PHOTOVOLTAICS BGPHOTOVOLTAICS BG
![Page 2: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/2.jpg)
Content
• Photovoltaics in Bulgaria• Economy of Bulgaria• Geography of Bulgaria• Legislation• Technical conditions for the connection
![Page 3: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/3.jpg)
Guaranteed period of purchase
• In Bulgaria, there is a purchase of electricity produced in the
photovoltaic power stations guaranteed for 25 years
![Page 4: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/4.jpg)
Guaranteed purchase price
• Price per 1 kWh in Bulgaria 0,464 € inc. VAT since 01.04.2010
• In Bulgaria, there is 35% higher sun radiation than in midl Europe
![Page 5: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/5.jpg)
In Bulgaria, there is no permit needed for the construction of photovoltaic power stations up to 5 MW of output
![Page 6: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/6.jpg)
• Exchange rate development which is fixed on Euro as of 10.01.2006
![Page 7: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/7.jpg)
Budget deficit of Bulgaria
The Bulgarian Ministry of Finance announced that the Bulgarian budget
deficit for 2009 was 529,5 BGN M or 0,8 % of GDP.
(http://www.novinite.com/view_news.php?id=112626)
![Page 8: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/8.jpg)
Development of inflation in BulgariaDevelopment of inflation in Bulgaria
![Page 9: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/9.jpg)
State dept of Bulgaria• State dept of Bulgaria was 3,4 Mld. Euro at the end of 2009, public debt
decreased for 0,5% when compared to previous year
![Page 10: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/10.jpg)
Taxes in Bulgaria
• Value income tax of legal persons in Bulgaria is only 10%.
![Page 11: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/11.jpg)
BULGARIA
![Page 12: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/12.jpg)
![Page 13: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/13.jpg)
Distribution companies in Bulgaria
![Page 14: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/14.jpg)
Distribution companies in Bulgaria
EVN – Austrian distribution company
EON – German distribution company
ČEZ – Czech distribution company
![Page 15: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/15.jpg)
Investor applies for the connection
• In application he defines the subject which is submitting the application
• He attaches the Certificate of Land Ownership
• Indicates which PTV output he wants to install
![Page 16: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/16.jpg)
Based on application respective distribution company issues preliminary opinion
• It implies information about maximum connectable output, location, exact place of connection and technical conditions of connection
![Page 17: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/17.jpg)
Following the issue of preliminary opinion the investor is obliged to obtain all the necessary permissions and opinions of involved institutions
After their receipt the investor request the respective distribution company for the conclusion of preliminary contract on connection
![Page 18: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/18.jpg)
Documents necessary for the conclusion of preliminary contract on connection
• Standpoint of the distribution company• Admissible reserved capacity of connection• Detailed territorial plan• Environmental permissions• Standpoint of the regional inspectorate of health protection• Standpoint of authority of water resources protection• Categorisation of land, opinion on possibility of constrution• Decision of Ministry of Agriculture• Written opinion on the detailed territorial plan and preliminary contract
with the distribution company
![Page 19: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/19.jpg)
Preliminary contract on connection is a binding document fulfilling all legislative conditions necessary for the conclusion of the contract on connection.
After its conclusion the investor can apply for the Building permission. However, he must also attach projects for the building permission.
![Page 20: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/20.jpg)
After granting the building permission the investor concludes the contract with respective distribution company.
![Page 21: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/21.jpg)
After granting the building permission the investor can commence construction works and the final building approval he concludes the contract on purchase of electricity with respective distribution company.
![Page 22: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/22.jpg)
Following conditions must be met to connect PVT power station to the network :
• Connection must be conducted in accordance with Par. 3 3 of Notice Nr. 6 as of 9.6.2004 on connection of producer and consumer of electricity through transfer network IDB Nr. 74 as of 24.08.2004
• It is imperative to meet the conditions stipulated in the Notice Nr. 14, as of 15.06.2005 on the technical rules and norms, for designing and use of facilities and appliances for the production, transmission and distribution of electric energy.
![Page 23: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/23.jpg)
Requirements for the appliances which must be attached to the central:
• All building components for connecting of the facility (photovolt. Modules, invertors, commutators, etc.) must comply with EU standards and the respective Bulgarian requirements. Before conclusion of the Contract on connection there must be documents for the approval of compliance submitted
• Invertors must be connected to the three phase system – symetric-sinusoid incoming voltage
• Outgoing voltage from invertor to the network must comply with EU standards EN 50160 as well as norms defined by the Government commission for energy and water regulation. Furthermore, it must comply with qualitative requirements of electric appliances (June 2004) and Chapter VII. of Head VI. of Regulation Nr. 6 as of 9 June 2004 on Connection of producers and consumers of electricy through transmission and distribution network
![Page 24: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/24.jpg)
Measurement of electricity
• Is realised in modules „Measurement“ from GRU of power station with one indirect, static, three-phase energy meter for active and non-active energy with measurements in four quadrants which must have a possibility of storage „on factory profile“ for active and reactive energy for the 15-minute-period during 62 days
• Energy measurement for production and consumption of all objects and properties must be realised with one measurement
![Page 25: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/25.jpg)
Service zones
• There must be terminal disconnectors installed on the borderlines of the lands
• There must be GPRS connection provided for the communication with monitoring system and management of recluser with CUM
• A possibility of access to facility of photovoltaic central to EON BG staff must be attained
• Before conclusion of the Contract for employment the documents for legalisation of service zone for wireline 20 kV as well as documents on compliance for the built power station must be provided
![Page 26: Photovoltaics EN](https://reader033.vdocuments.mx/reader033/viewer/2022061110/545407f5af795907578b7b07/html5/thumbnails/26.jpg)
Service zones
• Before start of the 72-hour-check all newly built facilities must be included into the scheme of the respective centre for the dispatch control of facilities as well as remote controlled facilities and must dispose of functional communication with operational basis in compliance with CUM
• The constructor is aware that in case of oversupply of energy or other obstructions of the power station to the network, it can be regulated or temporarily disconnected from the network
• In accordance with Act on power supply and production of electricity it is subject to issue of licence. The licence is not requested for the appliances up to 5 MW of output.