phase-1 inauguration photos held on 17.06.2017 at vidhana...

12
Durga Shanker Mishra, IAS Secretary, MoUD, GoI & Chairman, BMRCL Pradeep Singh Kharola, IAS Managing Director Vijay Kumar Dhir Director (P&P) N.M. Dhoke Director (RSE & OM) U.A. Vasanth Rao General Manager (T&R) & Chief Public Relations Officer Editorial Team T. L. Ravi Prakash Senior Manager-Public Relations & Srivas Rajagopalan Registered Office Address Bangalore Metro Rail Corporation Limited, 3rd Floor, BMTC Complex, K H Road, Shantinagar, Bengaluru—560 027 Telephone / Fax Nos Ph: +91-080-22969300 / 301 Fax : 080-22969222 Co. Identification No. (CIN) U16286KA1994GOI016286 Your feedback helps us serve you better. For any suggestions about Namma Metro email us at [email protected] or [email protected] You can also call on Toll Free Helpline No. 1800-425-12345 Inauguration of Namma Metro Phase 1 by Hon’ble President of India along with H.E. Governor of Karnataka, Hon’ble Chief Minister of Karnataka, other Union & State Ministers, Worshipful Mayor & Dignitaries at Vidhana Soudha on 17.06.2017

Upload: leduong

Post on 08-May-2018

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Phase-1 Inauguration Photos held on 17.06.2017 at Vidhana ...english.bmrc.co.in/FileUploads/ffcefe_PressQuesFiles.pdf · Test pile of 6 Nos for initial vertical pile load test and

Madhusudan Prasad, IASSecretary, MoUD, GoI &

Chairman, BMRCL

Pradeep Singh Kharola, IASManaging Director

M. Naveen KumarDirector (Finance)

Vijay Kumar DhirDirector (P&P)

N.M. DhokeDirector (RSE & OM)

U.A. Vasanth RaoGeneral Manager (T&R) &

Chief Public Relations Officer

EDITORIAL TEAMT. L. Ravi Prakash

Senior Manager-Public Relations

&Srivas Rajagopalan

Bangalore Metro RailCorporation Limited,

3rd Floor, BMTC Complex,K H Road, Shantinagar,

Bengaluru—560 027

Ph: +91-080-22969300/ 301Fax : 080-22969222

For any suggestions aboutNamma Metro email us at

[email protected] or [email protected]

Your continued feedbackhelps us serve you better.You can also call on Toll

Free Helpline No.1800-425-12345. You canalso view the updates on

ww.facebook.com / bmrcl.

Durga Shanker Mishra, IASSecretary, MoUD, GoI &

Chairman, BMRCL

Pradeep Singh Kharola, IASManaging Director

Vijay Kumar DhirDirector (P&P)

N.M. DhokeDirector (RSE & OM)

U.A. Vasanth RaoGeneral Manager (T&R) &

Chief Public Relations Officer

Editorial Team

T. L. Ravi PrakashSenior Manager-Public Relations

&Srivas Rajagopalan

Registered Office AddressBangalore Metro RailCorporation Limited,

3rd Floor, BMTC Complex,K H Road, Shantinagar,

Bengaluru—560 027

Telephone / Fax Nos

Ph: +91-080-22969300 / 301Fax : 080-22969222

Co. Identification No. (CIN)

U16286KA1994GOI016286

Your feedback helps usserve you better. For any

suggestions aboutNamma Metro email us at

[email protected] [email protected]

You can also call onToll Free Helpline No.

1800-425-12345

Inauguration of Namma Metro Phase 1 by Hon’ble President of India along withH.E. Governor of Karnataka, Hon’ble Chief Minister of Karnataka, other Union & State

Ministers, Worshipful Mayor & Dignitaries at Vidhana Soudha on 17.06.2017

Page 2: Phase-1 Inauguration Photos held on 17.06.2017 at Vidhana ...english.bmrc.co.in/FileUploads/ffcefe_PressQuesFiles.pdf · Test pile of 6 Nos for initial vertical pile load test and

Phase-1 Inauguration Photos held on 17.06.2017 at Vidhana Soudha

Page 3: Phase-1 Inauguration Photos held on 17.06.2017 at Vidhana ...english.bmrc.co.in/FileUploads/ffcefe_PressQuesFiles.pdf · Test pile of 6 Nos for initial vertical pile load test and

