PENNDOT PROJECT INFORMATION
South Arch StreetBridge Replacement
SR 1037, Section B10City of Connellsville,
Fayette County
PROJECT TEAM
Design Division
Direct questions to:
Brian C. Svesnik - Project Manager at 724.415.2400Engineering District 12-0 | Project Delivery Unit,825 N. Gallatin Avenue | Uniontown, PA 15401or [email protected].
Cristin Covert - District Environmental Manager
District Officials
Jay Ofsanik - Safety Press Officer
Valerie Petersen - Community Relations Coordinator
Please complete survey at end of presentation
PURPOSE OF PRESENTATION & PROJECT INTRODUCTION
SR 1037, Section B10 (South Arch Street) Bridge Project
The purpose of this presentation is to introduce the project to the public, gather feedback, and present the traffic impacts that will occur during construction.
The purpose of this project is to maintain a safe and reliable crossing for vehicular and pedestrian traffic at South Arch Street over Trump Run in the City of Connellsville.
PROJECT LOCATION
Project Location
PROPOSED PROJECT IMPROVEMENTS
Bridge Replacement Project
Existing Structure is a single-span supported by concrete encased steel beams.
Scope of work includes replacement of superstructure and abutments with a precast concrete box culvert, rock lining streambank protection, drainage improvements, approach roadway pavement resurfacing between points 115 feet south and 115 feet north of the new structure, sidewalk reconstruction, and guide rail replacement.
Project will be built utilizing a full detour for vehicular and pedestrian traffic.
PROPOSED PROJECT IMPROVEMENTS
Bridge Replacement Project (Cont’d)
Right-of-Way will be acquired at upstream and downstream sides of South Arch Street for culvert construction and other related work. Additionally, channel easements will be required for rock lining placement in the stream channel, and temporary construction easements will be required to accommodate construction activities.
Underground utilities will likely need relocation to allow for excavation for culvert installation. Utilities affected include Columbia Gas of Pennsylvania, Pennsylvania American Water, and Connellsville Municipal Authority (sanitary).
Construction anticipated to begin the summer of 2022.
PROPOSED TRAFFIC CONTROL
Traffic Control Plan
During construction of the bridge replacement and roadway work, vehicular traffic on South Arch Street (SR 1037) will be detoured via West Cedar Avenue, South Pittsburgh Street (SR 1037), and West Woodlawn Ave. The detour route length is just under one (1) mile (0.9 miles) from closure point to closure point. Pedestrians will be expected to use these same roads, but total detour length is 1.1 miles.
Local Traffic Access
Access to Connellsville Area School Stadium, DraybellaSalon, Rocky’s Auto Services and residences along South Arch Street will be provided at all times, from the south via South Arch Street and West Woodlawn Avenue.
Project Location
Connellsville Area School Stadium
Draybella Salon
SOUTH ARCH STREET (SR 1037) VEHICLE DETOUR PLAN
SR 1037 Detour Route Detour Length – 0.9 milesTraffic Flow
SOUTH ARCH STREET (SR 1037)PEDESTRIAN DETOUR PLAN
Detour Length – 1.1 milesSR 1037 Detour Route
Traffic Flow
NATIONAL ENVIRONMENTAL POLICY ACT (NEPA)
Public outreach begins with PennDOT Connectsand extends into the NEPA (National Environmental Policy Act) process:
NEPA requires agencies to integrate environmental values into their decision-making processes by considering the environmental impacts of their proposed actions and reasonable alternatives to those actions
NEPA also includes public involvement activities and gathering feedback from the public
Image courtesy of MDOT