periodic field observation report
TRANSCRIPT
![Page 1: Periodic Field Observation Report](https://reader037.vdocuments.mx/reader037/viewer/2022083117/577cce021a28ab9e788d137b/html5/thumbnails/1.jpg)
PERIODIC FIELD OBSERVATION REPORT
Project: _Two-Storey Academic Bldg__ Report Number:: _____1_______________Owner: _NDDU – IBED Espina________ Date:_____Sept. 17, 2013______________Re: _Field Observation Report________ Time:_____6:40-8:40__________________
Weather Site Conditions Day
Clear Clear Monday Overcast Muddy Tuesday Rain Dusty Wednesday Foggy _______ Thursday Cold Temperature Range Friday Warm _____________ __________
Hot______________________________________________________________________________ Persons Contacted:
Bro. NinoEngr. Faisal Kusain______________________________________________________________________________Work Observed:
Setting of Steel DeckSetting of slab reinforcement______________________________________________________________________________Items Discussed:
Request for set of plan and specificationsCurrent work done: setting of steel deck for slab and slab reinforcement.Specifications of steel used in construction.Slab concreting on the second floor is expected on September 25.______________________________________________________________________________Remarks:
This is the first field visit on site of the construction project.The construction is on-going for two months now, starting on July 15, 2013, according to the project Engineer on site. The project is contracted for P25.5 M , 10-month period.
Attachments:______________________________________________________________________________Signed By: Date:_____________________________________________________________________________Copies: Owner A/E Contractor Consultants __________ File
![Page 2: Periodic Field Observation Report](https://reader037.vdocuments.mx/reader037/viewer/2022083117/577cce021a28ab9e788d137b/html5/thumbnails/2.jpg)
PERIODIC FIELD OBSERVATION REPORT
Project: _Two-Storey Academic Bldg__ Report Number:: _____2_______________Owner: _NDDU – IBED Espina________ Date:_____Sept. 19, 2013______________Re: _Field Observation Report________ Time:_____3:00______________________
Weather Site Conditions Day
Clear Clear Monday Overcast Muddy Tuesday Rain Dusty Wednesday Foggy _______ Thursday Cold Temperature Range Friday Warm _____________ __________
Hot______________________________________________________________________________ Persons Contacted:
Engr. Faisal Kusain
______________________________________________________________________________Work Observed:
Setting of slab reinforcementSlab reinforcement is 10mmø both for one-way and two-way slabs. The 12mmø as per plan was erroneously written, instead, it should be 10mmø as mentioned by Engr. Kusain
______________________________________________________________________________Items Discussed:
Current work done: setting of steel deck for slab and slab reinforcement.Specifications of steel deck used, 0.80mm thickness.Slab reinforcement is 10mmø both for one-way and two-way slabs and not 12mmø.The number of reinforcing steel bars for columns 1-3.______________________________________________________________________________Remarks:
Eskumbro soil type is on-site for back-filling.
Attachments:______________________________________________________________________________Signed By: Date:_____________________________________________________________________________Copies: Owner A/E Contractor Consultants __________ File
![Page 3: Periodic Field Observation Report](https://reader037.vdocuments.mx/reader037/viewer/2022083117/577cce021a28ab9e788d137b/html5/thumbnails/3.jpg)
PERIODIC FIELD OBSERVATION REPORT
Project: _Two-Storey Academic Bldg__ Report Number:: _____3_______________Owner: _NDDU – IBED Espina________ Date:_____Sept. 20, 2013______________Re: _Field Observation Report________ Time:_____4:30______________________
Weather Site Conditions Day
Clear Clear Monday Overcast Muddy Tuesday Rain Dusty Wednesday Foggy _______ Thursday Cold Temperature Range Friday Warm _____________ __________
Hot______________________________________________________________________________ Persons Contacted:
Engr. Faisal Kusain
______________________________________________________________________________Work Observed:
Setting of slab reinforcementElectrical-setting for electrical connectionsStart of back-filling for a portion of the natural ground line.
