  • Plan de minado 2013

    Andaychagua

  • TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS %Cu %Pb %Zn oz/t Ag PROBADO 4,638,000 4.93 5.14 0.14 1.05 4.90 6.97 146.62 4,068,000 5.19 5.51 0.11 0.94 4.75 6.00 131.84 -570,000 -0.03 -0.11 -0.15 -0.97 PROBABLE 2,802,000 5.22 5.40 0.15 0.84 4.09 5.07 113.06 2,706,000 5.74 6.01 0.18 0.92 5.10 5.97 135.43 -96,000 0.03 0.08 1.01 0.91

    TOTAL 7,440,000 5.07 5.27 0.14 0.97 4.59 6.25 133.98 6,774,000 5.46 5.76 0.14 0.94 4.89 5.99 133.28 -666,000 -0.02 -0.08 0.02 -0.70

    Cut off 2012 Mina Andaychagua 36.90 Alta 54.30 Baja Cut off 2012 Mina Toldorrumi 33.27

    TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS %Cu %Pb %Zn oz/t Ag

    PROBADO 6,250,000 4.27 4.54 0.12 0.97 4.50 6.22 131.77 5,726,000 4.40 4.75 0.10 0.87 4.34 5.38 118.81 -524,000 -0.02 -0.09 -0.15 -0.84

    PROBABLE 4,817,000 4.09 4.34 0.12 0.74 3.87 4.23 97.78 4,796,000 4.39 4.69 0.13 0.77 4.43 4.63 108.87 -21,000 0.01 0.04 0.56 0.40

    TOTAL 11,067,000 4.18 4.44 0.12 0.87 4.22 5.36 116.97 10,522,000 4.40 4.72 0.11 0.83 4.38 5.04 114.28 -545,000 -0.02 -0.09 -0.13 -0.79

    TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS %Cu %Pb %Zn oz/t Ag

    MEDIDO 953,000 3.83 4.24 0.09 1.00 4.26 5.72 123.53 1,064,000 3.65 4.02 0.11 0.75 3.27 4.14 91.80 111,000 0.03 -0.25 -0.99 -1.58

    INDICADO 1,395,000 3.86 4.11 0.08 0.33 2.08 2.56 54.57 1,684,000 3.66 3.98 0.07 0.30 1.95 2.27 49.51 289,000 -0.01 -0.02 -0.14 -0.29

    TOTAL 2,348,000 3.84 4.18 0.09 0.60 2.97 3.84 82.56 2,748,000 3.66 4.00 0.09 0.48 2.46 3.00 65.88 400,000 0.00 -0.09 -0.37 -0.65

    TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS %Cu %Pb %Zn oz/t Ag

    INFERIDO 5,015,000 0.22 0.48 3.31 3.70 84.26 5,099,000 0.17 0.45 3.11 3.49 79.14 84,000 -0.05 -0.04 -0.20 -0.21

    TOTAL 5,015,000 0.22 0.48 3.31 3.70 84.26 5,099,000 0.17 0.45 3.11 3.49 79.14 84,000 -0.05 -0.04 -0.20 -0.21

    COMPARACION DE RECURSOS MINA ANDAYCHAGUA DICIEMBRE 2011 A JUNIO 2012

    RECURSOSMINA ANDAYCHAGUA DICIEMBRE 2011 MINA ANDAYCHAGUA A JUNIO 2012 COMPARACION

    COMPARACION DE RECURSOS MINA ANDAYCHAGUA DICIEMBRE 2011 A JUNIO 2012

    RECURSOSMINA ANDAYCHAGUA DICIEMBRE 2011 MINA ANDAYCHAGUA A JUNIO 2012 COMPARACION

    COMPARACION DE RESERVAS MINA ANDAYCHAGUA DICIEMBRE 2011 A JUNIO 2012

    RESERVASMINA ANDAYCHAGUA DICIEMBRE 2011 MINA ANDAYCHAGUA A JUNIO 2012 COMPARACION

    RESERVASRESERVAS DE MINERAL VETA ANDAYCHAGUA DIC-2011 RESERVAS DE MINERAL VETA ANDAYCHAGUA A JUNIO 2012 COMPARACION

    COMPARACION DE RESERVAS VETA ANDAYCHAGUA DICIEMBRE 2011 A JUNIO 2012

    Variacin de Reservas 2011-2012 TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS %Cu %Pb %Zn oz/t Ag

