pataudi mpr may

Upload: sumit

Post on 02-Mar-2018

227 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/26/2019 Pataudi Mpr May

    1/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 2 of 26

    Meeting societys Needs Globally

    CONTENTS

    S. No. Description Page No.

    1.0 Project Background 1

    1.1 Description of Project 2

    1.2 Project Area 3

    2.0 ContractsInformation 3

    2.1 Employer 3

    2.2 Contactor 3

    2.3 ContractsDetails 3

    2.4 Engineer/Project Manager 5

    3.0 Progress of Works 6

    3.1 Executive Summary 6

    3.1.1 Status of Physical Implementation 6

    3.1.2 Financial Status 8

    4.0 Physical Progress vs. Scheduled Programme 9

    5.0 Quality Control 21

    5.1 Quality Assurance Plan 215.2 Material Testing and Approval 22

    6.0 Financial Status 22

    7.0 Weather Report 26

    8.0 Environmental, Health And Safety Issues 27

    9.0 Interaction With Stakeholders / Authorities 28

    10.0 Accidents And Incidents 28

    11.0 Matter of Concerns 28

    12.0 Outstanding Correspondence 2913.0 Conclusion 30

  • 7/26/2019 Pataudi Mpr May

    2/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 3 of 26

    Meeting societys Needs Globally

    Figure 1 FARRUKHNAGAR

    1.1INTRODUCTION

    The urban utility and service infrastructure including water, sewerage and solid waste

    has become a prime concern in National Capital Region due to exponential growth ofpopulation in the towns. The National Capital Region Planning Board (NCRPB), a statutory

    body under Ministry of Urban Development, Govt. Of India, is planning to develop NCT of

    Delhi and urban areas under NCR sub-regions of Uttar Pradesh, Haryana and Rajasthan.

    Farrukh Nagar Town (district Gurgaon-Haryana) is part of NCR. The National Capital Region

    Planning Board is arranging by lateral loans to finance the infrastructure projects of NCR Sub

    Regions. NCRPB has received a loan from A D B / Kfw. Part of this loan will be used for

    payments for this work.

    Public Health Engineering Department will be Executing Agency (EA) for the works of

    Augmentation of Water Supply Scheme and Sewerage system for Farrukh Nagarand both

    the contractors shall be selected on the basis of National Competitive Bidding. The Civil

    works will be supervised by the Consultants on behalf of Public Health Engineering

    Department (the Employer) who intends to engage Construction Supervision Consultancy

    Services for the works.

    The project basically comprises construction, operation & maintenance of water supply

    scheme and sewerage system for Farrukh-Nagar. As mentioned in above para. The proposed

    construction work will involve use of modern equipments and construction practice.

    PROJECT TOWN & ITS SALIENT FEATURES

    LOCATION

    Farrukhnagar is a town and municipality inGurgaon

    District in HARYANA state, India. Itis located at

    28.45N 76.82E. It has an average elevation of

    223 meters (731 feet). It is one of the nine

    Administrative blocks of Gurgaon district Situated FARUKHNAGAR

    21 km from Gurgaon. It takes only 30 minutes to

    reach there and shares its border with Jhajjar

    district. Established in 1732 by Farrukhnagar

    Faujdar Khan, the firstNawab ofF a r r u k h n a g a r

    and a governor Of Mughal Emperor (17131719) Farrukhsiyar in 1732, Fa rr uk hn ag ar

    flourished dueto its saltTrade till the late 19th

    century andLater it was Abandoned in early

    20th

    century. Today, Mughal era monuments like Sheesh Mahal, Baoli and Jama Masjid

    built Faujdar Khan are popular visitorsattractions. The town is connected toGarhi Harsaru,

    south of Gurgaon, by railway line. The Sultanpur National Park is situated in Farrukhnagar

    block on Road. The Pataudi Pa l a c e is the nearest palace above 12 Km of the Farrukhnagar.

    In the present Farrukhnagar called as a Shear.

