Physics Division “BIA-Like” Projects

L. S. Cardman

Page 2: Physics Division “BIA-Like” Projects L. S. Cardman

Hall A BIA-like Projects1. Upgrade of the slow-controls system - $300k

Upgrade needed to replace obsolete equipment, no longer in production. Spares have been depleted or nearly depleted.

Systems included are (1) cryogenic control systems, (2) HRS controls (e.g. VME IOCs for magnet controls),  (3) measurement instrumentation and, (4) rebuild of the various magnet power supplies internal electronics.

Cost based on external group estimates (e.g. cryo group ~ 100 k$), quotes from vendors and catalog items.

2. DAQ upgrade for the two HRSs - $600kThe upgrade is needed to (a) replace obsolete components and (b) achieve substantially higher data acquisition rates using pipelined electronics.  (Note:  one of these was originally in the project and "de-scoped" while the second was never in the project but is equally necessary for the planned 12 GeV experimental program)

3. Recondition vacuum system and exit beam pipe - $110kSeveral sections of the exit beam pipe show signs of corrosion caused by chemical compounds generated when running beam in the hall.

Cost estimate based on previous experience. 

Page 3: Physics Division “BIA-Like” Projects L. S. Cardman

Hall A BIA-like Projects

4. Replace Wika cryo-valves by regular JLab valves - $100kThe Wika cryo-valves have the control electronics in the valve head.  Due to their locations on the magnets, the valves are exposed to large amounts of radiation which affects their operation & calibration causing instabilities in the cryogenic distribution system of Hall A & magnet crashes.

Cost estimate provided by cryo group

5. Expand gas shed - $75kExpand gas shed to house larger gas distribution system capable of handling additional detectors (e.g. GEMs of Super-Big-Bite and Big-Bite)

Cost estimate based on previous experience

6. Upgrade controls of HRS bogie system - $50kMost of the system components are no longer available including the servo amplifiers and motors.

Cost estimate based on catalog items.

Page 4: Physics Division “BIA-Like” Projects L. S. Cardman

Hall A BIA-like Projects

7. Replace front-end electronics of HRS VCDs - $75kIncrease event rate capability of HRS VDCs.

Cost based on catalog & previous purchases.

8. Upgrade first layer of trigger scintillators - $80kIncrease thickness of first plane of trigger scintillators to improve timing resolution. Upgrade will improve particle discrimination by time-of-flight.

Cost based on catalog items & previous purchases.

9. Recondition A1 aerogel detector - $150kDetector refurbishing for upcoming experiments. 

Cost based on catalog items.

Sum of all nine Hall A projects - $1,540k

Page 5: Physics Division “BIA-Like” Projects L. S. Cardman

Hall B “BIA-like” Projects

Remove CLAS $1,201k

SVT Infrastructure/Workshop $ 523k

Upgraded Readout boards for CLAS12 $ 306k

Sum of all three Hall B projects$2,030k

Page 6: Physics Division “BIA-Like” Projects L. S. Cardman

Drift chambersargon/CO2 gas, 35,000 cells

Electromagnetic calorimetersLead/scintillator, 1296 PMTs

Torus magnet6 superconducting coils

Gas Cherenkov counterse/p separation, 216 PMTs

Time-of-flight countersplastic scintillators, 684 PMTs

Large angle calorimetersLead/scintillator, 512 PMTs

CEBAF Large Acceptance Spectrometer (CLAS)

Page 7: Physics Division “BIA-Like” Projects L. S. Cardman

CLAS Component Remove from HALL ?

Temporary Storage?

Re-use in CLAS12? Permanent Storage needed?

SOUTH CLAMSHELL ✓ N/A NO NO

NORTH CLAMSHELL ✓ N/A NO NO

FORWARD CARRIAGE NO N/A ✓ HALL B

EC NO N/A ✓ HALL B

TOF Panel 1 ✓ ✓ ✓ HALL B

TOF Panel 2 ✓ ✓ partial HALL C - partial

TOF Panel 3 & 4 ✓ NO NO HALL C

LTCC ✓ ✓ ✓ HALL B

DC R1 ✓ NO Considered EEL

DC R2, R3 ✓ NO NO NO

IC ✓ EEL ✓ EEL

TORUS Magnet ✓ NO NO NO

CRYO TARGET ✓ YES ✓ w/ mod. HALL B

POL. TARGET N/A EEL NO NO

HYCAL ✓ NO NO ??