    PROBADO 4,638,000 4.93 5.14 0.14 1.05 4.90 6.97 146.62 4,068,000 5.19 5.51 0.11 0.94 4.75 6.00 131.84 -570,000 -0.03 -0.11 -0.15 -0.97 PROBABLE 2,802,000 5.22 5.40 0.15 0.84 4.09 5.07 113.06 2,706,000 5.74 6.01 0.18 0.92 5.10 5.97 135.43 -96,000 0.03 0.08 1.01 0.91

    TOTAL 7,440,000 5.07 5.27 0.14 0.97 4.59 6.25 133.98 6,774,000 5.46 5.76 0.14 0.94 4.89 5.99 133.28 -666,000 -0.02 -0.08 0.02 -0.70

    Cut off 2012 Mina Andaychagua 36.90 Alta 54.30 Baja Cut off 2012 Mina Toldorrumi 33.27

    TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS %Cu %Pb %Zn oz/t Ag

    PROBADO 6,250,000 4.27 4.54 0.12 0.97 4.50 6.22 131.77 5,726,000 4.40 4.75 0.10 0.87 4.34 5.38 118.81 -524,000 -0.02 -0.09 -0.15 -0.84

    PROBABLE 4,817,000 4.09 4.34 0.12 0.74 3.87 4.23 97.78 4,796,000 4.39 4.69 0.13 0.77 4.43 4.63 108.87 -21,000 0.01 0.04 0.56 0.40

    TOTAL 11,067,000 4.18 4.44 0.12 0.87 4.22 5.36 116.97 10,522,000 4.40 4.72 0.11 0.83 4.38 5.04 114.28 -545,000 -0.02 -0.09 -0.13 -0.79

    TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS %Cu %Pb %Zn oz/t Ag

    MEDIDO 953,000 3.83 4.24 0.09 1.00 4.26 5.72 123.53 1,064,000 3.65 4.02 0.11 0.75 3.27 4.14 91.80 111,000 0.03 -0.25 -0.99 -1.58

    INDICADO 1,395,000 3.86 4.11 0.08 0.33 2.08 2.56 54.57 1,684,000 3.66 3.98 0.07 0.30 1.95 2.27 49.51 289,000 -0.01 -0.02 -0.14 -0.29

    TOTAL 2,348,000 3.84 4.18 0.09 0.60 2.97 3.84 82.56 2,748,000 3.66 4.00 0.09 0.48 2.46 3.00 65.88 400,000 0.00 -0.09 -0.37 -0.65

    TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS AV AL %Cu %Pb %Zn oz/t Ag U.S.$ TMS %Cu %Pb %Zn oz/t Ag

