pavement evaluation and rehabilitation of flexible ... · fig-2: benkelman beam test the results of...
TRANSCRIPT
International Journal of Engineering Technology, Management and Applied Sciences
www.ijetmas.comMay 2017, Volume 5, Issue 5, ISSN 2349-4476
655 Abhishek M. Loya, S.M.Damodariya,Sharad N. Deokar
Pavement Evaluation and Rehabilitation of Flexible Pavement
by Overlay Incorporating Waste Plastic
Abhishek M. Loya
P.G Student
PIET, Parul University
Vadodara
S.M.Damodariya
Reader
PIET, Parul University
Vadodara
Sharad N. Deokar
Consultant
Shri Aranyeshwar Consultancy
& Testing Services Nashik.
ABSTRACT
This research paper deals with evaluation and rehabilitation of flexible pavement near Dindori in Nashik. Benkelman
Beam deflection method for overlay design is used for designing pavement overlay thickness. This research also throws
light on use of waste plastic (PET) in pavement overlay and its structural and economical comparison with conventional
type flexible pavement overlay.
Keywords
Overlay Design, Benkelman beam Deflection, Waste Plastic (PET).
1. INTRODUCTION
Pavements are one of the most crucial factors to connect the society. Health of the pavements is not assessed
from time to time and it results in their poor performance not only leading to many accidents but also
increased running cost. The condition of pavement gets deteriorated as time passes unless maintenance is
properly done.
A new MIDC is being proposed in Dindori area in Nashik. The existing approach road condition for the same
is to be enhanced looking at the future increase of Commercial vehicle traffic load. Existing pavement is a
Flexible pavement with bituminous surfacing and 5.5m width with clayey soil in subgrade. The high traffic
intensity in terms of commercial vehicles, overloading of axles and significant variations in daily and seasonal
temperature of the pavement will be responsible for early development of distress symptoms like undulations,
rutting, cracking, and potholing of bituminous surfacing in future. Here Overlay Design along with widening
from 5.5m to 7.5m is being proposed to overcome the same problems using Benkelman beam deflection
method. Additional to this use of waste plastic and its structural and economical aspects were studied.
Following methodology is adopted for the study:
1) Existing traffic volume study was carried out.
2) Condition survey of the existing pavement was carried out.
3) Benkelman Beam deflection test was carried out for the stretch of 8 km.
4) Pavement overlay thicknesses for every 1 km were calculated.
5) Waste Plastic (PET) was used in pavement overlay. Following is basic process of using waste plastic
with bitumen.
a) Collection of PET Bottles.
b) Cleaning Process.
c) Shredding Process.
d) Collection Process.
6) Comparison between conventional overlay and waste plastic blended overlay was studied
2. CONDITION SURVEY
A visual survey has been be used to evaluate the surface condition of segments of pavement at MDR
AkralePhata to Mohadi Village, Nashik .On moving from starting to CH:0/00 km to CH:8/00 km the surface
International Journal of Engineering Technology, Management and Applied Sciences
www.ijetmas.comMay 2017, Volume 5, Issue 5, ISSN 2349-4476
656 Abhishek M. Loya, S.M.Damodariya,Sharad N. Deokar
was observed. The distress types generally resulting from environmental factors in conjunction with traffic:
Random or block cracking o transverse cracking.Load associated distress manifestations: alligator cracking,
shear failure or potholes.
The condition survey observations are coded as Surface defects: A, Crack types: B, Deformation: C and
Disintegration: D, are provided in Table 1 and observations of conditions are recorded in Table II as given
below.
Table 1: Measurement for Condition Survey
SurfaceDefects
(A)
Crack type
(B)
Deformation(C) Disintegration
(D)
1.Smooth surface 1. Hairline
crack
1.Ruts 1.Ravelling
2.Hungry surface 2. Alligator crack 2.Settlement 2.Potholes
3. Longitudinal crack 3. Sunk
4.Edge crack
5. Shrinkage cracks
6.Transverse crack
Table 2: Pavement Condition Survey on M.D.R: AkralePhata to
Mohadi Village, Nashik (CH:0/00 KM to CH:8/00 KM)
Chainage(m) Defects Condition
100 B2,B3,D1 Fair
450 B2,B3,B4,C1 Fair
600 A2,C1 Good
850 A2,B5,B6,D2,D1 Poor
900 A2,B1,B4,B6, Fair
950 A2,B5,B6,D2,D1 Very poor
1600 A1,B4,B5 Fair
2200 A2,B1,C1,C2,D2 poor
2550 B2,B4,B5,B6 Fair
2600 C-D Work
3400 B4,B5,C3,D1 Fair
3450 Damaged Portion
3500 B1,B4,D1 Fair
4500 B2,B6,D2 Fair
4600 D2 Poor
5200 A1,A2 Fair
5550 A2,B1,B4,B6, Fair
5600 A2,B5,B6,D2,D1 Poor
5750 A2,B1,B4,B6, Fair
5850 A2,B5,B6,D2,D1 Very poor
5900 A2,B1,B4,B6, Fair
6100 B1,B4 Fair
6250 B2,B6,D2 Fair
6900 B2,B3 Fair
7400 B2,B3,B4,C1 Fair
7600 D1. D2 , Poor
7900 D2 poor
International Journal of Engineering Technology, Management and Applied Sciences
www.ijetmas.comMay 2017, Volume 5, Issue 5, ISSN 2349-4476
657 Abhishek M. Loya, S.M.Damodariya,Sharad N. Deokar
3. TEST AND RESULTS
3.1 C.B.R Test on Soil
C.B.R. test was carried out for the sample collected from the site. The samples were collected from most
damaged road section and each was tested two times for C.B.R value. The results are tabulated below.
