Functional Location
Functional locations are elements of a technical structure (for example, functional unitswithin a system). Functional locations can be created according to the hierarchy, andcan be structured based on the following criteria:
Functional
Process-related
Spatial
In Plant, Functional location is managed by
Each functional location is managed independently in the system, to:
Description:
Use this transaction for creating structured location
Double CLICK on selected line or press Enter to get following screen
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 3/20
Page 3 of 20
Instructions
In the initial screen, enter the values in the following fields:
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 4/20
Page 4 of 20
After entering required data click on LOCATION TAB
After entering required data click on ORGANISATION TAB
TO GET FOLLOWING SCREEN :
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 5/20
Page 5 of 20
After entering required data click on STRUCTURE TAB
You will reach the following screen
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 6/20
Page 6 of 20
Click on
The Functional Location is saved.
First dismantle the already existing installation and then input / select new installation location and click
on Enter / Continue icon
Click on to Save the changes made and following message will be given by the
system:Functional location XXXXXXXXXXXXXXX changed.
Structural Display of Functional Location
Following Screen will Display:
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 7/20
Page 7 of 20
Double Click on Structural Display, You will find the following Screen:
Execute And you will see the following Screen
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 8/20
Page 8 of 20
Click on expand whole you will see the following Screen and you can find out your newly crated
functional location and its structural display.
Equipment
A piece of equipment is an individual object that is to be maintained independently. Eachpiece of equipment is managed independently in the system, so that you can:.
Description:
Use this transaction for creating & maintaining Equipment
Double click or press Enter Key to reach the following screen
Instructions
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 9/20
Page 9 of 20
For All equipment in XXXXN to select „M ‟
Press Enter key or click on Enter / Continue icon to reach the following screen.
Enter the parameters as detailed below: in „General‟ screen
Click on Location Tab to get the following screen
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 10/20
Page 10 of 20
The field in the Function location blank, so it is to be selected for the Hierarchy Icon.
Click on to Save the Equipment and following message will be given by the
system
Fill Up the above mentioned field as per your requirement for search criteria then Execute button
You will get the following screen
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 11/20
Page 11 of 20
Maintenance Processing
Notifications
Notification is a means, by which internal company notifications like equipmentmalfunctions; breakdowns, maintenance requests or activity reports etc are entered andmanaged in Plant Maintenance.
For the purpose of test equipment calibration, separate notification is to be created
Notifications can be created on Equipment and Functional locations.
After selecting the transaction, press Enter key or double click to reach the following screen
In the Initial screen , you can select the type of Notification and press ENTER key or click on Enter /
Continue icon to reach the next screen
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 12/20
Page 12 of 20
Notification for reporting Transformer /Breakdown (N1)
Notification for recording Activity Report (N2)
Notification for reporting Mal Function Activities (N3)
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 13/20
Page 13 of 20
Notification for Audit Purposes (N4)
With the selected Notifications, following Values are to be entered against
each TAB as applicable to notification type
Each TAB attributes are explained below
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 14/20
Page 14 of 20
Notification Header
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 15/20
Page 15 of 20
In the above screen fields enter the following important values as explained in the following table
Any other values can be obtained from the drop down lists
IMPORTANT : If it is a Breakdown, checkbox ‘Breakdown to be selected.
After entering all the required values, click on to save the Notification.
Notification Processing
Initially Notification will have the status “OSNO” when it is created,
Notification is to be released for changing the status as “NOPR” and after completing the notification, status will
change to “NOCO”, if any order is assigned to this notification, status “ORAS” will be there.
Different Notification Status codes are shown below
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 16/20
Page 16 of 20
Click on release button to release the notification
Enter Notification processing details like, start and completion details as explained in following table
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 17/20
Page 17 of 20
After entering all the required values, click on to save the Notification. And following
message will appear on the screen
Notification – Put in process :
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 18/20
Page 18 of 20
Notification Completion
Notification is to be selected by using transaction codes IW22 / IW28 to reach the following screen
Enter the notification number in Notification box or select from the list
Press Enter key or click on “Notification” to reach the following screen
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 19/20
Page 19 of 20
Enter completion details as explained in following table
Complete the notification by clicking on Complete Flag.
Observe status change from NOPR to NOCO (Notification completion.)
The Notification is completed, If the activity is unsatisfactory, the notification can again be opened and again put
into operation.
7/30/2019 Plant Maintenance-User Manual
http://slidepdf.com/reader/full/plant-maintenance-user-manual 20/20
Plant Maintenance Information System
Area wise, Machine wise and notification Analysis List
Select the required transaction and double click to reach the following screen
Enter selection fields like Equipment, Functional location, Start & end dates, Activity, item or
task codes as per your report requirement