BPM 2H01 ✓ ✓ ✓ HALL B

TAGGER Magnet NO N/A ✓ HALL B

PAIR Spectrometer NO N/A ✓ HALL B

MOLLER Polarimeter NO N/A ✓ HALL B

GONIOMETER NO N/A ✓ HALL B

Faraday Cup NO N/A ✓ HALL B

Page 8: Physics Division “BIA-Like” Projects L. S. Cardman

CLAS Removal Summary

• Start 5/15/2012 – Finish 10/26/2012

• Schedule as presented based on single shift – Goal is to be ready for Torus installation when Magnet arrives since it must be

first and will take up most of the Hall

• Schedule has ~14000hrs in 120 work days thus average crew is 14 people

• Major contracts– North and South Clam Shell Removal - 27 days – Torus Removal– 15 days

March 2009 Installation Review

Page 9: Physics Division “BIA-Like” Projects L. S. Cardman

CLAS Removal Cost EstimateHuman Resources Man Hours FTE Cost in (K$)Mechanical technician 3520 2 140.8Crane operator 704 0.4 28.16Rigger 440 0.25 17.6Forklift operator 440 0.25 17.6Cryogenics engineer 264 0.15 16.5Cryo/vacuum technician 440 0.25 17.6Cable technician supervisor 1760 1 70.4Cable technician 3520 2 140.8other support 880 0.5 35.2Mechanical engineer 704 0.4 44Electrical engineer (electronics) 880 0.5 55Work coordinator 880 0.5 35.2Total number of hours 13675.2 8.2 618.86

Major contracts Cost in (K$)North and South Clam Shell removal 225Torus removal contract 150Forklift and expenses 90Sum of proc. and expenses 465

Resources/Preparation and Training MW FTEs Cost in (K$)Engineer 6.6 0.15 10.56Hall Coordinator 11 0.25 27.5Scientist/management 6.6 0.15 0New technicians training 55 1.25 88Total 126.06

Total Cost 1209.92

Note: We estimate that $176k of the Labor can come from current Hall B Technical Staff

Page 10: Physics Division “BIA-Like” Projects L. S. Cardman

Upgrade of CLAS12 ADB to DCRB• Plan at the time of the CD-3 review (5/08) for the drift chamber

readout system included:– The original CLAS Amplifier Discriminator Board (ADB), – The multiplexing circuit, – The Level 2 Segment Finding System and – The FastBus 1877 TDC.

• Proposed upgrade idea – Eliminates the need for very old FastBus crates and LeCroy 1877 TDC modules. – The superlayer track finding function could be added at any time and would

take advantage of the Crate Trigger Processor (CTP) already designed for the 12GeV trigger systems

Page 11: Physics Division “BIA-Like” Projects L. S. Cardman

Overview of the Proposed DCRB

The proposed new CLAS12 Drift Chamber Readout Board (DCRB) would include:

• A complete upgrade of the ADB module. Amplifier and discriminator functions would remain virtually identical to the original ADB module but the pulse width circuitry and ECL output drivers would be eliminated. The common threshold voltage for the discriminator function would be programmable through VME and the test pulse control for each group of sixteen amplifier channels would also be retained and controlled through VME.

• A single FPGA would be added to the new DCRB to capture the output hits from each drift chamber wire that crosses threshold, and produce a TDC value for these wire outputs with a resolution of 1ns. The TDC values would be readout through VME upon receipt of a system readout trigger.

• Scaler functions could be implemented to count wire hits or other values which would be very useful for monitoring purposes.

• The FPGA would also process these discriminated signals and serially transmit to the central Crate Trigger Processor. The CTP function would be programmed to produce a trigger signal based on the track segments of two superlayers. The CTP would be collecting the 96 discriminated signals from each DCRB at the same time and streaming this trigger information forward to the global trigger crate.