    INFERIDO 5,015,000 0.22 0.48 3.31 3.70 84.26 5,099,000 0.17 0.45 3.11 3.49 79.14 84,000 -0.05 -0.04 -0.20 -0.21

    TOTAL 5,015,000 0.22 0.48 3.31 3.70 84.26 5,099,000 0.17 0.45 3.11 3.49 79.14 84,000 -0.05 -0.04 -0.20 -0.21

    COMPARACION DE RECURSOS MINA ANDAYCHAGUA DICIEMBRE 2011 A JUNIO 2012

    RECURSOSMINA ANDAYCHAGUA DICIEMBRE 2011 MINA ANDAYCHAGUA A JUNIO 2012 COMPARACION

    COMPARACION DE RECURSOS MINA ANDAYCHAGUA DICIEMBRE 2011 A JUNIO 2012

    RECURSOSMINA ANDAYCHAGUA DICIEMBRE 2011 MINA ANDAYCHAGUA A JUNIO 2012 COMPARACION

    COMPARACION DE RESERVAS MINA ANDAYCHAGUA DICIEMBRE 2011 A JUNIO 2012

    RESERVASMINA ANDAYCHAGUA DICIEMBRE 2011 MINA ANDAYCHAGUA A JUNIO 2012 COMPARACION

    RESERVASRESERVAS DE MINERAL VETA ANDAYCHAGUA DIC-2011 RESERVAS DE MINERAL VETA ANDAYCHAGUA A JUNIO 2012 COMPARACION

    COMPARACION DE RESERVAS VETA ANDAYCHAGUA DICIEMBRE 2011 A JUNIO 2012

  • Programa de produccin:

    Programa avances:

    Etapa ene-13 feb-13 mar-13 abr-13 may-13 jun-13 jul-13 ago-13 sep-13 oct-13 nov-13 dic-13 Total 2013

    Explotacion 110 110 110 110 110 110 110 110 110 110 110 110 1320

    Desarrollo 497 543 524 496 470 493 457 410 370 415 417 518 5610

    Exploracion 50 50 50 50 50 50 50 50 50 50 50 50 600

    Preparacion 229 220 292 234 275 242 230 288 343 386 342 288 3369

    Infraestructura 80 80 40 55 55 90 90 90 65 65 25 25 385

    Raise Borer 100 100 150 150 130 110 132 85 110 120 100 1287

    Total 1066 1103 1166 1095 1090 1095 1069 948 1023 1136 1064 1091 12571

    Datos ene-13 feb-13 mar-13 abr-13 may-13 jun-13 jul-13 ago-13 sep-13 oct-13 nov-13 dic-13 Total 2013

    TMS 68000 62500 68000 67000 68000 67000 70000 70000 69000 70000 69000 70000 818,500

    %Cu 0.08 0.12 0.07 0.14 0.10 0.10 0.09 0.14 0.07 0.14 0.07 0.14 0.11

    %Pb 0.95 0.78 1.02 0.90 0.89 1.00 1.00 0.91 1.07 0.91 1.04 0.91 0.95

    % Zn 4.62 4.41 4.82 4.50 4.70 4.41 4.61 4.98 4.78 4.72 4.81 4.67 4.67

    Ag oz 5.47 5.57 5.44 5.74 5.47 5.86 5.71 5.69 5.70 5.71 5.69 5.80 5.65

  • Programa de produccin Andaychagua por Zonas:Zona Datos ene-13 feb-13 mar-13 abr-13 may-13 jun-13 jul-13 ago-13 sep-13 oct-13 nov-13 dic-13 Total 2013

    Alta TMS 32,000 22,500 32,500 33,500 28,000 34,500 34,000 27,000 31,500 32,000 32,000 30,500 370,000

    %Cu 0.01 0.02 0.02 0.07 0.02 0.08 0.02 0.09 0.02 0.08 0.02 0.08 0.05

    %Pb 0.34 0.51 0.41 0.55 0.42 0.58 0.40 0.62 0.41 0.58 0.41 0.60 0.48

    % Zn 1.19 1.62 1.48 2.21 1.50 2.35 1.43 2.49 1.45 2.25 1.46 2.29 1.81

    Ag oz 3.26 4.48 3.36 4.04 3.45 4.35 3.74 4.38 3.50 4.08 3.59 4.19 3.85

    Baja TMS 36,000 40,000 35,500 33,500 40,000 32,500 36,000 43,000 37,500 38,000 37,000 39,500 448,500

    %Cu 0.14 0.18 0.12 0.21 0.16 0.13 0.15 0.18 0.11 0.19 0.11 0.18 0.16

    %Pb 1.50 0.93 1.58 1.25 1.23 1.45 1.57 1.09 1.63 1.18 1.57 1.16 1.34

    % Zn 7.66 5.99 7.88 6.79 6.95 6.60 7.62 6.55 7.58 6.80 7.70 6.51 7.04

    Ag oz 7.43 6.18 7.35 7.44 6.88 7.46 7.57 6.51 7.55 7.09 7.50 7.04 7.14

    0

    10,000

    20,000

    30,000

    40,000

    50,000

    ene-13 feb-13 mar-13 abr-13 may-13 jun-13 jul-13 ago-13 sep-13 oct-13 nov-13 dic-13

