perencanaan pembangunan jaringanfttxsmkm1-kpn.sch.id/~namrif/materi fiber optic/h-2b-...
TRANSCRIPT
Perencanaan PembangunanJaringan FTTx
ByMumu& Andri
FTTx networkssystem
PoP (PointofPresence) ODN(OpticalDistributionNetworks) CPE(CustomersPremiseEquipments)
ByMumu& Andri
CableBackbone&CableFishbone§ CableBackbone
Ø Capacity:48/4T,24/4T§ CableFishbone
Ø Capacity:12/2T,6/1T
ODN(OpticalDistributionNetworks)
ByMumu& Andri
Kombinasi Splitter
1PON=1G(1000Mbps)
64USER/ONU15Mbps/ONU
Topology FTTx Networks
ByMumu&Andri
48Core24Core
12Core
12Core12Core- 3Km
24Core
DPFO– Splitter1- 8
PoP AreaJointBox
48Core
24Core– 4Km
24Core
JointBox
JointBox
12Core DropCable2Core
OLTOLTOLTOLT
DPFO
DPFO– Splitter1
DPFO– Splitter8
12Core12Core
2Km
4 Km
150m
DPFO– Splitter1- 8
4 Km2Km
Source : LA
ByMumu& Andri
PerencanaanPembangunan
FTTx
MembuatBoundarypadaMapsource
/GoogleEarth
Membuat JalurBackbone&Fishbone
Membuat TabelLinkBudget
Membuat TabelBOQ(BillOfQuantity)
Perencanaan PembangunanFTTx
ByMumu& Andri
DesignMappingJaringan FTTx
Standar SymbolDesignMappingJaringan
:PoP (PointofPresence)
:JointClosure/MainSplitter
:ODP/Splitter
:Pole7&9Meter
:Kabel Optik 96Core
:Kabel Optik 48Core
:Kabel Optik 24Core
:Kabel Optik 12Core
ByMumu& Andri
LinkBudget
BOQ(BillOfQuantity)
ByMumu& Andri
TimeLinePembangunanFTTx
ByMumu& Andri
2015Week1 3 5 7 9 11 13 15 17 19
6/20/2015
6/22/2015
6/29/2015
6/29/2015
6/29/2015
7/5/2015 7/27/2015 8/24/2015
8/31/2015
9/7/2015
9/14/2015
6/14/2015- 6/20/2015FinalisasiDesign
6/21/2015- 6/28/2015FinalisasiSPH
6/29/2015- 7/3/2015PenandatangananPO/SPK
6/29/2015- 7/10/2015PengajuanIjinPembangunan
6/29/2015- 7/10/2015PemesanMaterial
7/5/2015- 8/21/2015ProsesProduksiMaterial
7/27/2015- 8/7/2015ProsesAkusisiLahanPoP
8/24/2015- 8/28/2015DeliveryMaterialkeLokasi
8/10/2015- 9/14/2015PembangunanPoP
9/1/2015- 10/23/2015ProsesPemasanganTiangdanKabel
10/26/2015-10/30/2015TestdanCommissioning
TIMEPLANRENCANAPEMBANGUNANFTTx
ByMumu& Andri
Optical Termination Box
UPS 4000 VA – 48 V & Battery 12 V 100 AhManageable Switch BDCOM S 3928 GX
Manageable Switch BDCOM S 5612
OLT BDCOM P 3616
Open Rack 42 U
PoP Equitment Specification
Joint Closure Type Inline
Joint Closure Type Dome
Pedestal
PLC Splitter
ODP/DPFO
Kabel Optik Type G 652 D
Steelband
Buckle
ODNEquitment Specification
Dea
dend
Braket
Pole`s & Accessories
ByMumu& Andri
CustomerPremiseEquipments (CPE)
ByMumu& Andri
• DropCable2CoreRoundTypeG657• Fiber Outlet• SCAdaptor.• Patchcord SC-SCpanjang 3mm• OpticalNetworkUnit(ONU)
Perangkat yangterpasang diCPE:
ByMumu& Andri
PoP (PointofPresence)
ByMumu& Andri
PoP (PointofPresence)
§ Bangunan luas 2m x 2m dan tinggi langit-langit 2.5m
§ Dinding tembokbata finishingacian dan cat§ Lantai keramik§ Pintu Plat Besi 80 x 180 cm denganketebalan plat 2 mm dan Ventilasi udara
§ Ventilasi udara 30 x 30 cm dengan WireMesh dilapisi Kain Nonwoven (Kain Filter)
§ Compressor (Outdoor Unit) dan dipasangTeralis
ByMumu& Andri
• UPS dengan kapasitas 4000VA 48 VDC• Battery yang dipasang adalah 4 buah battery 12 V
100 AH• AC (Air Conditioning) setiap PoP standar dipasang
2 buah AC Panasonic dengan kapasitas masing-masing 1 PK
• Pengaturan AC (Timer) untuk masing – masing ACselama 12 Jam
• Proteksi Perangkat PoP menggunankan Arrester 1Phase N +1 20 kA
Mechanical Electrical
ByMumu& Andri
ODN(OpticalDistributionNetworks)
ByMumu& Andri
Deadend
Steelband
Buckle
Braket
Accessories Pole1
Pole`s&Accessories
Standard Pole 7 & 9 m2
§ Pole 9 m ditanam dengankedalaman 150cm dan Pole7 m ditanam dengankedalaman 120 cm, dansisanya di atas permukaantanah.
§ Pondasi beton Polesepanjang 60 cm, dengan 40cm tertanam di dalamtanah, dan 20 cm dipermukaan tanah. Diameterbeton 20 cm
§ Jarak antar tiang maksimal80m (Span 80)
Pole7meter1
Pole9meter2
StandardPemasangan Pole7&9Meter
ByMumu& Andri
StandardPemasangan JointBoxandODP/DPFO
ByMumu& Andri
COREMANAGEMENT
• Point Of Presence (PoP)
• Backbone
ByMumu& Andri
• Fishbone