pompano g.o. bond streetscape...mlk/hammondville rd phase 2 phase 1 mlk blvd. –phase 2 mlk blvd....

8
POMPANO G.O. BOND STREETSCAPE DR. MARTIN LUTHER KING JR. BLVD. RECONSTRUCTION PHASE 2 (BETWEEN NW 10 th AVE. AND NW 6 th AVE.) CITY PROJECT NO. 19356 SECOND PUBLIC OUTREACH MEETING JULY 29, 2019

Upload: others

Post on 16-Jul-2020

13 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: POMPANO G.O. BOND STREETSCAPE...MLK/HAMMONDVILLE RD PHASE 2 PHASE 1 MLK BLVD. –PHASE 2 MLK BLVD. –PHASE 2 PROJECT BACKGROUND LANDSCAPE CONCEPT -2012 MLK BLVD. –PHASE 2 …

POMPANO G.O. BOND STREETSCAPEDR. MARTIN LUTHER KING JR. BLVD. RECONSTRUCTIONPHASE 2 (BETWEEN NW 10th AVE. AND NW 6th AVE.)

CITY PROJECT NO. 19356SECOND PUBLIC OUTREACH MEETING

JULY 29, 2019

Page 2: POMPANO G.O. BOND STREETSCAPE...MLK/HAMMONDVILLE RD PHASE 2 PHASE 1 MLK BLVD. –PHASE 2 MLK BLVD. –PHASE 2 PROJECT BACKGROUND LANDSCAPE CONCEPT -2012 MLK BLVD. –PHASE 2 …

PROJECT BACKGROUND

CONSTRUCTION PHASING - 2014

BLA

NC

HE

ELY

/ 6TH

AVE

ATLANTIC BLVD

I-95

MLK/HAMMONDVILLE RD

PHASE 2PHASE 2 PHASE 1PHASE 1

MLK BLVD. – PHASE 2

Page 3: POMPANO G.O. BOND STREETSCAPE...MLK/HAMMONDVILLE RD PHASE 2 PHASE 1 MLK BLVD. –PHASE 2 MLK BLVD. –PHASE 2 PROJECT BACKGROUND LANDSCAPE CONCEPT -2012 MLK BLVD. –PHASE 2 …

MLK BLVD. – PHASE 2

PROJECT BACKGROUND

LANDSCAPE CONCEPT - 2012

Page 4: POMPANO G.O. BOND STREETSCAPE...MLK/HAMMONDVILLE RD PHASE 2 PHASE 1 MLK BLVD. –PHASE 2 MLK BLVD. –PHASE 2 PROJECT BACKGROUND LANDSCAPE CONCEPT -2012 MLK BLVD. –PHASE 2 …

MLK BLVD. – PHASE 2PREVIOUSLY DESIGNED AND PERMITTED PLANS 

Page 5: POMPANO G.O. BOND STREETSCAPE...MLK/HAMMONDVILLE RD PHASE 2 PHASE 1 MLK BLVD. –PHASE 2 MLK BLVD. –PHASE 2 PROJECT BACKGROUND LANDSCAPE CONCEPT -2012 MLK BLVD. –PHASE 2 …

MLK BLVD. – PHASE 2PROJECT DESCRIPTION –ROADWAY RECONSTRUCTION AND STREETSCAPECOMPLETED PHASE 1 (EAST OF NW 6th AVENUE)

Page 6: POMPANO G.O. BOND STREETSCAPE...MLK/HAMMONDVILLE RD PHASE 2 PHASE 1 MLK BLVD. –PHASE 2 MLK BLVD. –PHASE 2 PROJECT BACKGROUND LANDSCAPE CONCEPT -2012 MLK BLVD. –PHASE 2 …

MLK BLVD. – PHASE 2PROJECT DESCRIPTION –LANDSCAPE & HARDSCAPE BEAUTIFICATION / MULTI‐MODAL / PEDESTIAN SAFETYCOMPLETED PHASE 1 (EAST OF NW 6th AVENUE)

Page 7: POMPANO G.O. BOND STREETSCAPE...MLK/HAMMONDVILLE RD PHASE 2 PHASE 1 MLK BLVD. –PHASE 2 MLK BLVD. –PHASE 2 PROJECT BACKGROUND LANDSCAPE CONCEPT -2012 MLK BLVD. –PHASE 2 …

MLK BLVD. – PHASE 2PROJECT CONSTRUCTION

• MLK PHASE 1 AND 2 WERE PREVIOUSLY FULLY DESIGNED AND PERMITTED.

• SOME PERMITS HAVE EXPIRED FOR PHASE 2 AND ARE CURRENYLY BEING REPROCESSED.

• THE CITY’s INTENT IS TO HAVE THIS PROJECT BE THE FIRST UNDER THE G.O. BOND TO GO UNDER CONSTRUCTION.

• THE CITY IS IN THE PROCESS OF FORMALLY SELECTING THE CONTRUCTION‐MANAGER‐AT‐RISK (CMAR)

• PROJECT SCHEDULECONSTRUCTION COMPLETION – 2021ANTICIPATED CONSTRUCTION DURATION 12‐MONTHS

Page 8: POMPANO G.O. BOND STREETSCAPE...MLK/HAMMONDVILLE RD PHASE 2 PHASE 1 MLK BLVD. –PHASE 2 MLK BLVD. –PHASE 2 PROJECT BACKGROUND LANDSCAPE CONCEPT -2012 MLK BLVD. –PHASE 2 …

#KEITHteam