    http://en.wikipedia.org/wiki/Gurgaon_districthttp://en.wikipedia.org/wiki/Gurgaon_districthttp://en.wikipedia.org/wiki/Gurgaon_districthttp://en.wikipedia.org/wiki/Indiahttp://en.wikipedia.org/wiki/Gurgaonhttp://en.wikipedia.org/wiki/Gurgaonhttp://en.wikipedia.org/wiki/Jhajjar_districthttp://en.wikipedia.org/wiki/Nawabhttp://en.wikipedia.org/wiki/Mughal_Emperorhttp://en.wikipedia.org/wiki/Farrukhsiyarhttp://en.wikipedia.org/wiki/Garhi_Harsaruhttp://en.wikipedia.org/wiki/Garhi_Harsaruhttp://en.wikipedia.org/wiki/Sultanpur_National_Parkhttp://en.wikipedia.org/wiki/Pataudi_Palacehttp://en.wikipedia.org/wiki/Pataudi_Palacehttp://en.wikipedia.org/wiki/Sultanpur_National_Parkhttp://en.wikipedia.org/wiki/Sultanpur_National_Parkhttp://en.wikipedia.org/wiki/Garhi_Harsaruhttp://en.wikipedia.org/wiki/Garhi_Harsaruhttp://en.wikipedia.org/wiki/Farrukhsiyarhttp://en.wikipedia.org/wiki/Mughal_Emperorhttp://en.wikipedia.org/wiki/Nawabhttp://en.wikipedia.org/wiki/Jhajjar_districthttp://en.wikipedia.org/wiki/Gurgaonhttp://en.wikipedia.org/wiki/Indiahttp://en.wikipedia.org/wiki/Gurgaon_districthttp://en.wikipedia.org/wiki/Gurgaon_district
  • 7/26/2019 Pataudi Mpr May

    3/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 4 of 26

    Meeting societys Needs Globally

    Farrukhnagar is connected to Gurgaon (16 km.), jhajjar, pataudi & other towns by road.

    Kundli-Manesar-Palwal Expressway (KMP Expressway), whose construction was scheduled to

    be completed by 2012, lies close to the town and will make access to the town easier.

    A branch line was laid in 1901 to Garhi Harsaru station on Rajputana- Malwa Railway

    (Delhi-Ajmer railway), is 12 km away. The meter gauge railway line was used to transport salt

    by steam engines. It was closed in 2004 for gauge conversion. The converted broad gauge

    track became operational in 2011. There has been a demand to extend the track to Jhajjar

    where it will joinRewari-Jhajjar -Rohtak railway line.

    1.2 PROJECT AREA

    The project area under the proposed projects is the area under jurisdiction of

    Farrukhnagar Municipality spread around 34 km2

    .

    The project area comprises of 11 wards having total population of 1.39 lakhs.

    Present Status of Water Supply:

    At present water is supplied through tube wells generally feeding direct in distribution system

    and through 2 Nos existing Zonal Booster pumping stations. Now in this project, it is proposed

    to draw treated fresh water from taking off- take connection from rising main of Mewat

    Water Supply Scheme from Badli up to Nuh Town in Mewat along the proposed KMP

    expressway, which is about 3 KM from Farrukh-Nagar Town. 2 Nosunderground clear water

    reservoirs one for each zone-I &III and distribution network system has been proposed. The

    existing capacity of Underground tank for zone-II is sufficient.

    Present Status of Sewerage

    The Town is not having sewerage system at present. There are individual septic tanks in

    most of the houses whereas some houses discharge the sewage through open drains.

    2.0 Contract Information

    http://en.wikipedia.org/wiki/Gurgaonhttp://en.wikipedia.org/wiki/Kundli-Manesar-Palwal_Expresswayhttp://en.wikipedia.org/wiki/Rajputanahttp://en.wikipedia.org/wiki/Malwahttp://en.wikipedia.org/wiki/Ajmerhttp://en.wikipedia.org/wiki/Rewarihttp://en.wikipedia.org/wiki/Rohtakhttp://en.wikipedia.org/wiki/Rohtakhttp://en.wikipedia.org/wiki/Rewarihttp://en.wikipedia.org/wiki/Ajmerhttp://en.wikipedia.org/wiki/Malwahttp://en.wikipedia.org/wiki/Rajputanahttp://en.wikipedia.org/wiki/Kundli-Manesar-Palwal_Expresswayhttp://en.wikipedia.org/wiki/Gurgaon
  • 7/26/2019 Pataudi Mpr May

    4/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 5 of 26

    Meeting societys Needs Globally

    2.1Employer

    Public Health Engineering Department (PHED), HARYANA

    2.2 Contractor

    THE INDIAN HUME PIPE CO. LTD.(Nuh,Badli and Farrukh Nagar)

    M/s GOYEL PROJECTS PVT LTD ( Pataudi and Haily Mandi town )

    2.3 Contracts Details

    Contract No;

    PHDN/48/2014-15 Dated 12/03/2014

    E.E. PHED No.1, NUH Allotment letter

    No. 2163-68 Dated 03/04/2014

    Contract description;

    Consultant for Providing Construction

    Supervision Consultancy (CSC) Services

    for Works awarded for Farrukh Nagar

    town, Nuh Town, Haily Mandi, Pataudi

    town & Sonipat Town under PHED,

    Haryana with Financial Assistance from ADB/ KfW through National Capital Region Planning

    Board (NCRPB)