    Produccion por Zonas

    Baja TMS

    Alta TMS

  • Tajeos Zona Alta y Recuay 2013

    LEYENDA

    PROGRAMA PRODUCCION 2013

    PROGRAMA AVANCE 2013

    Nv_800

    Nv_620

    Nv_470

    Nv_540

    TJ_1300 (8,000 TMS Zn 2.27%, Ag 3.93Oz)

    TJ_1400, TJ_1500 (77,000 TMS Zn 1,07%, Ag 3.44Oz)

    TJ_1300, TJ_1400, TJ_1500 (100,000 TMS Zn 1,15%, Ag 3,6Oz)

    TJ_1200, TJ_1300, TJ_1400 (58,000 TMS Zn 1,51%, Ag 5.01Oz)

  • Tajeos Zona Baja 2013

    LEYENDA

    PROGRAMA PRODUCCION 2013

    PROGRAMA AVANCE 2013

    Nv_800

    Nv_1050

    Nv_1100

    Nv_1000

    TJ_300 (45,000 TMS Zn 4.5%, Ag 3.43Oz)

    TJ_300 y TJ_400 (112,000 TMS Zn

    6.92%, Ag 3.33Oz)

    TJ_600 y TJ_1100 (55,000 TMS Zn 6.2%,

    Ag 15.11Oz)

    TJ_400, TJ_500, TJ_600 y TJ_1100 (140,000 TMS Zn 14,05%, Ag 20.8Oz)

    Nv_1150

    TJ_400, TJ_500 (60,000 TMS Zn

    5,11%, Ag 2.7Oz)

    TJ_1100 (15,000 TMS Zn 3,9%, Ag

    12.86Oz)

  • Programa de relleno:

    Relleno detrtico

    Relleno cementado

    Metodo Zona ene-13 feb-13 mar-13 abr-13 may-13 jun-13 jul-13 ago-13 sep-13 oct-13 nov-13 dic-13

    OCF Alta 0 0 0 0 0 0 0 0 0 0 0 0

    SLS Alta 0 0 0 0 0 0 0 0 0 0 0 0

    UCF Alta 136 1,226 2,043 3,406 1,771 3,406 1,635 2,724 2,043 3,133 2,043 2,861

    Baja 9,809 10,896 9,673 8,583 10,627 8,852 9,672 11,715 9,808 10,080 9,945 10,625

    Total 2013 9,945 12,122 11,716 11,989 12,398 12,258 11,307 14,439 11,851 13,213 11,988 13,486

    Metodo ExplotZona ene-13 feb-13 mar-13 abr-13 may-13 jun-13 jul-13 ago-13 sep-13 oct-13 nov-13 dic-13

    OCF Alta 993 868 993 1,737 1,241 1,737 1,365 496 1,365 1,364 1,365 1,240

    SLS Alta 7,395 4,662 6,752 5,145 5,626 4,823 7,396 4,822 6,431 5,144 6,270 4,983

    UCF Alta 0 0 0 0 0 0 0 0 0 0 0 0

    Baja 0 0 0 0 0 0 0 0 0 0 0 0

    Total 2013 8,388 5,530 7,745 6,882 6,867 6,560 8,761 5,318 7,796 6,508 7,635 6,223

  • Programa sostenimiento:

    Elemento Etapa ene-13 feb-13 mar-13 abr-13 may-13 jun-13 jul-13 ago-13 sep-13 oct-13 nov-13 dic-13

    Shotcrete Explotacion 1791 1546 1726 1686 1701 1676 1801 1686 1751 1731 1746 1721