Page 12: Physics Division “BIA-Like” Projects L. S. Cardman

96 Channel DCRB

Page 13: Physics Division “BIA-Like” Projects L. S. Cardman

Cost Estimate for DCRB

Bottom Line: $306k

Page 14: Physics Division “BIA-Like” Projects L. S. Cardman

SVT InfrastructureCleanroom Infrastructure Equipment (not including cleanroom construction)

# Item Qty Cost Per Item Total Manufacturer Comments

1 Dry Storage Containment System 1 $11,792 $11,792Terra Universal  

2 UNH Laser Driver & equipment 1 $31,220 $31,220BNC Has 1064 module (24.7K) & pulser (6.5K)

3 Vacuum pickup pen 1 $2,765 $2,765Terra Universal  

4 DryClean SnowBox 1 $9,450 $9,450Terra Universal  

5 Dual Purge for Glove Box 1 $2,586 $2,586Terra Universal  

6 Replacement Gloves 1 $296 $296Terra Universal  

7 RB Valve for Glove Box 1 $307 $307Terra Universal  

8 NitroWatch Controller 1 $866 $866Terra Universal  

9 NitroWatch/Humex Sensor 1 $490 $490Terra Universal  

10 SnoGun II Dry Ice Cleaner 1 $1,975 $1,975Terra Universal  

11 Vacuum Cleaner; MicoVac Portable Cleanroom 1 $955 $955Terra Universal  

12 Portable Wire-Bond Strength Tester 1 $2,765 $2,765Terra Universal  

13 Cleaner for compoents (plasma) 1 $12,508 $12,508Terra Universal  

14 48 x48 x 24 Module Dark Box (module tests) 1 $602 $602ThorLabs  

15 Probe Station Automation equipment 1 $57,000 $57,000Cascade Microtech Includes interface hardware and software

16 Probe Station Microscope Video Capture and Measurement System 1 $8,461 $8,461MIS  

17 Probe Test Station Isolation Table 1 $5,765 $5,765Cascade Microtech  

18 Probe Station Dark Box 1 $6,159 $6,159Cascade Microtech  

19 Probe Test Station Iso Table/Dark Box Adapter 1 $1,780 $1,780Cascade Microtech  

20 Probe Test Station Dark Box-Light Tight feed thru for chuck, video, prober 1 $316 $316Cascade Microtech  

21 Probe Test Station Test Equipment Interface (Triax & coax feed-throughs) 1 $1,677 $1,677Cascade Microtech  

22 Probe station Kelvin probes 2 $3,490 $6,980Cascade Microtech  

23 Probe station card adapter for FSSR2 1 $3,500 $3,500Cascade Microtech  

24 Coordinate Measurement Machine Brown and Sharp Optive w/ White Light Sensor 1 $150,000 $150,000Brown and Sharp  

25 GPIB Controller 1 $549 $549National Instruments  

26 SVT Module Environment Test Station 1 $16,885 $16,885Assoc Environmental Sys  

27 ETC (environmental test station) Instrumentation 1 $7,974 $7,974National Instruments  

28 Upgrade of wirebonder to semiautomatic & extended range for SVT module repair 1 TBD TBD  Needed to repair modules

        $345,623 Total  

             

Test Hardware & Software# Item Qty Cost Per Item Total Manufacturer Comments1 Tektronix scope & Probes 1 $30,388 $30,388Tektronix  

2 Replacement of long-term loaned equipment for MSU (NIM bin, HV supply, signal generator) 1 $19,200 $19,200Multiple  

3 Altera License Renewals 1 $2,495 $2,495Altera  

4 Xilinx Software 2 $5,195 $10,390Xilinx  

5 Labview & Daq Software Updates 1 $11,129 $11,129National Instruments  

6 Mixed Signal Scope 1 $16,310 $16,310Agilent  

7 Surface mount equipment (itemized list) 1 $17,860 $17,860Multiple  

8Multiplexer System (probe station)

1 $28,755 $28,755TestMart (vendor for Keithley)  

9 CAEN Test equipment 1 $26,672 $26,672CAEN  

10 DAq PCB Test Station & Docking Station 1 $4,980 $4,980HP  

11 SVT Test Station computers 3 $2,500 $7,500Dell  

12 Tektronix Preamplifier 1 $2,000 $2,000Tektronix  

        $177,679Total  

Grand Total: $523k

Page 15: Physics Division “BIA-Like” Projects L. S. Cardman

Hall C “Must for FY11” Projects

1. SOS Removal - $500kSOS work is moved into this year because: a) analysis of SHMS installation schedule shows that things are tight, so any work we can do earlier helps.  b) a trial cut of the SOS shows that cutting the SOS can be done without a large mess, so some chopping up of the SOS can happen in FY11. 

$170 is an estimate from Walter Kellner for hiring contractors for cutting and for disposal of radioactive wastes.  $75 is for 2 techs working ~6 months on SOS disassembly. $15 for radcon support.  (should this be no charge?)

