Port Macquarie Base Hospital – Very Early Stages
Jo CampbellProject Lead, Whole of Hospital ProgramPort Macquarie Base Hospital
![Page 2: Port Macquarie Base Hospital – Very Early Stages Jo Campbell Project Lead, Whole of Hospital Program Port Macquarie Base Hospital](https://reader036.vdocuments.mx/reader036/viewer/2022062307/551b4289550346d41a8b57c1/html5/thumbnails/2.jpg)
Governance TeamGeneral Manager
Project Lead
Director of Nursing
Director of ICU (became Clinical Lead)
Director of Emergency
Head of Department of Surgery
Head of Department of Medicine
Staff Specialist Paediatrician
![Page 3: Port Macquarie Base Hospital – Very Early Stages Jo Campbell Project Lead, Whole of Hospital Program Port Macquarie Base Hospital](https://reader036.vdocuments.mx/reader036/viewer/2022062307/551b4289550346d41a8b57c1/html5/thumbnails/3.jpg)
What and How
Who Owns The Timeline Study – 18th- 20th August, 2013
Why Am I Still Here Study – 16th – 20th September
![Page 4: Port Macquarie Base Hospital – Very Early Stages Jo Campbell Project Lead, Whole of Hospital Program Port Macquarie Base Hospital](https://reader036.vdocuments.mx/reader036/viewer/2022062307/551b4289550346d41a8b57c1/html5/thumbnails/4.jpg)
WOTTL exampleBiggest delay was
Medical Review (time from request of medical consult to time of complete medical consult)
11:51 - Triage
13:30 - Med review requested
14:38 - CT ordered
21:38 – Medical Consult Complete
LOS 11hrs 30mins
![Page 5: Port Macquarie Base Hospital – Very Early Stages Jo Campbell Project Lead, Whole of Hospital Program Port Macquarie Base Hospital](https://reader036.vdocuments.mx/reader036/viewer/2022062307/551b4289550346d41a8b57c1/html5/thumbnails/5.jpg)
WAISH example
Biggest delay category was
“Doctors delay in decision making” (either an actual delay or no communication of plan)
20/9 “stay in until next week” – no reason
23/9 “for discharge”
![Page 6: Port Macquarie Base Hospital – Very Early Stages Jo Campbell Project Lead, Whole of Hospital Program Port Macquarie Base Hospital](https://reader036.vdocuments.mx/reader036/viewer/2022062307/551b4289550346d41a8b57c1/html5/thumbnails/6.jpg)
Next Steps
1. Communication
2. Communication
3. Communication
![Page 7: Port Macquarie Base Hospital – Very Early Stages Jo Campbell Project Lead, Whole of Hospital Program Port Macquarie Base Hospital](https://reader036.vdocuments.mx/reader036/viewer/2022062307/551b4289550346d41a8b57c1/html5/thumbnails/7.jpg)
Taking Ownership
![Page 8: Port Macquarie Base Hospital – Very Early Stages Jo Campbell Project Lead, Whole of Hospital Program Port Macquarie Base Hospital](https://reader036.vdocuments.mx/reader036/viewer/2022062307/551b4289550346d41a8b57c1/html5/thumbnails/8.jpg)
Address Concerns
“So we are going to end up with sicker patients on the ward because they’ll be pushed out of ED at 4 hours”
![Page 9: Port Macquarie Base Hospital – Very Early Stages Jo Campbell Project Lead, Whole of Hospital Program Port Macquarie Base Hospital](https://reader036.vdocuments.mx/reader036/viewer/2022062307/551b4289550346d41a8b57c1/html5/thumbnails/9.jpg)
![Page 10: Port Macquarie Base Hospital – Very Early Stages Jo Campbell Project Lead, Whole of Hospital Program Port Macquarie Base Hospital](https://reader036.vdocuments.mx/reader036/viewer/2022062307/551b4289550346d41a8b57c1/html5/thumbnails/10.jpg)
Transparent Documentation
• Top 5 solutions displayed in Boardroom• WoHP a standing Agenda Item on many
forums within the hospital• Weekly activity Reporting• Regular feedback when new targets have
been reached
![Page 11: Port Macquarie Base Hospital – Very Early Stages Jo Campbell Project Lead, Whole of Hospital Program Port Macquarie Base Hospital](https://reader036.vdocuments.mx/reader036/viewer/2022062307/551b4289550346d41a8b57c1/html5/thumbnails/11.jpg)
Ongoing Learning
• A Whole of District approach with Coffs Harbour proactively supported by our CE
• Networking at WoHP Conferences• Teleconference support from WoHP• Teleconference peer support with Coffs,
Lismore and Tweed
![Page 12: Port Macquarie Base Hospital – Very Early Stages Jo Campbell Project Lead, Whole of Hospital Program Port Macquarie Base Hospital](https://reader036.vdocuments.mx/reader036/viewer/2022062307/551b4289550346d41a8b57c1/html5/thumbnails/12.jpg)
Outcomes
Admitted NEAT
Non-Admitted
NEAT
Total NEAT
July 16.97% 78.41 60.11%
November 39.9% 87.74% 70.74%
![Page 13: Port Macquarie Base Hospital – Very Early Stages Jo Campbell Project Lead, Whole of Hospital Program Port Macquarie Base Hospital](https://reader036.vdocuments.mx/reader036/viewer/2022062307/551b4289550346d41a8b57c1/html5/thumbnails/13.jpg)
Key learnings
It doesn’t happen overnight
It does happen when you’re not looking
Once it does happen it doesn’t necessarily keep happening
Just because you “emailed it” doesn’t mean it was read
![Page 14: Port Macquarie Base Hospital – Very Early Stages Jo Campbell Project Lead, Whole of Hospital Program Port Macquarie Base Hospital](https://reader036.vdocuments.mx/reader036/viewer/2022062307/551b4289550346d41a8b57c1/html5/thumbnails/14.jpg)
www.health.nsw.gov.au/wohpwww.ecinsw.com.au/neat
Level 4, Sage Building , PO Box 699 T 02 9464 4674 www.ecinsw.com.au
67 Albert Avenue, Chatswood NSW 2067 Chatswood NSW 2057 F 02 9464 4728 ABN 89 809 648 636