red Sea for Tourism Development

Duration : 4 Years

Contract Date : 2005

Project Value 200 Million EGP

Page 55: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Amer Group Projects

Specializing in Turn Key projects for Recreational Resorts

projects.

Total Projects 175 Million EGP

50 M EGP 55 M EGP

Start of Journey

South Beach Project

Challenging Scope

South Beach - Water Treatment Plant

Client Satisfaction

Porto Sokhna – Golf Bay

New Challenge

Hanging Gardens Platform 5

5 M EGP 65 M EGP

Page 56: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Porto Sokhna – South Beach

Turn Key project comprises construction and handover of 7

multistory Buildings: H2, H4, H5, H7, RU1, RU2 &RU3

compromising a total of 348 chalet

Location: Sokhna

Consultant: Shaker Group and

Moharam Bakhoum “ACE”

Owner : Amer Group

Duration : 2 Years

Contract Date : 2013

Project Value 50 Million EGP

Page 57: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Porto Sokhna – South Beach WTP

Construction of the Porto South Beach main Water

Treatment Plant of daily capacity 800 m3/day

Location: Sokhna

Consultant: Shaker Group and

Moharam Bakhoum “ACE”

Owner : Amer Group

Duration : 1 Year

Contract Date : 2013

Project Value 5 Million EGP

Page 58: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Porto Sokhna – South Beach WTP

Page 59: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Porto Sokhna – Golf Bay

Turn Key project comprises construction and handover of 4

Multistory Buildings: B1, B2, B3 & B4 compromising a total

of 374 chalet

Location: Sokhna

Consultant: Hill International

and ACE

Owner : Amer Group

Duration : 2 Years

Contract Date : 2013

Project Value 55 Million EGP

Page 60: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Porto Sokhna – Hanging Gardens (PL5)

Construction of Hanging Gardens Platform 5 consisting of 12

Multi Story Building comprising 294 Chalets of different

models and areas

Location: Sokhna

Consultant: Hill International

and ACE

Owner : Amer Group

Duration : 1 Year

Contract Date : 2016

Project Status: Under Construction

Project 65 Million EGP

Page 61: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Movenpick Hotel in Al Haram

Turn Key project comprises construction and fully furnishing

of 148 rooms and suits as an extension of the existing

Movenpick Hotel on a total area of 4,000 m2

Location: Giza

Area: 4,000 m2

Consultant: Integrated Consultant

Group “Gayed”- Dr. Aymen Meselhy

Owner : Tourism Urbanization Company

Duration : 3 Years

Contract Date : 2009

Project Value 45 Million EGP

Page 62: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Multi Purpose Building in Suez City

Turnkey Project comprises the

construction of a reinforced

concrete multi purpose building

on an area of 20,000 m2.

Including all the interior &

exterior finishing , MEP and

landscape work. The Project

Consists of:

1. 120 Room Hotel Building

2. Main Building

3. 1,000 m2 Auditorium

Project Value 24 Million EGP

Page 63: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Multi Purpose Building in Suez City

Location : Suez City

Area: 20,000 m2

Consultant: Barakat & Associates-Dr Magdy Barakat

Owner : Al Nasr for Petroleum Co.

Contract Date : 2010

Page 64: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Palm Beach Hotel

Turnkey project comprising the construction of: 8 Suits , 92

Rooms , Restaurant, Kitchen , Laundry , Cafeteria Beach

Swimming, Pool with an area

of 420 m2.

Location : Hurghada

Consultant: ASSA Consulting Eng. Omar Zatoun

Owner : Red Sea for Tourism

Development

Duration : One Year

Contract Date : 2005

Project Value 12 Million EGP

Page 65: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Project 4 Million EGPProject 6 Million EGP

Mubarak Hotel in Siwa Oasis

Construction of the Olympic Village Hotel which comprises the following:

– 4 Main Suits

– 3 Presidential Suits

– 60 Rooms

– Restaurant

– Kitchen

– Laundry

– Landscape

Location: Siwa Oasis

Consultant: Egyptian Engineering House Dr. Hany El Gamal

Owner : Region of Western Military

Duration: 18 Months

Contract Date : 2001

Pyramisa Village in Hurghada

Construction of the Market Facility which comprises the following:

– Antique Shops

– Main Gate

– Fences

Location: Hurghada City

Consultant: Decoration Office Omar Ghoneim

Owner : Misr Real Estate Development

Duration : One Year

Contract Date : 2005

IV. Hotels and Resorts

Page 66: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

V. COMMERCIAL BUILDINGS

Success story extends for more than 28 years

Page 67: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

V. Commercial Buildings

Rofayda Health Park 75 Million EGP

Cairo Business Park 55 Million EGP

Shorouk Academy 30 Million EGP

Hyper One 10th of Ramadan 23 Million EGP

Eastern Suburbs Mall in 5th Settlement 20 Million EGP

Tivoli Dome Zayed 15 Million EGP

ITS Company Building 14 Million EGP

Page 68: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Rofayda Health Park

Construction of a medical center of two main buildings;

Clinics building, Maternity & Dar Al Oyoun Hospitals

Location: Zayed

Area: 17,000 m2

Consultant: Engineering Office-

Eng. Alaa Abou El Ezz

Owner: Mabany for Real

Estate Investment

Duration: 2 Years

Contract Date: 2013

Project Value 75 Million EGP

Page 69: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Cairo Business Park

Administrative Buildings comprises 2 Multi Story Semi

finished Buildings, Building H & L, with a total BUA of

33,000 m2

Location: New Cairo

Area: 33,000 m2

Consultant: ECB Consulting –

PhD. Eng. Hany El Zyat

Owner: Misr Italia

Duration: 1 Year

Contract Date: 2017

Project Value 55 Million EGP

Page 70: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Shorouk Academy

Construction of Applied Arts building, Economy building,

and R&D Building with a total BUA of 23,000 m2

Location: El Shorouk City

Area: 23,000 m2

Consultant: PhD. Eng. Amr El

Halafawy

Owner: 10th of Ramadan for

development and educational services Co.

Duration : 9 Months

Contract Date : 2016

Project Status: Under Construction

Project Value 30 Million EGP

Page 71: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Hyper One in 10th of Ramadan City

Construction of Hyper One commercial mall at Cairo

Ismailia main road on an area of 12,000 m2 comprising :

1. Exhibition Area

2. Administration Building

3.Infrastructure Work

Project Value 23 Million EGP

Page 72: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Hyper One in 10th of Ramadan City

Location: 10th of Ramadan City

Area: 12,000 m2

Consultant: MA Consulting

Office-Dr. Moamen Afify

Owner : Eng. M. Hawary

Duration : 2 Years

Contract Date : 2011

Page 73: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Eastern Suburbs Mall in 5th Settlement

Construction of “Eastern Suburbs” commercial mall in 5th

Settlement in front of AUC’s Gate 4

Location : 5th Settlement

Area: 10,000 m2

Consultant: Space Consultants

Owner : Misr Real Estate

Management

Duration : 18 Months

Contract Date : 2013

Project Value 20 Million EGP

Page 74: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Tivoli Dome in Zayed

Construction of “Tivoli Dome” commercial mall on an area of

6,000 m2 , consisting of basement , ground floor and three

typical floors

Location : Zayed

Area: 6,000 m2

Owner : Mabany for Real Estate Investment

Duration : 2 Years

Contract Date : 2010

Project Value 15 Million EGP

Page 75: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

ITS Company Building

Construction and finishing work of the ITS extension

building

Location : Nasr City

Consultant: Building Consulting

Group PhD. Alaa Sayed

Owner : ITS Company

Duration : 2 Years

Contract Date : 2008

Project Value 14 Million EGP

Page 76: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees

Contact us

1125 Kornish El-Nile, Maspero – Cairo, Egypt

(+202) 27738940 - (+202) 27738941 - (+202) 27738776

(+2) 01144140490

www.construction-eg.com

[email protected]

Page 77: Portfolio - construction-eg.com · ISO 90001 Certificate. Overview Authorized Capital 100 Million EGP Issued Capital 20 Million EGP Assets 20 Million EGP Staff Strength 172 Employees