______________________________________________________________________________Items Discussed:
______________________________________________________________________________Remarks:
Attachments:______________________________________________________________________________Signed By: Date:_____________________________________________________________________________Copies: Owner A/E Contractor Consultants __________ File
![Page 4: Periodic Field Observation Report](https://reader037.vdocuments.mx/reader037/viewer/2022083117/577cce021a28ab9e788d137b/html5/thumbnails/4.jpg)
PERIODIC FIELD OBSERVATION REPORT
Project: _Two-Storey Academic Bldg__ Report Number:: _____4_______________Owner: _NDDU – IBED Espina________ Date:_____Sept. 24, 2013______________Re: _Field Observation Report________ Time:_____4:30______________________
Weather Site Conditions Day
Clear Clear Monday Overcast Muddy Tuesday Rain Dusty Wednesday Foggy _______ Thursday Cold Temperature Range Friday Warm _____________ __________
Hot______________________________________________________________________________ Persons Contacted:
Engr. Faisal Kusain
______________________________________________________________________________Work Observed:
Electrical-setting for electrical connectionsSetting of slab reinforcement
______________________________________________________________________________Items Discussed:
______________________________________________________________________________Remarks:
Attachments:______________________________________________________________________________Signed By: Date:_____________________________________________________________________________Copies: Owner A/E Contractor Consultants __________ File
![Page 5: Periodic Field Observation Report](https://reader037.vdocuments.mx/reader037/viewer/2022083117/577cce021a28ab9e788d137b/html5/thumbnails/5.jpg)
PERIODIC FIELD OBSERVATION REPORT
Project: _Two-Storey Academic Bldg__ Report Number:: _____5_______________Owner: _NDDU – IBED Espina________ Date:_____Sept. 25, 2013______________Re: _Field Observation Report________ Time:_____9:30__________________
Weather Site Conditions Day
Clear Clear Monday Overcast Muddy Tuesday Rain Dusty Wednesday Foggy _______ Thursday Cold Temperature Range Friday Warm _____________ __________
Hot______________________________________________________________________________ Persons Contacted:
Engr. Faisal Kusain
______________________________________________________________________________Work Observed:
Pouring / Concreting of Second Floor Slab
______________________________________________________________________________Items Discussed:
Specifications of steel used in construction.Specifications of premix concrete for slab concreting on the second floor (14 days, 3000 psi)
______________________________________________________________________________Remarks:
Attachments:______________________________________________________________________________Signed By: Date:_____________________________________________________________________________Copies: Owner A/E Contractor Consultants __________ File
![Page 6: Periodic Field Observation Report](https://reader037.vdocuments.mx/reader037/viewer/2022083117/577cce021a28ab9e788d137b/html5/thumbnails/6.jpg)
PERIODIC FIELD OBSERVATION REPORT
Project: _Two-Storey Academic Bldg__ Report Number:: _____6_______________Owner: _NDDU – IBED Espina________ Date:_____Sept. 27, 2013______________Re: _Field Observation Report________ Time:_____10:30__________________
Weather Site Conditions Day
Clear Clear Monday Overcast Muddy Tuesday Rain Dusty Wednesday Foggy _______ Thursday Cold Temperature Range Friday Warm _____________ __________
Hot______________________________________________________________________________ Persons Contacted:
Leadman Joel Mabagat
______________________________________________________________________________Work Observed:
Setting of Steel Deck/Reinforcement for the remaining portion of second floor slab Setting of column reinforcements for second floorSetting of forms for second floor columns.
______________________________________________________________________________Items Discussed:
______________________________________________________________________________Remarks:
Attachments:______________________________________________________________________________Signed By: Date:_____________________________________________________________________________Copies: Owner A/E Contractor Consultants __________ File
![Page 7: Periodic Field Observation Report](https://reader037.vdocuments.mx/reader037/viewer/2022083117/577cce021a28ab9e788d137b/html5/thumbnails/7.jpg)
PERIODIC FIELD OBSERVATION REPORT
Project: _Two-Storey Academic Bldg__ Report Number:: _____7_______________Owner: _NDDU – IBED Espina________ Date:_____Sept. 30, 2013______________Re: _Field Observation Report________ Time:_____9:30__________________
Weather Site Conditions Day
Clear Clear Monday Overcast Muddy Tuesday Rain Dusty Wednesday Foggy _______ Thursday Cold Temperature Range Friday Warm _____________ __________
Hot______________________________________________________________________________ Persons Contacted:
Leadman Joel Mabagat
______________________________________________________________________________Work Observed:
Setting of Steel Deck/Reinforcement for the remaining portion of second floor slab Setting of column reinforcements for second floorSetting of forms for second floor columns.
______________________________________________________________________________Items Discussed:Splicing of column reinforcements______________________________________________________________________________Remarks:
The following items were counter-checked by actual measuring/counting:
a. The dimensions of columnsb. The diameter and the number of reinforcing steel bars for columns.c. The dimensions of : hallway and classrooms
Attachments:______________________________________________________________________________Signed By: Date:_____________________________________________________________________________Copies: Owner A/E Contractor Consultants __________ File