BENGKEL LAS BAGOESAlamat : Jalan Raya Kedung Asem No 53 Surabaya
Telp. 081234267220
Kebutuhan Bahan Pekerjaan Baja Noah
1. WF 200 = 27 btg × 256 kg = 6912 kg × 9.600 = Rp 66.355.200
2. CNP 125, 2,3 = 160 btg × 165.000 = Rp 26.400.000
3. Plat easer 10mm = 2 lbr × 233kg = 466kg × 10.000 = Rp 4.660.000
4. Plat easer 8mm = 2lbr × 187 kg = 374kg × 10.000 = Rp 3.740.000
5. Besi beton 16mm = 33btg × 130.000 = Rp 4.290.000
6. Besi beton 10mm = 120btg × 55.000 = Rp 6.600.000
7. Baut 5/8 2” = 980 biji × 1.780 = Rp 1.744.400
8. Baut ½ 1” = 900 biji ×1.100 = Rp 990.000
9. Mur N10 = 600 biji × 500 = Rp 300.000
10.Jarum keras 20mm = 24 biji × 30.000 = Rp 720.000
11.Baut dreling = 2500 biji × 325 = Rp 812.500
Hormat kami
Samsul Mu’in