Phase-1 Inauguration Photos held on 17.06.2017 at Vidhana Soudha

Page 4: Phase-1 Inauguration Photos held on 17.06.2017 at Vidhana ...english.bmrc.co.in/FileUploads/ffcefe_PressQuesFiles.pdf · Test pile of 6 Nos for initial vertical pile load test and

View of Nadaprabhu Kempegowda Station, Majestic during Operations

Page 5: Phase-1 Inauguration Photos held on 17.06.2017 at Vidhana ...english.bmrc.co.in/FileUploads/ffcefe_PressQuesFiles.pdf · Test pile of 6 Nos for initial vertical pile load test and

REACH-4B Extension—(Puttenahalli Cross to Anjanapura Township)

Compensation packages for 255 properties amounting ₹ 308.85 Crores have been sent to SLAO, KIADB and

payment has been made in respect of 239 properties amounting to ₹ 254.54 Crores.

28(4) Notification in respect of 27 properties required for electric utility shifting is approved by Govt. and thevaluation Report from the Land Committee is received and compensation packages are sent to KIADB forpayment.

Out of 8 properties pertaining to Anjanapura Township Station, Compensation packages in respectof 5 properties has been sent to SLAO, KIADB for payment, 3 properties are pending for clarification fromBDA.

Land plan for Anjanapura Depot is being revised by concerned Chief Engineer.

28(1) Notification for additional area of 1005.21 Sq. mtrs. is published in Karnataka Gazette on 14.03.2017.JMC work is completed.

REACH-5 New Line--(R.V. Road to Bommasandra)

Out of total 461 properties acquired, compensation packages for 331 properties amounting to ₹ 1046.17Crores have been sent to SLAO, KIADB and payment has been made in respect of 145 properties amountingto ₹ 482.75 Crores.

28(4) Notification in respect of Jayadeva Station and BTM Station is published in the Gazette.

Joint Measurement in respect of 72 properties required for electric utility shifting is completed and Drawingsare prepared and submitted. SLAO, KIADB has to pass order u/s 28(3).

28(1) Notification in respect of Silk Board Station is sent to SLAO, KIADB.

28 (1) Notification in respect of additional properties required for Jayadeva Station is published in the Gazette.SLAO, KIADB has to pass orders u/s 28(3).

REACH-6 New Line--(Gottigere (IIMB) to Nagawara)

Kothnur Depot– Joint measurement sketch along with draft 28(4) notification is sent to SLAO for approval. Thematter is pending in the Hon’ble High Court with regard to Sy. No. 87 of Kothnur.

28(4) Notification for lands from Gottigere to Diary Circle is approved by the Government. and is published inthe Karnataka Gazette on 27.10.2016. Compensation packages are being prepared and will be sent to KIADB.

28(1) notifications in respect of additional lands required for above reach and the lands required for ElectricUtility Shifting have been published in the Gazette dated: 02.02.2017 and JMC is to be held.

28(1) Notification in respect of 7 Under Ground Stations from Dairy Circle to Shivajinagar is published in theGazette on 30.03.2017 and JMC is under progress. JMC for two stations is completed.

28(1) Notification in respect of other Underground Stations (3 Stations) is already submitted to SLAO, KIADB.

DETAILS OF LAND AND PROPERTY ACQUISITION FOR GOVERNMENT & PRIVATE PROPERTIES

Page 6: Phase-1 Inauguration Photos held on 17.06.2017 at Vidhana ...english.bmrc.co.in/FileUploads/ffcefe_PressQuesFiles.pdf · Test pile of 6 Nos for initial vertical pile load test and

Viaduct & Stations: along with Road Widening works:-

M/s Tender Notification-NIT has been received for R1A between Baiyappanahalli to Visvesvaraya IndustrialArea Station including Road Widening.

Test pile of 6 Nos for initial vertical pile load test and lateral pile load test work are completed at LowrySchool.BP-221 & BP-222 and Visvesvaraya Industrial Area station. Rock anchoring is completed atLowry School and initial vertical load test is in progress.

Road widening work is in progress from BP 243 to BP 270 (LHS) and BP-183 to BP-216 (RHS).

