Parklands Albury Wodonga Ltd The Murray Parkways Corryong to Wodonga to Wahgunyah Implementation Plan for Kiewa River 2012 to 2015 Enhancing the river environment Improving community access Connecting Indigenous communities to country through co-management Parklands Albury Wodonga Limited P.O. Box 1040 Wodonga VIC 3689 Phone: 02 6023 6714 Fax: 02 6023 2425 Email: [email protected] Date: 27 th July 2012 Updated: 15 th October 2013

Upload: others

Post on 24-Nov-2020

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

Parklands Albury Wodonga Ltd

The Murray Parkways Corryong to Wodonga to Wahgunyah

Implementation Plan for

Kiewa River 2012 to 2015

Enhancing the river environment Improving community access

Connecting Indigenous communities to country through co-management

Parklands Albury Wodonga Limited

P.O. Box 1040

Wodonga VIC 3689

Phone: 02 6023 6714

Fax: 02 6023 2425

Email: [email protected]

Date: 27th

July 2012

Updated: 15th

October 2013

Page 2: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

1

CONTENTS

Overview of Strategic Plan 2010 to 2022 ............................................................................................................ 2

Creating the Murray to Mountains Regional Experience .................................................................................. 3 Map 1a – Regional Experience ..................................................................................................................... 3

Summary of Action Plan 2010 to 2022 ................................................................................................................ 4

Ongoing Consultation ........................................................................................................................................... 4

Map of Action Plan Area 2012 to 2015 ............................................................................................................... 5

Summary of Resource Requirements ................................................................................................................. 6

Specific Kiewa Water Frontages - 2012 to 2015 ................................................................................................. 7

1. Lower Kiewa (Murray River to Boyes Road) ........................................................................................... 7 Map 1.1 - Lower Kiewa (Murray River to Boyes Road) .............................................................................. 7 Map 1.2 - Killara section of Kiewa River ..................................................................................................... 8 Map 1.3 - Three Options for Murray Walking Track footbridge .................................................................. 9 Map 1.4 Overview of eastern section of Murray Walking Track .................................................................. 9

2. Middle Kiewa (Boyes Road to Yackandandah Creek) ............................................................................ 10 Map 2.1 Boyes Rd to Yackandandah Ck .................................................................................................... 10 Map 2.2 Pollards Road and Chappels Road (closed road reserves) ............................................................ 11 Map 2.3 Overview of closed road reserves ................................................................................................. 11

3. Upper Kiewa (Yackandandah Ck to Tangambalanga) ........................................................................... 12 Map 3.1 Yackandandah Creek Junction to Kiewa Tangambalanga ............................................................ 12 Map 3.2 Jenkins Road (closed) and Riverside Reserve .............................................................................. 13 Map 3.3 Kiewa Waterside Reserve ............................................................................................................. 13

4. Lower Yackandandah Creek .................................................................................................................. 14 Map 4.1 Kiewa Valley Highway upstream to Lindsay Lane ...................................................................... 14 Map 4.2 Kiewa Valley Highway section .................................................................................................... 15 Map 4.3 Boundary Road section ................................................................................................................. 15 Map 4.4 Yackandandah Creek Junction section ......................................................................................... 16

Progress to date – October 2013 ........................................................................................................................ 17

Downstream of Killara .................................................................................................................................... 17

Upstream of Killara (Murray Valley Highway) ............................................................................................... 18

Downstream of Kiewa / Tangambalanga townships ........................................................................................ 19

Page 3: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

2

Overview of Strategic Plan 2010 to 2022

This Action Plan is part of Parklands Albury Wodonga’s 2010 to 2022 Strategic Planning Process;

Strategic Plan (2010 to 2022): identifies the focus for Parklands Albury Wodonga and the modus

operandi: a partnership culture in the planning and implementation.

Strategic Plan – Schedule of Works (2010 to 2022): identifies the key works proposed that are

unique to specific sites. Whilst not stated in these works schedules, consistent and continued pest

plant and animal control and fire management strategies will be required to be undertaken for the

length of this strategic plan.

Action Plan (2012 to 2015): prioritises works identified in the Schedule of Works and provides

detailed maps and costings for the initial stages.

Priorities are based on the following principles;

Strong community support and demand

Active community stewardship

Initially focus on establishing continuous links

Ease of implementation, that is, sites where minimal capital infrastructure, such as

footbridges are required

Page 4: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

3

Creating the Murray to Mountains Regional Experience Parklands Albury Wodonga is committed to a “partnership culture” where partnerships are integral

to how work gets accomplished and how connections are made. For instance;

In 2011/12, Parklands Albury Wodonga worked in partnership with 82 organisations and

agencies as well as volunteers, in the joint planning and implementation of park projects.

Over $12.8 million work of volunteer hours has been invested in the development of the

regional parklands over the past 15 years.

The process of building community stewardship and involving local communities in the building of

this regional trail is critical to the longer term success and sustainability.