Fig-1- C.B.R Test on Soil
Table 3- C.B.R test results
Penetration
in (mm)
Sample
1
Avg. Sample
2
Avg.
2.5 3.34 3.44
5 3.24 3.33 3.03 3.51
2.5 3.32 3.58
5 3.30 3.08
From the test result it is seen that the average C.B.R value taken was equal to 3.42.
3.2 Benkelman Beam Deflection Test
Following data was collected prior to the deflection test.
1. Traffic in C.V. per Day : 490
2. Year of traffic count : 2016
3. Vehicle damage factor : 3.75
4. Annual traffic growth rate : 7.50%
5. Year of traffic projection : 2032
International Journal of Engineering Technology, Management and Applied Sciences
www.ijetmas.comMay 2017, Volume 5, Issue 5, ISSN 2349-4476
658 Abhishek M. Loya, S.M.Damodariya,Sharad N. Deokar
6. Annual rainfall in mm : 900
7. Type of Subgrade : clayey soil
8. Plasticity index of soil : 14.5
9. Existing terrain : plain
10. Existing pavement condition: fair
Projected traffic in M.S.A
Calculation
𝑁𝑠 =365 × 𝐴 × 1 + 𝑟 𝑥 − 1
𝑟× 𝐹
= 20.24 MSA
The test was carried per Kilometer according to IS-81:1997.
Fig-2: Benkelman Beam Test
The results of the test are tabulated below in terms of thicknesses of overlay required for each span.
Table 4- Abstract of the Test
Sr.No. Kilometer Required Overlay as Per Testing
in terms of BM
Required Overlay as Per
Testing in Terms of BC
1 0-1 95 mm 66.5 mm
2 1-2 110 mm 77 mm
3 2-3 85 mm 60 mm
4 3-4 75 mm 52.5 mm
5 4-5 125 mm 87.5 mm
6 5-6 135 mm 94.5 mm
7 6-7 97 mm 70 mm
8 7-8 138 mm 96.6 mm
Average 107.5 mm 76 mm
International Journal of Engineering Technology, Management and Applied Sciences
www.ijetmas.comMay 2017, Volume 5, Issue 5, ISSN 2349-4476
659 Abhishek M. Loya, S.M.Damodariya,Sharad N. Deokar
3.3 Marshall Stability Test
Marshall Stability test was carried out for conventional mix as well as for waste plastic blended mix.Marshal
specimens were prepared with varying binder content viz. 4.5, 5.0, 5.5, and 6.0 percent by the weight of
aggregate. Three specimens for each combination were prepared to obtain optimum binder content for the
bituminous concrete mix is as show in the Table
Table 5- Abstract of the Test
Property Binder content by weight of aggregate (%)
4.5 5.0 5.5 6.0
Marshal Stability (Kg.) 1258 1383 1480 1280
Bulk density (gm/cc) 2.327 2.363 2.377 2.367
Flow values (mm) 2.6 3.5 4.2 4.6
Air Voids (%) 6.8 4.6 3.4 3.2
Voids filled with bitumen
VMA (%)
59.7 70.7 78.7 80.9
OBC (Optimum bitumen
content) (%)
5.5
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
4.5 5 5.5 6
Flo
w V
alu
e (
mm
)
Bitumen Content(%)
2.3
2.31
2.32
2.33
2.34
2.35
2.36
2.37
2.38
2.39
4.5 5 5.5 6
Bu
lk D
en
sity
(gm
/cc)
Bitumen Content (%)
International Journal of Engineering Technology, Management and Applied Sciences
www.ijetmas.comMay 2017, Volume 5, Issue 5, ISSN 2349-4476
660 Abhishek M. Loya, S.M.Damodariya,Sharad N. Deokar
Fig 3:Graphof Marshall Stability test
The modifier was added into the heated aggregate just before mixing the bitumen at the optimum 5.5 percent
binder content. It was found that the optimum modifier (waste plastic) content was 8 per cent by weight of
bitumen.Marshal mix design was conducted by varying the binder content viz 4.5, 5.0, 5.5,6.0 percent by
weight of aggregate and 8 per cent waste plastic (by weight of binder)
Table 6: Properties of Bituminous Concrete mix 8 percent waste plastic
Property Binder content by weight of aggregate (%)
4.5 5.0 5.5 6.0
Marshal Stability (Kg.) 1725 1753 1798 1733
Bulk density (gm/cc) 2.225 2.228 2.355 2.342
Flow values (mm) 3.6 3.8 4.1 4.4
Air Voids (%) 6.9 5.7 4.4 3.8
VFB (%) 59.3 66.3 73.8 77.5
VMA (%) 16.7 16.6 16.4 17.0
OBC (Optimum bitumen
content) (%)
5.5
1100
1150
1200
1250
1300
1350
1400
1450
1500
4.5 5 5.5 6
Mar
shal
l Sta
bili
ty (
Kg.
