PCSM Changes per the New Chapter 102

Presented By: Jason Bailey, E.I.T.

Page 2: Pcsm requirements   copy

Overview

• General PCSM Changes

• PCSM Plans• PCSM Report• Analysis• Implementation for

Special Protection Waters

• Long Term Operations and Maintenance

• Certification Criteria

Page 3: Pcsm requirements   copy

General PCSM• As of November 19th, 2010

– All projects greater than 1 acre will require an NPDES Permit Application

– Permits considered administratively complete as of November 19th, 2010 are grandfathered from Long Term O&M and buffer requirements

– Renewals considered administratively complete by January 1st, 2013 are also grandfathered from Long Term O&M and buffer requirements

Page 4: Pcsm requirements   copy

PCSM Plans• PCSM Plans must be consistent with and separate

from E&S Plans• PCSM Plans must be prepared by a person with

experience in PCSM and projects of applicable size and scope

• Contents:– Existing topographic features of the site and

surrounding area– Types, depth, slope, locations and limitations of soils– Identification and classification of surface waters– Location and type of PCSM BMP’s– Separate sequence for PCSM BMP construction and

critical inspections (E&S Plan too)– O&M Schedule, including noting requirement of

written record of inspection and actions taken (E&S Plan too)

– A riparian buffer or forest buffer plan (when required)

Page 5: Pcsm requirements   copy

PCSM Report

• Characteristics of the site including land use (up to 50 years ago) and proposed alterations

• Net change pre. vs. post. in volume and rate

• Identification of thermal impacts and prevention and mitigation measures

• Infiltration and geo-technical studies

• Supporting Calculations– Demonstration that PCSM BMP’s meet rate reductions,

volume reductions and water quality

– 2-year through 100-year event analysis

Page 6: Pcsm requirements   copy

Analysis• Existing pre-development non-forested

pervious areas must be considered meadow in good condition

– Repair, reconstruction and restoration of roadways, rail lines and utility infrastructure are exempt from this criteria.

Page 7: Pcsm requirements   copy

Analysis Continued

• Existing pre-development non-forested pervious areas must be considered meadow in good condition

– Repair, reconstruction and restoration of roadways, rail lines and utility infrastructure are exempt from this criteria.

Page 8: Pcsm requirements   copy

Implementation for Special Protection Waters

• Any project in HQ, EV or discharging to EV Wetlands must perform anti-degradation analysis

– Must evaluate for non-discharge alternatives

– If no non-discharge alternatives exist, the project must demonstration meeting ABACT criteria

Page 9: Pcsm requirements   copy

Long Term Operations and Maintenance

• Permittee and co-permittee will remain responsible with the land owner for long term O&M unless a different person is identified in the Notice of Termination

• Person responsible for long term O&M may enter into an agreement with another party– Transfer responsibility– Perform O&M

• Notice and recorded instrument should be provided to DEP and Conservation District– An instrument shall be recorded with

Recorder of Deeds and contain the following• Indentify the PCSM BMP• Provide access• Provide notice that the responsibility for O&M

of PCSM BMP’s runs with property

Page 10: Pcsm requirements   copy

Certification Criteria• Licensed professional (designer or delegated person)

must be on-site during critical stages– Critical stages include:

• Installation of underground storage or treatment BMP’s

• Installation of structurally engineered BMP’s

• Installation of other BMP’s deemed appropriate by DEP or Conservation District.

• Inspection schedule must be provided on E&S and PCSM Plans

• Three copies of record drawings must be submitted– One copy for the District

– One for the permittee

– One for the party responsible for Long Term O&M

Page 11: Pcsm requirements   copy

Certification Criteria Cont.

• Certification

– ‘‘I (name) do hereby certify pursuant to the penalties of 18 Pa. C.S.A. § 4904 to the best of my knowledge, information and belief, that the accompanying record drawings accurately reflect the as-built conditions, are true and correct, and are in conformance with Chapter 102 of the rules and regulations of the Department of Environmental Protection and that the project site was constructed in accordance with the approved PCSM Plan, all approved plan changes and accepted construction practices.’’

– This language is to be stamped and signed by the licensed professional

Page 12: Pcsm requirements   copy

Questions