Tender Notification-NIT has been received for R1B between Visvesvaraya Industrial Area Station toWhitefield Station including Road Widening and Depot Entry ( BP-273-BP-509) for Rs. 666.12 Cores. As perFinancial scrutiny report the lowest bidder is M/s ITD Cementation India Ltd–ITD(JV) and Letter ofAcceptance is issued by BMRCL.

Test Pile of 4 Nos for initial vertical pile load test and lateral pile load test are completed at Hope farmand Lesso location.

Road widening work is in progress from BP-277 to Graphite India Circle (LHS) and BP-285 to BP-296(LHS).

REACH-2Extension-Reach-2A:- Construction of Elevated Structures of Length 3.945 kms (approx)from Mysuru Road Station dead end to Pattanagere Station including 4 Nos. of Elevated MetroStations viz Nayandahalli Station, Rajarajeshwarinagar Station, Jnanabharathi Station andPattanagere Station in the extension on west side of East-West Corridor of Bangalore MetroRail Project, Phase-2.

Name of the Contractor :- M/s IL&FS Engineering Construction Company Limited

Total Cost of the Project :- Rs. 327.00 Crores

Shifting of Water Supply Lines & Underground Drainage (UGD) Lines:- The affected water supply line andUnderground line are identified along with the concerned BWSSB Engineers for the entire stretch. The drawingsare prepared and submitted to BWSSB for shifting the identified utilities to the new location of utility corridor.

BWSSB has submitted the estimate. According to that BMRCL deposited the estimated amount to BWSSB. Thework has been taken up by BWSSB and completed at Jnanabharathi, Rajarajeshwari and Nayandahalli stations inall respects.

Road Widening Works:- Road Widening works from Nayandahalli to Rajarajeshwarinagar both sidecompleted and Jnanabharathi station and Pattanagere station all the road works has been completed. In Stationsboth side drain work with Road widening/diversion work is in Progress. Retaining wall work is under construction.

Page 7: Phase-1 Inauguration Photos held on 17.06.2017 at Vidhana ...english.bmrc.co.in/FileUploads/ffcefe_PressQuesFiles.pdf · Test pile of 6 Nos for initial vertical pile load test and

Casting Yard:- 44 number of Span Segment Casted. I-Girder –Pretension I-Girder 140 numbers has been casted. Total 140 numbers of segments has been casted.

At Jnanabharathi (JNB), Pattanagere (PTN) and Rajarajeshwari Stations 100% Piling Works are completed.

Auto launching work in progress at Reach-2A of Phase-2

Page 8: Phase-1 Inauguration Photos held on 17.06.2017 at Vidhana ...english.bmrc.co.in/FileUploads/ffcefe_PressQuesFiles.pdf · Test pile of 6 Nos for initial vertical pile load test and

REACH-2Extension-Reach-2B:- Construction of Elevated Structures (Viaduct) of length of

4.869 Kms. (approx.) from Pattanagere Station (excluding) to beginning of Challagatta Depotincluding 2 Nos of Elevated Metro Stations viz. Mailasandra Station and Kengeri Station in theextension on west side of E-W Corridor on Bangalore Metro Rail Project, Phase – 2

Name of the Contractor :- M/s Soma Enterprise Limited,

Total Cost of the Project :- Rs. 332.00 Crores

Land Acquisition:- The land acquisition for Reach 2B from Pattanagere Station to Kengeri Arch Bridge is

completed and the land is in position with BMRCL from Kengeri Arch Bridge to Challaghatta Depot. The

preliminary notification for acquisition has been issued for Joint Measurement work which is in progress.

Building Condition Study & Structural Analysis:- The work has been awarded to M/s Civil Aid Techno

Clinic Pvt Ltd. and the work has been completed from Pattanagere station to Kengeri Arch Bridge and from

Kengeri Arch Bridge to Challaghatta and the work which is in progress.

Demolition of Buildings / Structures Identified for Acquisition:- The work has been awarded to M/s Binyas

Contech Pvt Ltd and M/s Sai Retro Fabs. The work has been completed from Pattanagere Station to Kengeri Arch

Bridge and from Kengeri Arch Bridge the work will commence after acquisition of properties.

Road Widening Works:- From Pattanagere Station to NICE Road the Road Widening work has been

started by National Highway PWD Karnataka. 97% of work is completed.

Viaduct & Stations:- The construction of 4.869 KMs Viaduct and Stations has been awarded to M/s SOMA

Enterprises Limited and the work is in progress.