    Desarrollo 836 879 855 810 770 764 785 694 674 662 727 782

    Exploracion 153 84 132 158 158 137 231 252 268 200 263 195

    Preparacion 204 222 287 238 267 237 239 318 337 379 337 320

    Infraestructura 56 56 23 23 68 68 68 67 45 34 34

    Total Shotcrete 3040 2788 2999 2914 2918 2881 3124 3019 3097 3017 3107 3051

    P Hidrabolt Explotacion 4,890 3,990 4,610 4,430 4,475 4,380 4,870 4,330 4,670 4,520 4,645 4,475

    Total Hidrabolt 4890 3990 4610 4430 4475 4380 4870 4330 4670 4520 4645 4475

    P Split set Desarrollo 1267 1236 1081 1028 1008 1045 1072 949 940 1018 1229 1459

    Exploracion 445 246 384 461 461 399 676 737 783 584 768 568

    Preparacion 591 644 834 690 775 686 693 937 993 1117 993 942

    Explotacion 338 338 338 338 338 338 338 338 338 338 338 338

    Infraestructura 0 0 0 0 0 0 0 98 33 0 0

    Total Split set 2642 2463 2637 2516 2582 2469 2779 2962 3153 3090 3328 3307

    P Helicoidal Desarrollo 1748 1908 1962 1859 1712 1675 1739 1522 1467 1389 1425 1446

    Exploracion 176 97 152 182 182 158 267 291 309 230 303 224

    Preparacion 173 186 234 197 219 197 198 248 262 294 262 238

    Infraestructura 179 179 73 73 212 212 212 131 114 106 106

    Total Helicoidal 2276 2369 2347 2311 2185 2241 2416 2273 2169 2027 2096 2015

  • Diseo de Mina 2013

    Andaychagua

  • Profundizacin mina 2012

    Zona explotada

    Reservas probadas

    Reservas probables

    Labores de diseo 2012

  • Profundizacin mina 2013

    Zona explotada

    Reservas probadas

    Reservas probables

    Labores de diseo 2012

  • Profundizacin 2012

    Profundizacin 2013

    Rampa de avance mas larga.

    Rampa profundizacin corta

    Pilares centrales

    Gaviotas a 20m veta

    Accesos a 25 m.

    Bypass superpuestos a 60 m de veta

    Bypass traslapados a 70 m de veta

    Distancia de rampa a veta 80 m

    Distancia de rampa a veta 110 m

  • Puente entre vueltas de RP 14m.

    Puente entre vueltas de RP 24m.Intersecciones

    en cruz

    Intersecciones en cruz

    Profundizacin 2012

    Profundizacin 2013

    Cruceros y gaviotas superpuestas

    Cruceros y gaviotas traslapados

  • Plan de minado 2013

    Toldorrumi

  • Datos ene-13 feb-13 mar-13 abr-13 may-13 jun-13 jul-13 ago-13 sep-13 oct-13 nov-13 dic-13 Total 2013

    TMS 12000 11000 12000 11800 12000 11800 11000 11000 13800 14000 13800 14000 148,200

    %Cu 0.02 0.02 0.02 0.02 0.02 0.02 0.03 0.02 0.03 0.03 0.03 0.03 0.03

    %Pb 0.18 0.13 0.18 0.18 0.17 0.21 0.20 0.13 0.15 0.16 0.15 0.15 0.17

    %Zn 4.65 4.90 4.65 4.66 4.81 4.83 4.71 4.66 4.58 4.56 4.57 4.55 4.67

    Oz-Ag 1.08 1.03 1.08 1.05 1.05 0.95 1.51 1.25 1.39 1.42 1.46 1.48 1.24

    Programa de produccin:

    Programa avances:

    Etapa ene-13 feb-13 mar-13 abr-13 may-13 jun-13 jul-13 ago-13 sep-13 oct-13 nov-13 dic-13 Total 2013

