Poplar Street Bridge City Arch River Consultant Presentation. December 16, 2011 Room 160, St. Louis District Office. MRB Phase 1 . MRB Phase 1 . PSB Interchange Scope. Remove EB I-70 Ramp Remove and Replace PSB ramp to Memorial/WB I-70 ramp - PowerPoint PPT PresentationTRANSCRIPT
Poplar Street Bridge City Arch River Consultant PresentationDecember 16, 2011Room 160, St. Louis District Office
MRB Phase 1
MRB Phase 1
PSB Interchange Scope Remove EB I-70 Ramp Remove and Replace PSB ramp to Memorial/WB I-70
ramp Remove and Replace SB I-55 Ramp with New Dual
Lane Ramp Remove and Replace NB I-55 Ramp with New Dual
Lane Ramp Convert I-70 Depressed Lanes from 4-Lane to 5-
Lane Section Add Auxiliary Lane Between PSB and New I-70 Exit
Ramp to Washington Avenue
2011 Improvements to PSB
2011 Proposed PSB Interchange Improvements
2011 Proposed PSB Interchange Improvements
I-70 Typical Section in Depressed Area
City Arch River 2015
Land Bridge Over I-70
City Arch River Land Bridge Scope
Improvements to I-70, Memorial Drive, and City Streets
Remove and Replace Walnut Street Bridge Remove Market, Chestnut, and Pine Street Bridges Construct Land Bridge over I-70 Between Market &
Chestnut Remove NB Memorial Drive between Walnut and
existing WB I-70 ramp
Remove SB Memorial Drive between Chestnut and Market
Land Bridge Over I-70
City Arch River I-70 Ramps and 3rd Street /MLK Bridge
Intersection Modifications Remove EB I-70 exit ramp to Memorial Drive and
Replace with new EB I-70 entrance ramp from Washington Ave.
Remove WB I-70 entrance ramp from Memorial Drive and Replace with a new WB I-70 exit ramp to Washington Ave.
Geometric revision to the 3rd Street / MLK Bridge Intersection.
I-70 Ramps to/from Washington Avenue
3rd Street / MLK Intersection Improvements
Schedule for CAR Proposals Due -
1/13/12 Interview Selection-
1/20/12 Interviews- 2/1/12 Final Selection- 2/3/12 Negotiations Done- 3/2/12 Notice to Proceed- 3/9/12
Schedule for PSB Proposals Due -
1/27/12 Interview Selection- 2/7/12 Interviews-
2/17/12 Final Selection-
2/21/12 Negotiations Done-
3/22/12 Notice to Proceed-
3/27/12
Schedule for Ramps & MLK
Proposals Due -2/17/12
Interview Selection- 2/24/12
Interviews- 3/2/12 Final Selection- 3/5/12 Negotiations Done- 4/4/12 Notice to Proceed-
4/11/12
AJR and NEPA Process Combined AJR for PSB / CAR Projects Separate NEPA documents AJR Submittal to FHWA by end of December NEPA for PSB Interchange requires Re-Evaluation
of NMRB EIS NEPA for City Arch River requires EA Approved AJR and Signed NEPA Documents by
May 2012 Some Risk in Moving Forward
Contingencies
CAR – Funding from TIGER Grant
PSB- Approval on TIP ALL 3 – Approval of NEPA and
AJR
Diversity
DBE & Workforce PSB – 20% DBE CAR (Land Bridge) – 20%
DBE Ramps & MLK – 20% DBE
Monthly Workforce Plan
Baseline Survey Control Points to be
provided by City Arch River to insure consistency on all projects.