NOTE: $135 of this request is for Hall C labor, so requires changing money flavor from COPS salaries to BIA/Capital codes.

Page 16: Physics Division “BIA-Like” Projects L. S. Cardman

Hall C “Must Eventually” Projects

1. Compton and beamline design - $250kAre part of beamline reconfiguration for Compton.

The amounts are based on reasonable estimate of how much labor would be available.  The work this year would also help to solidify overall cost estimates.

2. HMS Wire chambers - $150kHU is building SHMS wire chambers and has offered to build replacement HMS chambers, funded by JLab.  Want to get this started while SHMS chambers in progress to have the benefit of experienced people.  $75K is just a guess about how much could be spent in terms of parts and student labor.

3. DAQ Upgrade - $350kBrad Sawatzky estimates a cost of $350k to upgrade Hall C electronics to multihit/pipeline trigger/electronics.  $100K this year is to get started by joining Hall D Flash ADC purchases.

Page 17: Physics Division “BIA-Like” Projects L. S. Cardman

Cost Summary – Hall A

FY11 FY12 FY13 FY14 FY15Total Cost Comments

Hall AUpgrade of the slow-controls system $150 $150 $300

DAQ upgrade for the two HRS $300 $300 $600$300k ws originally in Project – Rescope?

Recondition vacuum system and exit beam pipe $55 $55 $110Replace Wika cryo-valves by regular JLab valves $50 $50 $100Expand gas shed $40 $35 $75Upgrade controls of HRS bogie system $25 $25 $50Replace front-end electronics of HRS VCDs $40 $35 $75Upgrade first layer of trigger scintillators $40 $40 $80Recondition A1 aerogel detector $75 $75 $150

Hall A Totals $0 $775 $765 $0 $0 $1,540

Page 18: Physics Division “BIA-Like” Projects L. S. Cardman

Cost Summary – Hall B

FY11 FY12 FY13 FY14 FY15Total Cost Comments

Hall B

CLAS Removal

Physics Division Labor $6 $141 $29 $176

non-Division Labor (Eng. & contract) $0 $400 $43 $443

Major Contracts $20 $350 $95 $465

Resources/Preparation and Training $35 $77 $14 $126

SVT Infrastructure $250 $273 $523Part of real project scope?

Upgrade of CLAS12 ADB $150 $156 $306Part of real project scope?

Hall B Totals $61 $1,368 $610 $0 $0 $2,039

Page 19: Physics Division “BIA-Like” Projects L. S. Cardman

Cost Summary – Hall C

FY11 FY12 FY13 FY14 FY15Total Cost Comments

Hall CSOS Removal (3) Must be started in FY11 Procurements $20 $30 $50 Major Contracts $150 $300 $450 Physics Div. Labor on SOS Removal $75 $50 $125 Eng. Div. labor on SOS removal $15 $15 $30HMS Wire Chambers Flexible re FY11 start Procurements and HU student labor $75 $100 $175 Physics Div. labor on HMS Wire Chamber design $10 $10DAQ Upgrade (4) $100 $50 $100 $50 $300 Flexible re FY11 startCompton Upgrade Flexible re FY11 start Procurements $50 $75 $25 $150 Physics Div labor on Compton Upgrade design $50 $50 $50 $150 Eng. Div. Labor on Compton Upgraded $50 $50Post Qweak beamline design Flexible re FY11 start Procurements $50 $150 $200 Part of project scope? Eng. Div Labor on Post Qweak beamline design $50 $50 $150 $100 $350 Part of project scope?

Hall C Totals $545 $595 $350 $425 $125 $2,040

Page 20: Physics Division “BIA-Like” Projects L. S. Cardman

Overall Cost Summary

FY11 FY12 FY13 FY14 FY15Total Cost Comments

Division Totals $606 $2,738 $1,725 $425 $125 $5,619

Notes:

1 Hall A estimates assume all labor is covered by Hall A OPS

2 The upgrade of one of the two HRSs was originally part of the project, but is now descoped

3SOS Removal includes $120k for radioactive waste dispposal; this may not be necessary and may be defered

4Hall C DAQ Upgrade: Parts of this may already be covered in existing BIA (15K), or will be covered by 12 GeV contingency.

Candidates for 12 GeV Project Funding include $1,679 of the $5,619 total, leaving

$3,940for BIA