    Explotacion

    Desarrollo

    Exploracion

    Preparacion 30 30 35 35 60 30 30 30 20 30 20 30 380

    Infraestructura

    Raise Borer

    Total 30 30 35 35 60 30 30 30 20 30 20 30 380

  • ESTRUCTURA TMS %Cu %Pb %Zn Oz-Ag

    T-Cuerpo Charito 58,000 0.01 0.07 5.25 0.40

    T-Cuerpo Inferior 306 10,000 0.02 0.18 3.63 1.29

    T-Cuerpo Rocio 24,000 0.03 0.12 2.63 0.72

    T-Manto A 12,000 0.05 0.16 13.79 1.90

    T-Manto B 15,200 0.05 0.27 3.72 2.98

    T-Manto C 11,000 0.03 0.50 2.31 2.04

    T-Manto D 13,000 0.03 0.27 1.69 2.87

    T-Manto Gladys 5,000 0.06 0.12 3.78 0.49

    Total 2013 148,200 0.03 0.17 4.67 1.24

    TMS

    T-Cuerpo Charito

    T-Cuerpo Inferior 306

    T-Cuerpo Rocio

    T-Manto A

    T-Manto B

    T-Manto C

    T-Manto D

    T-Manto Gladys

    Total 2013

    Programa de produccin Toldorrumi por Estructuras:

  • Programa Relleno detrtico

    Zona Metodo Explotene-13 feb-13 mar-13 abr-13 may-13 jun-13 jul-13 ago-13 sep-13 oct-13 nov-13 dic-13

    Alta OCF 2,976 2,728 2,977 2,927 2,977 2,928 2,729 2,729 3,424 3,474 3,424 3,473

    Total 2013 2,976 2,728 2,977 2,927 2,977 2,928 2,729 2,729 3,424 3,474 3,424 3,473

    Programa sostenimiento:

    Elemento Etapa ene-13 feb-13 mar-13 abr-13 may-13 jun-13 jul-13 ago-13 sep-13 oct-13 nov-13 dic-13

    SHOTCRETE Desarrollo 95 142 142 142 142 153 159 159 159 159 142 95

    Exploracion 109 77 89 78 67 67 89 67 100 78 89 67

    Preparacion 74 33 39 39 67 33 33 33 22 33 22 33

    Explotacion 360 330 360 354 360 354 330 330 414 420 414 420

    Total Shotcrete 638 583 630 613 636 607 611 589 695 690 667 615

    P Hidrabolt Explotacion 1,080 990 1,080 1,062 1,080 1,062 990 990 1,242 1,260 1,242 1,260

    Total Hidrabolt 1080 990 1080 1062 1080 1062 990 990 1242 1260 1242 1260

    P Split set Exploracion 319 227 262 229 196 196 262 196 294 229 262 196

    Preparacion 98 98 115 115 196 98 98 98 65 98 65 98

    Total Split set 3215 2888 3166 3080 3188 3026 2951 2863 3539 3537 3479 3429

    P Helicoidal Desarrollo 297 446 446 446 446 454 458 458 458 458 446 297

    Exploracion 98 62 66 58 50 50 66 50 75 58 66 50

    Preparacion 152 25 29 29 50 25 25 25 17 25 17 25

    Total Helicoidal 548 533 541 533 545 529 550 533 550 541 529 372

  • Diseo de Mina 2013

    Toldorrumi

  • Cuerpo Charito:

    AC_242

    AC_267

    34 m

    Por AC_267 se tiene 3 cortes (12m) para explotar.Por AC_242 se tiene 7 cortes (28m) para explotar.

    TAJO TOLDORRUMI SUR

  • Cuerpo Rocio:

    AC_751

    AC_892

    26 m

    AC_393

    RP_670

    11.5m

    10m

    Por AC_892 se explotara 3 cortes (labor concluida). Por AC_751 se explotara 2 cortes (labor concluida).Por AC_393 se explotara 6 cortes (labor concluida) se realizara preparacion en mineral.

    TAJO TOLDORRUMI CENTRAL

    AC_750 (acceso actual de minado

  • Cuerpo Rocio:

    AC_242

    AC_267

    34 m

    Por AC_892 se explotara 3 cortes (labor concluida). Por AC_751 se explotara 2 cortes (labor concluida).Por AC_393 se explotara 6 cortes (labor concluida) se realizara preparacion en mineral.