  • 7/26/2019 Pataudi Mpr May

    5/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 6 of 26

    Meeting societys Needs Globally

    of task;

    Further the project is divided into Four parts as describe below:-

    Sr.No. Name of work FundingAgency

    Estimated Cost(Rs in Lakhs)

    Name ofDivision

    Contract

    Assi n toA. Augmentation and

    extension of water supply

    for Farrukh Nagar with canal

    water as source

    KfW through

    NCRPB

    628.38 Gurgaon IHP

    B. Providing sewerage scheme

    & sewage treatment plant

    for Farraukh Nagar

    Note:- The tender work in

    progress

    KfW through

    NCRPB

    901.00 Gurgaon

    C Augmentation Water Supply

    Scheme for Nalhar Medical

    College, Nuh Town &

    surrounding

    17 No. villages under PHED,

    Haryana with Financial

    Assistance from ADB

    through National Capital

    Region Planning Board

    ADB through

    NCRPB

    7336.93 Nuh IHP

    D Augmentation and

    extension of water supply

    for Pataudi & Haily Mandi

    town

    ADB through

    NCRPB

    1514.14 Sohna M/s Goyel

    Projects

    E Construction of storm waterdrainage in Sonipat town

    ADB through

    NCRPB

    1982.40 Sonipat

    Project about to complete 95% done.

    Project yet not started.

  • 7/26/2019 Pataudi Mpr May

    6/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 7 of 26

    Meeting societys Needs Globally

    (A) Augmentation and extension of water supply for Farrukh-Nagar

    with canal water as source.

    (i) Rising Main:

    Rising main DI K7 has been proposed from off take point from rising main near KMPexpressway to Boosting Stations zone I, II & III at Farrukh Nagar.

    Pipe Dia in mm 150 200 300 350 Total

    Length in m 150 1221 380 3272 5023

    (ii) Zonal Reservoirs:

    Under Ground Storage Reservoirs (U.G.S.R) has been proposed at 2 places via at zone 1 & 3.

    Capacity and location proposed is given below. For zone-II the existing capacity is sufficient.

    Zone No CapacityProposed ML

    UGSR Reservoir Location LandOwnership

    Zone -1 0.732 UGSR At CHC.(COMMUNITY HEALTH CENTER)

    Government of

    Haryana

    Zone -III 0.683 UGSR At Shamshan Ghat Municipality(PATAUDI)

    Total 1.415

    (iii) Zonal Booster Pumping Stations: (Pumping machinery)

    3 Nos Zonal Booster pumping stations have been proposed for installation, 6 Nos pumping

    machinery, 2 for each (1 will act as stand bye). The details of pumping sets are given below

    PUMPS FOR

    EACH ZONE

    DISCHARGE OF

    EACH PUMP

    NO OF

    PUMPS

    PUMPING

    HEAD IN

    METERS

    KILO WATT OF

    EACH PUMP

    LOCATION OF PUMPING STATIONS

    Zone-1 300 cub. meter 1W +1 S 30 m 55At CHC.

    (COMMUNITY HEALTH CENTER)

    Zone -II 300 cub. meter 1W +1 S 30 m 55 Existing B/S

    Zone -III 300 cub. meter 1W +1 S 30 m 55 At Shamshan ghat.

  • 7/26/2019 Pataudi Mpr May

    7/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 8 of 26

    Meeting societys Needs Globally

    (iv) Strengthening of the Distribution System:

    The existing distribution networks reviewed, rezoned and redesigned. Extension of pipe

    network has been proposed in streets and lanes where pipes are not already laid. Water

    shall be supplied to consumers through 3 Nos. Existing OHSRs (overhead storage reservoirs)

    and 3 NosZonal under Ground level Reservoirs with boosters. Distribution network analysishas been carried out using Water CAD software. About 20.90 km of new pipeline for

    distribution network will be laid, The Diameter of distribution system ranges from 100 300

    mm. About 95 percent of total length of pipelines will be of small diameter (100mm).

    Pipe ID, mm 100 150 200 250 300 Total

    Length, m 24717 1353 284 263 137 26754

    (v) System Metering:

    There is no metering system for water produced at present. In absence of metering of

    production and distribution of water, there is no system of estimating quantity of water

    produced, distributed and lost UN accounted. As such it is proposed to provide 3

    electromagnetic flow meters one in each distribution zone at delivery end of Booster pump

    station.

    (vi) Consumer Metering:

    At present Domestic water connections are on flat rate basis. Under this project it isproposed to have all distribution zones with 100% consumer meters. These all zones will be

    provided water supplies and Non-revenue water will be targeted to be reduced to less than

    15%.

    To improve the water supply system of Farrukh Nagar Town all bulk consumers having

    connection size above 12 mm ( inch) and all commercial and industrial consumers will be

    asked to have functional water meter in their premises as per policy Govt. of Haryana.

