  • 8/12/2019 Per Km Cost Metro Works 1

    1/3

    S.No Item Unit Rate (In Crores)

    1 Section

    Viaduct PKM 35.28

    2 Station

    Elevated Station Each 41.33

    3 P.Way Works PKM 8.33

    4 Traction works

    Elevated PKM 17.97

    5 E/M works at StationsElevated Each 7.18

    6 Signalling & Telecommunication PKM 17.99

    7 AFC Each 2.81

    8Rolling Stock @ Rs.40.20 crore per coach for rake of 8

    coachesPKM 40.20

    Total Per km. cost (Elevated) In Crores 171.09

    Design charges @ 2 % 3.42

    Continegencies @ 3 % 5.13

    General Charges @ 9.13% 15.62

    Octroi on OHE & AFC @ 7% 1.45

    Octroi on Sig.&Tele. @ 7% 1.26Octroi on Rolling stock @7% 2.81

    Octroi on other materials @ 1% of balance project

    cost0.92

    201.71

    SAY 202.00

    S.No Item Unit Rate (In Crores)

    1 Section

    TBM Tunnel PKM 120.00

    2 Station

    UG Station Each 111.20

    3 P.Way Works PKM 8.33

    4 Traction works

    Underground PKM 17.97

    5 E/M works at Stations

    Underground Each 38.27

    6 Signalling & Telecommunication PKM 17.99

    7 AFC Each 2.81

    8Rolling Stock @ Rs.40.20 crore per coach for rake of 8

    coachesPKM 40.20

    Total per km. cost UG by using TBM In Crores 356.77

    Design charges @ 2 % 7.14

    Continegencies @ 3 % 10.70

    General Charges @ 9.13% 32.57

    Octroi on OHE & AFC @ 7% 1.45

    Octroi on Sig.&Tele. @ 7% 1.26

    Octroi on Rolling stock @7% 2.81

    Octroi on other materials @ 1% of balance project

    cost2.78

    415.49

    SAY 415.00

    PER KILOMETER COST ELEVATED SECTION (BG)

    PER KILOMETER COST UNDERGROUND SECTION BY USING TBM (BG)

  • 8/12/2019 Per Km Cost Metro Works 1

    2/3

    S.No Item Unit Rate (In Crores)

    1 Section

    Cut and Cover Tunnel PKM 80.00

    2 Station

    UG Station Each 111.20

    3 P.Way Works PKM 8.33

    4 Traction works

    Underground PKM 17.97

    5 E/M works at Stations

    Underground Each 38.27

    6 Signalling & Telecommunication PKM 17.99

    7 AFC Each 2.81

    8Rolling Stock @ Rs.40.20 crore per coach for rake of 8

    coachesPKM 40.20

    Total per km. cost UG by using Cut & Cover In Crores 316.77

    Design charges @ 2 % 6.34

    Continegencies @ 3 % 9.50

    General Charges @ 9.13% 28.92

    Octroi on OHE & AFC @ 7% 1.45

    Octroi on Sig.&Tele. @ 7% 1.26

    Octroi on Rolling stock @7% 2.81

    Octroi on other materials @ 1% of balance project

    cost2.38

    369.44

    SAY 369.00

    S.No Item Unit Rate (In Crores)

    1 SectionAt Grade PKM 16.00

    2 Station

    At Grade Station Each 23.33

    3 P.Way Works PKM 1.75

    4 Traction works

    At Grade PKM 17.97

    5 E/M works at Stations

    At Grade Each 7.18

    6 Signalling & Telecommunication PKM 17.99

    7 AFC Each 2.81

    8 Rolling Stock @ Rs.40.20 crore per coach for rake of 8coaches

    PKM 40.20

    Total per km. cost at grade In Crores 127.23

    Design charges @ 2 % 2.54

    Continegencies @ 3 % 3.82

    General Charges @ 9.13% 11.62

    Octroi on OHE & AFC @ 7% 1.45

    Octroi on Sig.&Tele. @ 7% 1.26

    Octroi on Rolling stock @7% 2.81

    Octroi on other materials @ 1% of balance project

    cost0.48

    151.22

    PER KILOMETER COST UNDERGROUND SECTION BY USING CUT & COVER (BG)

    PER KILOMETER COST AT GRADE SECTION (BG)

  • 8/12/2019 Per Km Cost Metro Works 1

    3/3

    SAY 151.00