S.No Item Unit Rate (In Crores)
1 Section
Viaduct PKM 35.28
2 Station
Elevated Station Each 41.33
3 P.Way Works PKM 8.33
4 Traction works
Elevated PKM 17.97
5 E/M works at StationsElevated Each 7.18
6 Signalling & Telecommunication PKM 17.99
7 AFC Each 2.81
8Rolling Stock @ Rs.40.20 crore per coach for rake of 8
coachesPKM 40.20
Total Per km. cost (Elevated) In Crores 171.09
Design charges @ 2 % 3.42
Continegencies @ 3 % 5.13
General Charges @ 9.13% 15.62
Octroi on OHE & AFC @ 7% 1.45
Octroi on Sig.&Tele. @ 7% 1.26Octroi on Rolling stock @7% 2.81
Octroi on other materials @ 1% of balance project
cost0.92
201.71
SAY 202.00
S.No Item Unit Rate (In Crores)
1 Section
TBM Tunnel PKM 120.00
2 Station
UG Station Each 111.20
3 P.Way Works PKM 8.33
4 Traction works
Underground PKM 17.97
5 E/M works at Stations
Underground Each 38.27
6 Signalling & Telecommunication PKM 17.99
7 AFC Each 2.81
8Rolling Stock @ Rs.40.20 crore per coach for rake of 8
coachesPKM 40.20
Total per km. cost UG by using TBM In Crores 356.77
Design charges @ 2 % 7.14
Continegencies @ 3 % 10.70
General Charges @ 9.13% 32.57
Octroi on OHE & AFC @ 7% 1.45
Octroi on Sig.&Tele. @ 7% 1.26
Octroi on Rolling stock @7% 2.81
Octroi on other materials @ 1% of balance project
cost2.78
415.49
SAY 415.00
PER KILOMETER COST ELEVATED SECTION (BG)
PER KILOMETER COST UNDERGROUND SECTION BY USING TBM (BG)
-
8/12/2019 Per Km Cost Metro Works 1
2/3
S.No Item Unit Rate (In Crores)
1 Section
Cut and Cover Tunnel PKM 80.00
2 Station
UG Station Each 111.20
3 P.Way Works PKM 8.33
4 Traction works
Underground PKM 17.97
5 E/M works at Stations
Underground Each 38.27
6 Signalling & Telecommunication PKM 17.99
7 AFC Each 2.81
8Rolling Stock @ Rs.40.20 crore per coach for rake of 8
coachesPKM 40.20
Total per km. cost UG by using Cut & Cover In Crores 316.77
Design charges @ 2 % 6.34
Continegencies @ 3 % 9.50
General Charges @ 9.13% 28.92
Octroi on OHE & AFC @ 7% 1.45
Octroi on Sig.&Tele. @ 7% 1.26
Octroi on Rolling stock @7% 2.81
Octroi on other materials @ 1% of balance project
cost2.38
369.44
SAY 369.00
S.No Item Unit Rate (In Crores)
1 SectionAt Grade PKM 16.00
2 Station
At Grade Station Each 23.33
3 P.Way Works PKM 1.75
4 Traction works
At Grade PKM 17.97
5 E/M works at Stations
At Grade Each 7.18
6 Signalling & Telecommunication PKM 17.99
7 AFC Each 2.81
8 Rolling Stock @ Rs.40.20 crore per coach for rake of 8coaches
PKM 40.20
Total per km. cost at grade In Crores 127.23
Design charges @ 2 % 2.54
Continegencies @ 3 % 3.82
General Charges @ 9.13% 11.62
Octroi on OHE & AFC @ 7% 1.45
Octroi on Sig.&Tele. @ 7% 1.26
Octroi on Rolling stock @7% 2.81
Octroi on other materials @ 1% of balance project
cost0.48
151.22
PER KILOMETER COST UNDERGROUND SECTION BY USING CUT & COVER (BG)
PER KILOMETER COST AT GRADE SECTION (BG)
-
8/12/2019 Per Km Cost Metro Works 1
3/3
SAY 151.00