    (vii) House Service Line Replacement:

    House service lines being major source of leakages; it is proposed to replace old, worn outand leaking service lines with MDPE pipes in all distribution zones. For this it will be the

    responsibility of the consumer to replace the old and worn pipe line up to the connection

    from main line.

    (viii) Reduction of NRW:

    At present the water meters both on production side and on consumer end are not available.

    As such there is no assessment of UFW or NRW. As such in all of 3 distribution zones intensive

    NRW reduction measures will be taken up under this work. In all zones, it is proposed that all

    consumers will have meters and system meters to assess quantity of water supplied in the

  • 7/26/2019 Pataudi Mpr May

    8/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 9 of 26

    Meeting societys Needs Globally

    zone and quantity of water reached to consumers. Difference in quantity supplied and

    quantity reached to consumer will give extent of NRW. The contractor will Assess regularly

    losses in all the zones and take appropriate measures to reduce NRW to less than 15%.

    (B)Providing sewerage scheme & sewage treatment plant for Farrukh-Nagar.

    This project is meant for providing Sewerage System Network and Sewage Treatment Plant

    for the town. The proposed scheme broadly comprise of Stone Ware and RCC pipe sewerage

    system with appurtenances, Sewage Pumping Station, MBBR (Moving Bed Biofilm Reactor)

    technology based 3 MLD capacity Sewage Treatment Plant, Sludge Thickener, Sludge

    Drying Beds and about 3 km long effluent wastewater channel to forest land.

    (i) Sewage Flow Generation

    It is estimated that by the year 2042 the sewage flow from existing & proposed future

    developments shall be approximately 3 MLD on the basis of present water supply and as such

    the capacity of the proposed MPS & STP has been taken as 3MLD with a peak factor of 2.50

    i.e. peak flow of 7.50 MLD.

    (ii) Main / Trunk and Branch Sewers

    Stone ware (SW) pipes and RCC pipes NP3 class are proposed for sewerage system asgiven below:

    Sewer Dia in mm 200

    SW

    250

    SW

    300

    SW

    350

    SW

    400

    SW

    600

    RCC NP3

    Total

    Length in m 17510 705 265 330 50 70 18930

    (iii) Sewage Pumping Station

    The main sewer will outfall in the Sewage Pumping Station of 3 MLD Capacity through

    screening chamber from where it will be pumped into the inlet chamber of SewageTreatment Plant. The Works of SPS includes all civil, Mechanical, Electrical and

    instrumentation works.

    (iv) Sewage Treatment Plant

    The Sewage from the Sewage Pumping Station will be received into the inlet chamber of 3

    MLD Capacity Sewage Treatment Plant based on Moving Bed Biological Reactor Technology

    (Attached Growth Process) The STP is to be constructed complete in all respect including

    construction of (i) Process units (ii)Boundary wall, Security Guard Room (iii) Staff Quarters,

    approach roads, Main Control Room, Laboratory, Office, Transformer, DG Set (iv) all Electrical,

  • 7/26/2019 Pataudi Mpr May

    9/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 10 of 26

    Meeting societys Needs Globally

    Mechanical, Piping & Instrumentation works (iii) effluent disposal system. The treated

    sewage shall be discharged to distant forest land through sewage channel.

    (v) Site for MPS and STP

    The Site for the proposed MPS & STP is on link road from Farrukh Nagar to forest land inFarrukh Nagar Town. The site is in depression. Site Plan and town plan are given at

    Drawing No. SW-D-20.

    (vi) Raw Sewage Characteristics

    For the design purpose of the proposed MPS & STP following raw wastewaterCharacteristics shall be adopted:

    PARAMETER VALUE

    PH 7-7.5

    TSS 350 mg/L

    BOD5250 mg/L

    COD 500 mg/L

    Oil & Grease 7-8 mg/L

    Total Coliform10^6 -10^7mg/L

  • 7/26/2019 Pataudi Mpr May

    10/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 11 of 26

    Meeting societys Needs Globally

    (vii) Treated Sewage Characteristics

    The treatment plant shall meet following effluent characteristics:

    Treated Sewage characteristics Value

    pH 7 - 8.50

    TSS < 30 mg/l

    BOD < 20 mg/l

    Oil + Grease

  • 7/26/2019 Pataudi Mpr May

    11/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 12 of 26

    Meeting societys Needs Globally

    some places it is rocky. Alluvial thickness varies from almost insignificant to above 185 m, in

    and around Nuh, as revealed by boreholes drilled in this block.

