    Pleasant Hill Road

    Reconstruction Project – Phase I

    Scarborough, Maine

    January 30, 2014

  • 8/13/2019 Phill Road

    2/16

    Pleasant Hill Road Reconstruction Project – Phase IScarborough, Maine

  • 8/13/2019 Phill Road

    3/16

    Pleasant Hill Road Reconstruction Project – Phase IScarborough, Maine

    Scope of Work – Phase 1

    • Water Main Renewal for Portland Water District Will involve temporary interruptions to service

    New water from Rigby Rd to Highland Ave

    Services renewed to property line

    • Road Widening – Rigby Road to Highland Avenue

    24’ wide existing; 36’ wide road proposed (improved bicycle access)

    Pavement reclamation

    Box cut work

    • Drainage Improvements

    • Surface Paving

  • 8/13/2019 Phill Road

    4/16

    Pleasant Hill Road Reconstruction Project – Phase IScarborough, Maine

    Schedule• Summer 2014

    Possible start mid-June to early July

    Completion by October 15 to November 1, 2014

    Funding dependent

    • Traffic Control

    Generally desirable to maintain two-way traffic at all times

    Signage

    Information bulletins

    May include periods of single lane traffic between 10:00 am to 3:00 pm

    • Detours

    Re-routing to Highland Ave and Black Point Road

    South Portland – Thornton Heights project

    • Work Hours

    Generally 7:00 am to 7:00 pm

    Some night work may be required

    Some weekend work may be required

  • 8/13/2019 Phill Road

    5/16

    Pleasant Hill Road Reconstruction Project – Phase IScarborough, Maine

    Other

    • Town participating with MaineDOT for funding

    through Municipal Partnership Agreement.

  • 8/13/2019 Phill Road

    6/16

    Pleasant Hill Road Reconstruction Project – Phase IScarborough, Maine

  • 8/13/2019 Phill Road

    7/16

    Pleasant Hill Road Reconstruction Project – Phase IScarborough, Maine

  • 8/13/2019 Phill Road

    8/16

    Pleasant Hill Road Reconstruction Project – Phase IScarborough, Maine

    Roadway Sta. 44+80 to 51+20

  • 8/13/2019 Phill Road

    9/16

    Pleasant Hill Road Reconstruction Project – Phase IScarborough, Maine

    Roadway Sta. 51+20 to 57+60

  • 8/13/2019 Phill Road

    10/16

    Pleasant Hill Road Reconstruction Project – Phase IScarborough, Maine

    Roadway Sta. 57+60 to 64+00

  • 8/13/2019 Phill Road

    11/16

    Pleasant Hill Road Reconstruction Project – Phase IScarborough, Maine

    Roadway Sta. 64+00 to 70+40

  • 8/13/2019 Phill Road

    12/16

    Pleasant Hill Road Reconstruction Project – Phase IScarborough, Maine

    Roadway Sta. 70+40 to 76+80

  • 8/13/2019 Phill Road

    13/16

    Pleasant Hill Road Reconstruction Project – Phase IScarborough, Maine

    Roadway Sta. 76+80 to 83+20

  • 8/13/2019 Phill Road

    14/16

    Pleasant Hill Road Reconstruction Project – Phase IScarborough, Maine

    Roadway Sta. 83+20 to 89+60

  • 8/13/2019 Phill Road

    15/16

    Pleasant Hill Road Reconstruction Project – Phase IScarborough, Maine

    Roadway Sta. 89+60 to 92+88

  • 8/13/2019 Phill Road

    16/16

    Pleasant Hill Road Reconstruction Project – Phase IScarborough Maine