Page 1: Performance Improvement Update. Next Steps ETCR Meeting – August 17, 2011  Complete analysis of opportunities prepared 1 Qtr 2012  Develop Action Plan:

Performance Improvement

Update

Page 2: Performance Improvement Update. Next Steps ETCR Meeting – August 17, 2011  Complete analysis of opportunities prepared 1 Qtr 2012  Develop Action Plan:

Next Steps ETCR Meeting – August 17, 2011

Complete analysis of opportunities prepared 1 Qtr 2012

Develop Action Plan:

– Management process improvement

– Work rules and practices

– Develop goals by function and specific work

– Develop effective metrics and measurement process

Savings achieved through attrition

No plans for layoffs from efficiency improvements

2Draft

Page 3: Performance Improvement Update. Next Steps ETCR Meeting – August 17, 2011  Complete analysis of opportunities prepared 1 Qtr 2012  Develop Action Plan:

Management Process Improvement Opportunities

Crew Sizing

• Network crews

• Line Service crews

• Line crews

• Streetlight crews (one person)

• Stations crews

• Resource requirements for locating services

3Draft

Page 4: Performance Improvement Update. Next Steps ETCR Meeting – August 17, 2011  Complete analysis of opportunities prepared 1 Qtr 2012  Develop Action Plan:

Management Process Improvement Opportunities

Re-organize management

Pole replacement – one crew set and transfer

Reinforce some poles with wood stub or steel stay

Compatible Units to standardize design and construction

4

Draft

Page 5: Performance Improvement Update. Next Steps ETCR Meeting – August 17, 2011  Complete analysis of opportunities prepared 1 Qtr 2012  Develop Action Plan:

Management Process Improvement Opportunities

Non-traditional network hours in Network area

Non-traditional Line crew work hours

Non-traditional work weeks for some crews

Crew Scheduling system

Mobile Data Dispatch

5

Draft

Page 6: Performance Improvement Update. Next Steps ETCR Meeting – August 17, 2011  Complete analysis of opportunities prepared 1 Qtr 2012  Develop Action Plan:

Management Process Improvement Opportunities

Identify OH work that can be easily segregated and contracted during peak workload

Identify UG bodies of work that can be easily segregated and contracted during peak workload

Identify civil construction bodies of work that can be easily segregated and contracted during peak workload

Review Seattle and Suburban City permitting requirements for traffic control and Street Use permits

6

Draft

Page 7: Performance Improvement Update. Next Steps ETCR Meeting – August 17, 2011  Complete analysis of opportunities prepared 1 Qtr 2012  Develop Action Plan:

Work Rules and Practices Opportunities

Broaden Job Descriptions

– Roles of Line Service and Field System Operations

– Qualified electrical worker perform OH or UG

OH and UG Line crews

Line Service crews

Two Line Service crews 24/7 (two OH crews per truck)

Two tiered overtime rate for scheduled and unscheduled work

Stand-by crew process

7

Draft