    The climate of the area is tropical, semi-arid and hot. The climate is characterized by the

    dryness in air, a hot summer and a cold winter. Average temperature in of the district ranges

    from 40

    C in January to 70

    C in May and June. Annual average rainfall in the district is 576 mm,with 28 normal rainy days in a year. The annual average rainfall in the district is 594 mm.

    Humidity is high in the south-west monsoon season. April and May are the driest months

    when the relative humidity in the mornings is about 45% and in the afternoons goes less than

    30%.

    Project Area for NUH TOWN

    The project area under the proposed projects is the area covering Nuh city and adjoining 19

    villages and intake on canal, WTP site at Badli and pipe line, intermediate booster site and

    alignment from Intake to service reservoir at Sehsola etc.

    Present Status of Water Supply:

    The water supply system in Nuh & adjoining villages is presently based on ground water i.e.

    through tube-wells. The ground water table is depleting alarmingly at approximately 2.5

    meter per year. The present water table is 30 meters below ground level. The quality of

    water though marginally good at present but the same is deteriorating rapidly. The Tube

    wells are installed outside Nuh i.e near village Palri as the ground water inside the Town is

    brackish.

    The town has been divided into 14 zones for the purpose of water supply and each zone gets

    approximately 1.5 hours of water supply on alternate days @ 40 LPCD. There are 8 number

    tube wells with a discharge of 100 LPM working 8 hours daily and 5 numbers tube wells

    with a discharge of 200 LPM working 5 hours daily. Daily water availability from all the

    tube wells is of the order of 684000 liters. The distribution pipe line size varies from

    80mm to 250mm. The water from all these tube wells is pumped to six number

    underground reservoirs in Nuh town with boosting arrangements from where the water is

    boosted to two number overhead service reservoir of one lac liter capacity each and some

    boosters are directly supplying water to the town. The adjoining villages are also having tube

    wells and water supply system.

    The sub-project will cover the entire population of Nuh town and eighteen adjoining villages.

    Total population to be served in the ultimate stage of the project is of the order of 130720.

    The implementation of the project has following advantages:-

    -To raise water supply status to 135 LPCD in Nuh town and 70 LPCD in villages for the

    prospective population.

    -To eliminate dependence of ground water.

    -Lying of connecting pipe lines and to ensure proper distribution of water.

  • 7/26/2019 Pataudi Mpr May

    12/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 13 of 26

    Meeting societys Needs Globally

    -Installation of meters at strategic locations as well as domestic meters to ensure

    effective management of the water supply system and reduce unaccounted for water (UFW)

    to minimum acceptable limits.

    -Improve infrastructural facilities and help creation of durable public assets and quality

    oriented services in villages & town.

    -To create assured source of water from Gurgaon Water Supply Channel.

    -To implement effective water supply management system.

    The project comprises of raw water intake works, raw water storage for 3 days near theintake, raw water pumping station, the treatment plant, a conventional treatment plant

    involving coagulation-flocculation, rapid sand filtration and chlorination, clear water pumping

    machinery and rising mains, a boosting station at Gurgaon -Pataudi road and ground level

    service reservoirs at Sehsola and distribution mains and supply mains to Nuh town and

    various villages of different sizes as per service zones. Selected critical components e.g.,

    intake works, storage tanks, rising mains, clariflocculator, etc. are designed corresponding

    to the ultimate design period i.e. 2042 while the rest of the components, e.g., Filters, pumping

    machinery, service reservoirs, etc. which can be implemented in a modular approach have

    been designed for the intermediate stage of 2027.

    (i) Intake station from Gurgaon Water Supply channel at Badli

    o Raw water conveyance comprising of canal out let & raw water carrier

    o Sedimentation and settlement tanks3 days capacity for next 15 years

    o Suction well

    o Raw Water Pumping station.

    (ii) Water treatment Plant at Badli

    o Rising Main from raw water pump house to inlet chamber of WTP

    o Inlet Chamber

    o Flash Mixer

    o Clariflocculator Unit

    o

    Rapid Gravity Filter Unit

  • 7/26/2019 Pataudi Mpr May

    13/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 14 of 26

    Meeting societys Needs Globally

    o Clear Water Reservoir

    o Clear Water Pumping Station

    (iii) Rising main from Badli Water treatment Plant to hillock at RD 44600

    The pipe line will encounter the following railways & roadways

    o Railway line crossing----Gurgaon- Farrukhnagar

    o Railway line crossing----Gurgaon- Hailymandi- Rewari

    o National highway number-8

    (iv) Supply Tank on hillock at RD 44600

    o Clear water tank for supply- one day capacity

    o Chlorination unit

    (v) Transmission Main

    From RD 44600 to RD 61100 i.e. Junction for NUH TOWN, 17 Nos. villages & MedicalCollege Nalhar Nuh town

    (vi) Connecting pipe lines

    From transmission main to Nuh town, to villages & to Nalhar medical college.