Test Pile :- Two numbers of Initial Vertical Pile Load test is completed for the Viaduct. Barricading work is

in progress. Working Pile:- The work is in progress.

Casting Yard at Kanminike near Bidadi:-

Two numbers of Batching Plant, Segment Casting Bed is in progress. Construction of Site office building is in

progress. All other preliminary works is under progress.

REACH WISE PROGRESS OF WORKS OF PHASE-II

Page 9: Phase-1 Inauguration Photos held on 17.06.2017 at Vidhana ...english.bmrc.co.in/FileUploads/ffcefe_PressQuesFiles.pdf · Test pile of 6 Nos for initial vertical pile load test and

REACH-4Extension-Reach-4B:- Construction of Elevated Structures of length 6.524 km (approx)from Puttenahalli Cross Station to Anjanapura Township Station and further viaductincluding 5 Nos. of Elevated Metro Stations Viz. Anjanapura Road Cross Station, KrishnaLeela Park Station, Vajrahalli Station, Thalaghattapura Station and Anjanapura TownshipStation.

Name of the Contractor :- M/s Nagarjuna Constructions Company Limited.

Total Cost of the Project :- Rs. 508.86 Crores.

Viaduct & Stations:-

The work of Construction of this Project is awarded to M/s Nagarjuna Constructions Company Limited and thework is in progress.

All Works like Barricading, Cross trenching, Piling, Pile caps, Piers and Pier caps, Road widening, Drain worksetc. are in progress along Viaduct.

Works like Drain works, Service Road and Foundation works are in progress at Anjanapura Cross RoadStation, Krishna Leela Park Station, Vajarahalli Station, Thalaghattapura Station & Anjanapura TownshipStation.

521 nos of Pile out of 976 piles are completed for Viaduct structures.

739 nos of Pile out of 830 piles are completed for Station locations.

107 nos of Pile caps out of 222 nos are completed for Viaduct structures.

124 nos of Pile caps are completed out of 320 nos for Off-road structures at Station locations.

44 nos of Pile caps are completed out of 50 nos for C-Gird at Station locations.

87 nos of Piers are completed out of 222 nos for Viaduct structures.

36 nos of Pier Arm for Concourse level are completed out of 50 nos at Station locations.

26 nos of Piers up to Concourse level are completed out of 50 nos at Station locations.

9 numbers of Pier Arm for Platform Level is completed out of 50 numbers at Station locations.

Drain including cover slab is completed for a length of 6697 Rmt.

Launching Activities:-

LG-01-11 Span of segments is erected at EP-138 & EP-139.

LG-02 -15 Spans of segments are erected upto EP 195 - EP 196.

LG-03-1 Span of segments is erected at EP-257 & EP-258.

REACH WISE PROGRESS OF WORKS OF PHASE-II

Page 10: Phase-1 Inauguration Photos held on 17.06.2017 at Vidhana ...english.bmrc.co.in/FileUploads/ffcefe_PressQuesFiles.pdf · Test pile of 6 Nos for initial vertical pile load test and