Map 1a – Regional Experience

Examples of successful community stewardship models;

Bibbulman Track, WA (1,000km) 271 volunteers maintain, managed by CALM (WA) &

Bibbulman Foundation

Appalachian Track, USA (3,500 km) 31 volunteer groups maintain, managed by National Park

Service, USDA Forest Service, state agencies, Appalachian Trail Conservancy and 31 local Trail-

maintaining clubs.

Bruce Track, Canada (800km) 9 Trail Conservancy Clubs, Bruce Trail Conservancy and volunteers

(Bruce Trail Clubs, 1,000 volunteers & 8,500 members) maintain, steward and promote the Trail.

Hume & Hovell Track, Wagga (400km) managed by NSW Government

Regional Parklands (98km so far… ) 11 Friends Groups & others, managed with Friends Groups

and supported by various volunteer programs

Page 5: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

4

Summary of Action Plan 2010 to 2022

Precinct B – Kiewa River frontages

Community Involvement

Establish Tangambalanga Friends Group (Kiewa River Reserve Action Group or KRRAG) through involvement with recreational fishing track project. Support Murray Bushwalking Club with Kiewa Track maintenance program and broaden involvement to include other groups and partners. Support Baranduda Landcare Group with lower Yackandandah Creek restoration works. Build ownership through corporate volunteering (eg Murray Goulburn) and involving local groups and schools (eg Kiewa Valley Primary School).

Recreational facilities

Maintain recreational fishing track . Footbridge to link crown land area near Yackandandah Creek junction. Support KRRAG to establish vehicular access waterside reserve at Kiewa township and in negotiating vehicle access reserve at Tangambalanga. Work with North East Anglers, City of Wodonga and Licensees to improve fishing access by part opening closed road reserves (Ryans Rd, Pollards Rd & potentially, in the longer term, Chapples Rd)

Biodiversity measures

Stage riparian fencing and revegetation with interest from Friends Groups, given the importance of fostering community stewardship and the high levels of maintenance required for the initial years.

Fire Prevention Biannual spray and slash of access track along corridor. Crash graze each spring (except for the 4 years after revegetating)

Ongoing Consultation

There has been considerable consultation with project partners and stakeholders over the past two years, during the development of Parklands Albury Wodonga’s Strategic Plan 2010 to 2022.

However, this consultation is ongoing. This Implementation Plan is a “working document” which means Parklands Albury Wodonga welcomes input, suggestions and any recommendations for changes. Help us build outcomes that benefit all stakeholders by getting in touch;

Mail: P O Box 1040, Wodonga VIC 3689

Email: [email protected]

Telephone: 02 6023 6714

Fax: 02 6023 2425

Page 6: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

5

Map of Action Plan Area 2012 to 2015

Map 1b – Map of Precincts

Section 1

Section 2

Section 3

Kie

wa

Riv

er

Yackandandah Creek

Fin

ns

Cre

ek

Section 4

Page 7: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

6

Summary of Resource Requirements

Bare earth track Chicane gates to facilitate stock watering points

Bollards to manage vehicles Managing for both agriculture and passive recreation outcomes

STAGE ISSUES UNDERWAY FUNDS SOUGHT

1.1 Grader hire

1.2 Blackberries, fencing & plants 3 year grant

1.3 Rocks and timber sleepers for erosion control $10,000

1.4 Removal of large Poplars, mulching & plants (revegetate site) $30,000

1.5 Fence & revegetate closed Ryans Road reserve 3 year grant

2.1 Negotiate access time

2.2 Negotiate access time

2.3 Grader, culverts and bollards to open Pollards Road $20,000

3.1 Blackberries, fencing & plants 4 year grant

3.2 Jenkins Road (culverts & fence materials) tba

3.3 Security fence (70 metres) $2,100

3.4 Riverside reserve (bollards, fence materials & plants) $8,000

3.5 Riverside reserve (bollards, fence materials & plants) $8,000

4.1 Blackberries and plants 4 year grant

4.2 Cultural Heritage Management Plan $20,000

4.3 Fence & revegetate lower Yackandandah Creek $25,000

estimated budget $123,100

STAGE ISSUES UNDERWAY FUNDS SOUGHT

1.6 Bridge contractor (footbridge at 1 of 3 Murray River locations) $80,000

2.4 Bridge contractor (footbridge near Yackandandah Creek) $80,000

estimated footbridge budget $160,000

# Budget for footbridges based on $2,000 per linear metre for 2 metre wide footbridge decking

Page 8: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

7

Specific Kiewa Water Frontages - 2012 to 2015

1. Lower Kiewa (Murray River to Boyes Road)

Map 1.1 - Lower Kiewa (Murray River to Boyes Road)

PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER

1.1 Short term Access track Grader to change slope of 200m City of Wodonga

1.2 Short term Blackberries & 2km fences

Dozer & chemicals Fence materials & labour

Communities for Nature (DSE)

