pfi street lighting & traffic signal project update

15
PFI Street Lighting & Traffic Signal Project Update

Upload: donna-russo

Post on 03-Jan-2016

29 views

Category:

Documents


2 download

DESCRIPTION

PFI Street Lighting & Traffic Signal Project Update. Why PFI? – Blackpool’s issues. Blackpool’s Issues - Infrastructure. Over 70% of street lights are “life expired” Only 14% of back streets are lit Over 44% of traffic signal sites require ‘urgent’ replacement / upgrading. PFI Scope. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: PFI Street Lighting & Traffic Signal Project Update

PFI Street Lighting & Traffic Signal Project Update

Page 2: PFI Street Lighting & Traffic Signal Project Update

Why PFI? – Blackpool’s issues

Page 3: PFI Street Lighting & Traffic Signal Project Update

Blackpool’s Issues - Infrastructure

• Over 70% of street lights are “life expired”

• Only 14% of back streets are lit

• Over 44% of traffic signal sites require ‘urgent’ replacement / upgrading

Page 4: PFI Street Lighting & Traffic Signal Project Update

PFI Scope

• Street lighting columns

• Adopted back streets

• Illuminated signs and bollards

• Traffic signals

Page 5: PFI Street Lighting & Traffic Signal Project Update

PFI ScopeAsset Replace

during first 5-years

Comments

Street lighting columns 72% An additional estimated 1,865 columns will be installed to improve the current lighting standards and to light many currently unlit adopted back streets

Illuminated signs & bollards

100% A number of bollards will be replaced with reflective material

Traffic signal points 84% Move to a robust planned maintenance regime for all sites

* Programming is based upon asset condition• Worst condition first• Alignment of lighting columns/traffic signal junctions

Page 6: PFI Street Lighting & Traffic Signal Project Update

PFI – Current position

Process Timeframe

£31.9M PFI Credits awarded Sept ‘07

Procurement Process• Bidders solutions

Oct ‘07 to current

Close Dialogue – Issue final tenders Dec ‘08

Appoint Preferred Bidder Feb / March ‘09

Contract start Aug / Sept ‘09

Page 7: PFI Street Lighting & Traffic Signal Project Update

Procurement Process to Date

• Three interested bidders submitted detailed

solutions – May ’08

• Refined solutions submitted – Aug ’08

• Two bidders will be invited to submit final tenders

• CLP (Community Lighting Partnership)

• TVL (Tay Valley Lighting)

• De-selected bidder - NLP

Page 8: PFI Street Lighting & Traffic Signal Project Update

Financial Information

PFI Credits £31.9 million

Contract Value £141 million

Affordability Gap £472,000

Economic Benefits £113.2 million

Page 9: PFI Street Lighting & Traffic Signal Project Update

Credit Crunch Impact

• Banks reluctant to lend in current economic climate

• Financing terms are changing daily

• Increasing costs of raw materials / energy / supplies

• Regular monitoring

• Sensitivity Analysis

Page 10: PFI Street Lighting & Traffic Signal Project Update

Contract Monitoring

• PFI Contract Manager Appointed – September ’08• Co-location with PFI Service Provider• Self-monitoring contract• Performance Standards – Output Specification• Incentives / Penalties - Payment Mechanism• Milestones• Independent Certifier• Monthly monitoring meetings• PFI Strategic Board

Page 11: PFI Street Lighting & Traffic Signal Project Update

Pre-Post PFI LightingTypical Residential Street – Prior to PFI

Typical Residential Street – Post PFI

Page 12: PFI Street Lighting & Traffic Signal Project Update

Devonshire Road – Recent Scheme

Devonshire Road Lighting

Page 13: PFI Street Lighting & Traffic Signal Project Update

Traffic Signals

Insert photo

Page 14: PFI Street Lighting & Traffic Signal Project Update

What next?

• Appointment of Preferred Bidder by Executive• Stakeholder Consultation• Future presentations to O & S

Page 15: PFI Street Lighting & Traffic Signal Project Update

Any questions?