    (D)Augmentation and extension of water supply for Pataudi & Haily

    Mandi town

    Description of Tasks

    The selected consultancy firm is required to take up Construction Supervision offollowing major project components of the project.

    (i) Rising Main: (Pumping main)

    Pumping main DI K7 has been proposed from offtake point from Rising main near KMPexpressway to Booster Stations for two zones in Pataudi and two zones in Hailymandi.

  • 7/26/2019 Pataudi Mpr May

    14/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 15 of 26

    Meeting societys Needs Globally

    Pipe Dia in mm 300 450 500 600 Total

    Length in m 3300 2600 300 11900 18100

    (ii) Zonal Reservoirs:

    Under Ground Reservoirs has been proposed at two places viz at zone 1, & 2 in Pataudi and at

    two places viz at zone 1, & 2 in Hailymandi. Capacity and location proposed is given below.

    City Zone No Capacity Proposed ML Reservoir Location

    Pataudi Zone -1 1.82 At Shamshan Ghat

    Pataudi Zone -2 1.54 At Moti Dungri

    Hailymandi Zone -1 1.488 Kulana road

    Hailymandi Zone -2 2.1 Railway road

    Total 6.948

    (iii) Zonal Booster Pumping Stations: (Pumping machinery)

    Zonal Booster pumping stations have been proposed 4 nos for each booster station for

    installation of 8 Nos pumping machinery, 2 for each booster pump station (1 working (W)+ 1

    stand bye (S)). The details of pumping sets are given below:-

    LOCATION PUMPS FOREACH ZONE

    DISCHARGEOF EACHPUMP

    NO OFPUMPS

    PUMPINGHEAD INMETERS

    LOCATION OF

    PUMPING

    STATIONS

    Pataudi Zone-1 470 m3/hr. 1W +1S 30 M Shamshan Ghat

    Pataudi Zone -2 470 m3

    /hr. 1W +1S 30 M Moti Dungri

    Hailymandi Zone -1 410 m3

    /hr. 1W +1S 30 M Kulana road

    Hailymandi Zone -2 565 m3

    /hr. 1W +1S 30 M Railway Road

  • 7/26/2019 Pataudi Mpr May

    15/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 16 of 26

    Meeting societys Needs Globally

    (iv) Strengthening of the Distribution System:

    The existing distribution networks reviewed, rezoned and redesigned. Extension of pipe

    network has been proposed in streets and lanes where pipes are not already laid. Water shall

    be supplied to consumers from zonal Under Ground level Reservoirs with boosters.

    Distribution network analysis has been carried out using Water CAD software. About 37 km of

    new pipeline for distribution network will be laid, The Diameter of distribution system ranges

    from (100400) mm. About 82 percent of total length of pipelines will be of small diameter

    (100mm).

    (v) System Metering:

    There is no metering system for water produced at present. In absence of metering of

    production and distribution of water, there is no system of estimating quantity of water

    produced, distributed and lost unaccounted. As such it is proposed to provide 1

    electromagnetic flow meter of 600 dia for offtake from main pumping main on KMP road and

    4 no electromagnetic flow meter of 300 mm dia one in each distribution zone at delivery end

    of Booster pump station.

    (E)Construction of storm water drainage in Sonipat town.

    Description of Sonipat town

    Sonipat is an important town of Haryana & is located north of Delhi at a distance of about 22km from Azadpur & 30 km from ISBT Kashmiri Gate in Delhi.

    Geographically, it is situated at28.9800 N 77.0200 E. It is connected to Delhi though NH1.

    The area of town is 18.25 sq. km. Location of Sonipat is shown in Figure 3-1.

    It traces its mythological history with Mahabharata. It is said that Sonipat is one of theprasthas asked by Yudhistara. It is conceived that the five Pandava brothers established this

    place called as Suvarnaprastha. As per another opinion. Raja Soni the thirteenth descendant

    of Arjuna was responsible for its creation. The first written & documented mention relates its

    history with the great Sanskrit grammarian Panini and his book Asthyadhyayi.

    The population of Sonipat town as per census 2001 was 216,213. The District Sonipat came in

    to existence on December 22, 1972. Till then it was a part of Rohtak district. Sonipat has an

    average literacy rate of 72% higher than the national average of 59.5%.