Abstract of Progress of Reach-4B as on 30.06.2017

REACH WISE PROGRESS OF WORKS OF PHASE-II

Sl No Item Unit Total QtyWork

done tillMay2017

Progress for theMonth of June 2017 Progress

upto dateTill Lastweek

For thisweek

I VIADUCT WORKS

1 Piling 1200 mm dia Nos. 976 497 23 1 521

2 Pile caps Nos. 222 100 5 2 107

3 Piers & Pier caps Nos. 222 79 7 1 87

4 Crash Barrier Nos. 222 44 10 1 55

5 Segment Casting Nos 2009 707 69 15 791

II STATION WORKS1 Piling 1200 mm dia Nos. 470 438 3 — 441

2 Piling 600 mm dia Nos. 360 298 — — 298

3 Pile caps off road structures Nos. 320 123 1 — 124

4 Pile caps C-Grid structures Nos. 50 41 3 — 44

5 Pier up to Concourse Level (C-Grid) Nos. 50 32 1 3 36

9 Pre-Tension I-Girder casting (For Concourselevel) Nos. 245 144 2 — 146

10 Pre-Tension I-Girder casting (For Platformlevel) Nos. 180 72 10 4 86

11 Post-Tension I-Girder casting (For TrackLevel) Nos. 180 24 4 1 29

6 Segment Erection Span 210 24 2 1 27

12 Post Tension I-Girder casting (for TransitionLevel) Nos. 60 6 — — 6

6 Pier Arm for Concourse Level Nos. 50 23 2 1 26

8 Pier Arm for Platform Level (C-Grid) Nos. 50 4 4 1 9

7 Parapet Casting Nos 4018 9 10 — 19

8 Drain Rmt 10930 5196 — — 5196

13 Drain Rmt 2850 1501 — — 1501

7 Pier above Concourse Level Nos 50 15 2 5 22

Page 11: Phase-1 Inauguration Photos held on 17.06.2017 at Vidhana ...english.bmrc.co.in/FileUploads/ffcefe_PressQuesFiles.pdf · Test pile of 6 Nos for initial vertical pile load test and

The Detailed Design and Drawings of viaduct and stations including Road widening works are in progress. The Road widening plan has been prepared and submitted to Traffic police and permission letter is obtained

from Addnl. Commissioner of Police (Traffic). The proposed traffic diversion plan along Marenahalli Road/ORR has been shown to the concerned Traffic

police. The approval for the same is expected shortly. Road widening work along Marenahalli/ORR will be taken up in consultation with Traffic police, BBMP etc.

The Tenders are awarded for Package –1, Package-2 & Package-3 of R5 Line for Construction of Viaductand Stations of packages between

Bommasandra to Hosa Road of 6.4 Kms length (Package-1) :- The work of construction of viaduct andstations between Bommasandra-Hosa Road of 6.4 Kms length is awarded.

Hosa Road to HSR Layout of 6.4 Kms length (Package-2) :- The work of construction of viaduct andstations between HSR Layout to RV Road of 6.4 Kms length is awarded.

HSR Layout to R V Road of 6.34 Kms length (Package-3):- The work of construction of viaduct andstations between HSR Layout to R V Road of 6.34 Kms length 6.34 Kms is awarded.

REACH-66 (New Line-Gottigere (IIMB) to Nagawara)Tender has been opened and LOA has been issued for the Construction of Elevated Structures (Viaduct andStations) of length 7.50 Kms (approx.) from Gottigere to Swagath Road Cross (Chainage 00.00m to 7501,818m)including Kothnur Depot, entry line, Road widening and allied works and 5 Numbers of Metro Stations viz.Gottigere, Hulimavu, IIMB, J.P. Nagar 4th Phase, Swagath RoadCross in Reach-6 line of Bangalore Metro Rail Project, Phase-2.

REACH WISE PROGRESS OF WORKS OF PHASE-II

Auto launching & Cantilever work is in progress at Reach-4B of Phase-2

Page 12: Phase-1 Inauguration Photos held on 17.06.2017 at Vidhana ...english.bmrc.co.in/FileUploads/ffcefe_PressQuesFiles.pdf · Test pile of 6 Nos for initial vertical pile load test and

DETAILS OF PHASE– II

Alignments showing the Extensions of the existing East-West CorridorsReach –1 East Extension - Baiyappanahalli to Whitefield (Fully Elevated) - 15.50 kms, 14 Stations.Reach-2 West Extension - Mysore Road Junction of Ring Road to Kengeri on the West (Fully Elevated) - 6.465 kms

and 5 Stations.Reach-3 North Extension - Hesaraghatta Cross to Bangalore International Exhibition Centre (BIEC-Fully Elevated) -

3.77 kms and 3 Stations.Reach-4 South Extension - Puttenahalli to Anjanapura (Fully Elevated) - 6.29 kms and 5 Stations.

Alignments of the two New East-West & North-South CorridorsReach-5 East-West - R.V. Road Station on the Existing N-S Corridor (Passenger Interchange) to Bommasandra

(Fully Elevated) 18.82 kms and 16 StationsReach-6 North-South- Gottigere (IIMB) to Nagawara (At Grade 0.48 Kms, Elevated 6.98 kms & Underground

13.79 kms) - 21.25 kms, with 6 Elevated and 12 Under Ground Stations.

It may be seen from above that Phase-II includes a total length of 72.095 km (13.79 km Underground) and61 Stations with 12 Underground Stations. Each line can be traced along with the Station Names in the Map belowfor both Phase-I & Phase-II