)
Bitumen Content %
International Journal of Engineering Technology, Management and Applied Sciences
www.ijetmas.comMay 2017, Volume 5, Issue 5, ISSN 2349-4476
661 Abhishek M. Loya, S.M.Damodariya,Sharad N. Deokar
Table 7: Comparison of volumetric properties of the mixes
Properties Modified Mix
(waste plastic)
Conventional mix
Marshal stability (kg.) 1800 1450
Bulk density (gm/cc) 2.350 2.374
VFB) (%) 73 76
Flow values (mm) 4 4
VMA (%) 16.5 15.6
Retained Stability (%) 4.98 88
4. COST ANALYSIS
Based on the above prices of convectional and modified bitumen, the cost of overlay construction for
modified and convectional 80/100 bitumen would be as in given table-Typical estimated cost of modified
bitumen vs. conventional bitumen.
Table 8: The cost of construction per cubic meter using conventional Bitumen
Sr. No Mix Binder Content
(%)
Amount
(Cu.m)
Rate of Bitumen
(MT)
1 BM 3.5 8820 82152
2 AC 6.25 15359 82152
Table 9: The cost of construction per cubic meter using Waste plastic Blended Bitumen
.Sr. No Mix Binder Content
(%)
Amount
(Cu.m)
Rate of Bitumen
(MT)
1 BM 3.5 8379 65221
2 AC 6.25 14590 65221
Above analysis shows that cost of construction of flexible pavement can be reduces up to 6% by
replacing bitumen with waste plastic.
Conclusion
Pavement Evaluation of the existing road was carried out which gave an indication of requirement of overlay.
Benkelman Beam Deflection method was used to design the overlay and overlay thickness for various
stretches were computed. An average thickness of 107.5 mm in BM and 76mm in terms of BC was
proposed.
International Journal of Engineering Technology, Management and Applied Sciences
www.ijetmas.comMay 2017, Volume 5, Issue 5, ISSN 2349-4476
662 Abhishek M. Loya, S.M.Damodariya,Sharad N. Deokar
Overlay incorporating Waste Plastic was also studied, it was found that for optimum binder content of 5.5
% and optimum waste plastic content of 8% by weight of bitumen increases the strength and performance
as compared to conventional mix.
By using the waste plastic reduces the dumping problems and more over by mixing it with bitumen it also
decreases the maintenance cost of the roads and also increases the life of the road.
REFERENCES [1] IRC.81 1997
[2] Khaled A. Abaza, P.E.1 Performance-Based Models for Flexible Pavement Structural Overlay Design, J. Transp.
Eng., 2005, 131(2): 149-159
[3] TienF. Fwa,1 Member, ASCE,Remaining-life consideration in pavement Overlay design, J. Transp. Eng., 1991,
117(6): 585-601
[4] Nilesh Kumar, Dr.P.D.Arumairaj ,Comparison Study of Overlay Design for Pavement using Light Weight
Deflectometer and Benkelman Beam, Volume : 4 | Issue : 6 | June 2015 ISSN No 2277 – 8179
[5] M. Amaranatha Reddy*,K. Sudhakar Reddy** & B.B. Pandey***, A rational approach for design of flexible
overlays for Indian highways,Highway Research BulletinYear 2004-2005bulletin no. 73
[6] Anil Kumar Sharama, Dr.Umesh Sharma, Comparison of Estimated overlay based back-calculated modulli by
FWD & Deflection of BBD, Indian Highways, June2016.
[7] Vishal R. Thombare, K V Krishna Rao, Thin White Topping Overlay: Insights from an Experimental Stretch, Indian
Highways, April 2016.
[8] Shiva Prasad K.Manjunath K. R, K. V R Prasad. Study On Marshall Stability Properties Of Bc Mix Used In Road
Construction By Adding Waste Plastic Bottles (2).
IOSR Journal of Mechanical and Civil Engineering (IOSRJMCE)
ISSN: 2278-1684 Volume 2, Issue 2 (Sep.-Oct. Aug 2012), PP 12-23
[9] ByDr. R. Vasudevan tar road with plastics wastes a successful experiment in Mumbai. Management of Plastics,
Polymer Wastes and Bi O -Polymers and Impact of Plastics on the Eco-System Volume 3 • Issue 1 • Jan.–Mar. 2005
ByDr. R. Vasudevan tar road with plastics wastes a successful experiment in Mumbai.