    DI Pipe K7, (in mm) 100 150 200 250 300 350 400 Total

    Length, m 30347 3878 998 1075 117 20 613 37048

  • 7/26/2019 Pataudi Mpr May

    16/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 17 of 26

    Meeting societys Needs Globally

    Climate

    Climate of District is district is dry with hot summers and cold winters .The weather becomes

    comparatively mild during monsoon period. The district experience high humidity during the

    monsoon. Summer starts early April and peaks in May. Winters are from November to

    February/March .The average temperature ranges from a minimum of 1.8C to a maximumof 44.9C; occasional extremes may in the range of 0.6C to 47C .Predominant winds are

    from north northwest and west, followed by east and southeast .Extreme temperatures

    have ranged from 0.6C (30.9F) to 47C (116.6F).The annual rainfall varies considerably

    from year to Year .The average annual rainfall of the city is about 624mm. Most of the rainfall

    is received during the monsoon season (July- September); this seasons accounts for75percent

    of the annual rainfall .On an average there are24 rainy days in a tear with rainfall of 25mm (or

    more) per days in the town.

    2.4 Engineer / Project Manager

    WAPCOS LIMITED

    Contract Nr;

    MEMO no, 6472 DT 05-06-15

    Contract description;

    Construction Supervision (CSC) services for works awarded for Farrukhnagar town, Nuh

    town Haily Mandi, Pataudi town & Sonipat town under PHED, Haryana with financial

    Assistance from ADB/Kfw through National Capita Region Planning Board (NCRPB).

    Scope of Works;

    The overall scope of Consultancy is to carry out the two phases described below:

    1.Check and Approval of Proposed Design Changes by the Contractor - Covers checking and

    approval of the Contractors proposed changes to the detailed design provided by the original

    Design and Supervision Consultant.

    2. Construction Supervision - Covers construction supervision of all works for the proposedinterventions, including attendance during the Defects Liability Period.

    Contract Price

    Rs. 210.00 Lakhs /-

    Commencement Date

    LOI DT: 12/03/2014

    Orig inal Contract Period 24 Months

  • 7/26/2019 Pataudi Mpr May

    17/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 18 of 26

    Meeting societys Needs Globally

    MONTHLY PROGRESS DETAILS FOR THE PROJECT C UNDER PHED DEPPT: CODED(WS01)

    3.0 Progress of Works

    3.1 Executive Summary

    3.1.1 Status of physical implementation

    1st

    MAY to 31st

    MAY PIPELINE LAID

    PIPE DIAMETER HAILY

    MANDI

    PATAUDI INSTALLED

    QUANTITY

    QUANTITY TOTAL

    (B.O.Q.)

    BALANCE PIPE

    100K7 16563.90 3396.65 29960.55 30347 381.45

    150K7 2298.60 1091.90 3390.50 3872 481.50

    200K7 963.95 18.80 982.75 998 15.25

    300K7 1074.80 .400 1075.20 1075 -

    250K7 101.15 11.58 112.73 117 4.27

    400K7 40.40 546.80 587.20 613 25.8

    350K7 20.00 - 20.00 20 -

    450K9 2540.95 - 40.95 260 55.05

    500K9 297.00 - 297.00 297 -

    600K9 - 11588.70 11588.7 11898.50 309.5

    300K9 1666.40 1537.75 - 3297 92.85

    SITE

    (BOOSTING

    STATION)

    CLEAR WATER

    TANK (%)

    STAFF QUARTER

    (%)

    PUMP HOUSE

    (%)

    OTHER

    MISCELLANEOUSWORKS (BOUNDARY,

    WALL ROAD, PIPE LINE)

    (%)

    PATAUDI zone-1 95 70 70 95

    PATAUDI zone-2 95 - 70 -

    HAILY MANDI

    ZONE-1

    95 70 70 95

    HAILY MANDI

    ZONE-1

    95 70 70 95

  • 7/26/2019 Pataudi Mpr May

    18/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 19 of 26

    Meeting societys Needs Globally

    3.1.2 Financial status:

    Ref. Description Contract Lump

    sum Amount

    %Work

    Done

    Released From the

    Department

    Gross Work Done

    %

    Lakhs

    1

    Augmentation Of Water

    Supply Scheme For

    Pataudi & Haily-Mandi

    Towns

    2949.03512 78.27 % 2308.44088 95 %

    4.0 Physical Progress Compared with Submitted Program me

    By the date of 31st

    MARCH 2016, 407 calendar days has elapsed since the project official

    started. Up to now the overall progress is % as against % of the scheduled program.

    Sr.no DESCRIPITION COMPLETION %

    AUGMENTATION AND EXTENSION OF WATER

    SUPPLY FOR PATAUDI & HAILY MANDI TOWN

    1. SHAMSHAN GHAT PATAUDI ZONE 1 92

    2. MOTI DUNGRI 923. KULANA 98

    4. RAILWAY ROAD HAILY MANDI 97

  • 7/26/2019 Pataudi Mpr May

    19/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 20 of 26

    Meeting societys Needs Globally

    5.0 Quality Control

    5.1 Quality Assurance Plan

    In order to guarantee the quality of the Works, the following measures are being followed.

