Perth Darwin National Highway – Reid Highway to Muchea Bullsbrook Residents and Ratepayers Meeting 24 th June 2013 Dominic Boyle & Paul Fourie, Main Roads

Upload: trankien

Post on 06-Mar-2018

222 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Perth Darwin National Highway – Reid Highway to · PDF filePerth Darwin National Highway – Reid Highway to Muchea Bullsbrook Residents and Ratepayers Meeting 24th June 2013 Dominic

Perth Darwin National Highway – Reid Highway to MucheaBullsbrook Residents and Ratepayers Meeting24th June 2013

Dominic Boyle & Paul Fourie, Main Roads

Page 2: Perth Darwin National Highway – Reid Highway to · PDF filePerth Darwin National Highway – Reid Highway to Muchea Bullsbrook Residents and Ratepayers Meeting 24th June 2013 Dominic

Our Roles

• Paul Fourie – Road Planning BranchIn-depth planning study using long term population, land use and traffic forecasts to identify future road infrastructure requirements. Definition of road reservation for an ultimate road concept taking into account stakeholder, environmental and heritage issues.

• Dominic Boyle – Infrastructure Delivery DirectorateReview how much of the ultimate road concept needs to be built at this time. Get the project “delivery ready” including stakeholder engagement, environmental/heritage clearances and offsets, geotechnical investigations, preliminary design, funding approvals & land acquisition. Develop procurement strategy for construction.

Page 3: Perth Darwin National Highway – Reid Highway to · PDF filePerth Darwin National Highway – Reid Highway to Muchea Bullsbrook Residents and Ratepayers Meeting 24th June 2013 Dominic

Objectives & Benefits

• Cater for growth in demand for freight movements between Perth and the Northwest

• Little scope for further improvements to section of Great Northern Highway through the Swan Valley

• Improved freight efficiency / national productivity

• Reduce environmental & safety impact of heavy vehicles through Swan Valley

Page 4: Perth Darwin National Highway – Reid Highway to · PDF filePerth Darwin National Highway – Reid Highway to Muchea Bullsbrook Residents and Ratepayers Meeting 24th June 2013 Dominic

Preferred Alignment

Page 5: Perth Darwin National Highway – Reid Highway to · PDF filePerth Darwin National Highway – Reid Highway to Muchea Bullsbrook Residents and Ratepayers Meeting 24th June 2013 Dominic

Funding

• State Government previously pledged $8M over three years to develop the project

• Submitted details to Infrastructure Australia January 2013

• State Government election pledge of $196M to commence construction in 2016

• Federal Government committed up to $418M in recent budget, contribution must be matched 50/50 by State

• State budget due in August

Page 6: Perth Darwin National Highway – Reid Highway to · PDF filePerth Darwin National Highway – Reid Highway to Muchea Bullsbrook Residents and Ratepayers Meeting 24th June 2013 Dominic

Provisional Timeline: Project Development

• Framing and staging study complete by end Sep 2013

– Staging options– Governance plan– Stakeholder engagement strategy

• Detailed project development during 2014– Further environmental & heritage surveys– Geotechnical surveys– Stakeholder engagement– Preliminary design

Page 7: Perth Darwin National Highway – Reid Highway to · PDF filePerth Darwin National Highway – Reid Highway to Muchea Bullsbrook Residents and Ratepayers Meeting 24th June 2013 Dominic

Provisional Timeline: Pre-construction

• Project Approvals during 2015– Environmental & Heritage– State / Commonwealth Land– Confirmation of Funding

• Land acquisition during 2014/15

• Determine Procurement Strategy - 2015

• Procurement during 2015/16

• Start construction 2016

Page 8: Perth Darwin National Highway – Reid Highway to · PDF filePerth Darwin National Highway – Reid Highway to Muchea Bullsbrook Residents and Ratepayers Meeting 24th June 2013 Dominic

Summary• Planning study nearing completion• Project Development 2013/14• Project approvals / land acquisition 2014/15• Procurement 2015• Start construction 2016