    Contractor is not submitting the form of REQUEST FOR APPROVAL to Engineer indicating

    the working areas and details of the works to be carried out the next day. So, that the

    inspection is being done on a daily basis by Engineer.

    Every week, the technical meeting is being held by Engineer to assess the progress and

    quality of works and other issues on site.

    St r i ct procedures of quality-check and acceptance are followed according to the

    Specifications to ensure that it complies with the requirement of the Specifications.

    6.2 Material Testing and Approval

    All the pipes, fittings and accessories have been purchased from Electrosteel Pipe Co.

    LTD. received with the QUALITY CERTIFICATE FOR DUCTILE IRON PIPES which was approved

    by M/S Rites Limited. Applicable tests and checks have been performed by the Manufacturer

    and confirmed.

    Concrete Cubes are collected during all concreting works as per the specifications and

    are NOT tested in the laboratory for compressive strength. The details of the test are

    recorded last year and are certified if the same are confirming to specifications. The details of

    the concrete used for different structures, the number cube samples collected and tested are

    presented in the format attached as Annxeure-1

    For pipeline works regular inspections are being carried out checking for provision of proper

    bedding, compaction and jointing. The completed pipeline is not tested for hydrostatic

    pressure equivalent to 1.5 times the static pressure at that location. Instead of recommended

    from WAPCOS officials present on site.

    9.0 Health and Safety Issues

    None were taken till date.

  • 7/26/2019 Pataudi Mpr May

    20/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 21 of 26

    Meeting societys Needs Globally

    10.0 Interaction with Stakeholders / Authorities

    During the construction time to time interaction is going on with PHED representatives

    and local people for their cooperation.

    11.0 Accidents and Incidents

    No accidents were noted till date.

    12.0 Matter of Concerns

    Regularly informing regarding quality documents (RFA, POUR CARDS, and TEST REPORTS)

    through letters and on meetings, but none of them were submitted till date.

    Hindrance Details for the Projects

    Near Babra Bakipur gas pipeline crossing.

    Near Pataudi Chawk cc road crossing.

    Railway line crossing near flyover.

    Near Rewari road, road crossing for 300mm pipeline.

    Hailymandi road near Mini Secretariat.

    Near shri ram chawk Hailymandi road crossing for 400mm pipeline with trench less

    method.

    Moti Dhungri road Nauhta Chawk Pataudi for 100mm pipeline.

    NOTEAll these are pending due to which work is suffering of reaching its finishing stage.

  • 7/26/2019 Pataudi Mpr May

    21/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 22 of 26

    Meeting societys Needs Globally

    13.0 Outstanding Correspondence

    The monthly correspondence details are given below:

    14.0 Conclusion

    Summarizing the information given above, the contractor has completed 95 % of

    overall progress of the project till 31st

    MAY2016.

    S .No. Letters No. Subject Date

    Incoming Correspondence

    PHED to WAPCOS

    1. - - -

    S .No. Letters No. Subject Date

    Outgoing Correspondence

    WAPCOS to PHED

    1. - - -

  • 7/26/2019 Pataudi Mpr May

    22/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 23 of 26

    Meeting societys Needs Globally

    SITE-PHOTOGRAPHS

    IMAGE 1-STAFF QUARTER (PATAUDI ZONE-1) IMAGE 2- PUMP HOUSE (PATAUDI ZONE-1)

    IMAGE 3- MAIN GATE INSTALLED AT PATAUDI ZONE. IMAGE 4-EXCAVATION FOR LAYING OF CC ROAD AT HAILY MANDI.

  • 7/26/2019 Pataudi Mpr May

    23/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 24 of 26

    Meeting societys Needs Globally

    IMAGE 5 - RAILING INSTALLED AT CWT STAIRS. IMAGE 6- STAFF QUARTER AT HAILY MANDI ZONE-2

    (HAILY MANDI BOOSTING STATION)

    IMAGE 7STAFF QUARTER AND PUMP HOUSE IMAGE 8PUMP HOUSE AT KULANA BOOSTING STATION.

    (AT RAILWAY ROAD BOOSTING STATION)

  • 7/26/2019 Pataudi Mpr May

    24/24

    PUBLIC HEALTH ENGINEERING DEPARTMENT (PHED)

    MonthlyProgress ReportMAY. 2016

    Page 25 of 26

    IMAGE 9PUMP INSTALLED AT BOOSTING STATION IMAGE 10MAIN GATE INSTALLED (MS PIPE)

    (PATAUDI ZONE 1 BOOSTING STATION) (AT SHIV MURTI BOOSTING STATION PATAUDI ZONE 2)