1.3 Short term Killara carpark Rocks and timber sleepers NECMA & Sponsor

1.4 Short term Killara poplars Excavator operator, plants and materials for bollards & seats

Sponsor / grant for $30,000

1.5 Medium term

Ryans closed road reserve

Time to secure COW permission Fence materials & plants

City of Wodonga Communities for Nature (DSE)

1.6 Medium term

Footbridge over Kiewa River

Bridge contractor (part of Wodonga to Wahgunyah Murray Walking Track)

Sponsor / grant for $80,000

Bonegilla Migrant

Experience Heritage Park

1.6 Potential

vehicle access along

closed road reserve

(Ryans Rd)

1.5 Footbridge over

Kiewa River for

Murray Track

(three options)

Bare earth

Murray

River track

High Country Rail Trail

Murray Valley Hwy 1.3 Rocks &

Sleepers to

tackle

erosion at

Killara picnic

area

Bare earth Kiewa

Track (8km)

established

1.4 Remove

poplars,

revegetate

and establish

picnic area Board walk across floodplain on

High Country Rail Trail

Pol

lar

ds

Ro

ad

Mahers

Road

Hig

h

Cou

ntr

y

Rail

Trai

l Mahers Hill

1.2 Tackle

blackberries

& fence east

bank

1.1 Upgrade

maintenance

access track

trackillara

picnic area

Kiewa track established

(Fisheries Vic)

Boyes Road

Page 9: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

8

Map 1.2 - Killara section of Kiewa River

1.3 Rocks & Sleepers

to tackle erosion at

Killara picnic area

1.4 Remove

poplars, revegetate

and establish picnic

area

1.2 Tackle

blackberries

& fence east

bank

Murray Valley Hwy

Kie

wa

Riv

er

Page 10: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

9

Map 1.3 - Three Options for Murray Walking Track footbridge

Map 1.4 Overview of eastern section of Murray Walking Track

A

B

C

A

B

C

Murray River

Murray Valley Hwy

Kiewa River

Ryans Road (closed)

Huon Hill Parklands

Killara Kenneth Watson Drive

Snowdons Road

Murray Valley Hwy

Rapsey Road

Ryans Creek

Ryans Road

Ryans Lagoon

Wetlands

Killara

Bonegilla Migrant

Experience Heritage Park

Murray River

Lake

Hume

Kookaburra

Point

Murray River

Page 11: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

10

2. Middle Kiewa (Boyes Road to Yackandandah Creek)

Map 2.1 Boyes Rd to Yackandandah Ck

PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER

2.2 Short term

Walking track along Pollards closed road reserves

Time to negotiate & fence materials & plants (if required) Stepping stones over Finns Ck

Crown road reserve licensee City of Wodonga Sponsor (fence materials)

2.1 Medium term

Walking track along Chappels closed road reserve

Time to negotiate Fence materials & plants (if required)

Crown road reserve licensee City of Wodonga

2.3 Medium term

Vehicle access along Pollards Rd

Grader, culverts & bollards Fence materials & plants (maybe)

City of Wodonga Fisheries Victoria

2.4 Medium term

Footbridge over Kiewa River

Bridge contractor est. $80,000 (continuous track from Murray River to Tangambalanga and possibly to Yackandandah)

Sponsor / Grant Gardiner Foundation

2.3

Vehicular

access to

river along

Pollards Rd

2.1 Vehicular

or pedestrian

access along

Chappells Rd

2.2 Negotiate

use of crown

road reserves for

Kiewa Track

Boundary Rd (closed)

Kiewa Track

along eastern

bank (Fisheries

Vic project)

2.4 Footbridge over Kiewa River

for Kiewa Track and links to

proposed Yackandandah Track

Kie

wa

Val

ley

H

wy

Mahers Rd

Boundary Rd Wo

don

ga

Yac

kan

dan

dah

Rd

Pol

lar

ds

Rd

(cl

os

ed)

Chappels Rd

(closed) Chappels Rd

W

hy

te

s

Rd

Yackandandah Ck

Ki

ew

a

Riv

er

Fin

ns

Ck

Hig

h

Co

unt

ry

Rai

l

Tra

il

Mahers Hill

Page 12: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

11

Map 2.2 Pollards Road and Chappels Road (closed road reserves)

Map 2.3 Overview of closed road reserves

Chappels Rd

open

W

hy

tes

Rd closed road

reserve

Kie

wa

Riv

er M

ah

ers

Rd

Po

lla

rds

Rd

(cl

os

ed

)

closed road reserve

Chappels Rd

closed

Fin

ns

Cr

ee

k

Page 13: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

12

3. Upper Kiewa (Yackandandah Ck to Tangambalanga)

Map 3.1 Yackandandah Creek Junction to Kiewa Tangambalanga

PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER

3.1 Short term

Yackandandah Ck restoration

Chemicals, plants Fencing materials (stage 2)

Baranduda Landcare Group Communities for Nature (DSE)

3.2 Short term

Jenkins Road vehicle access

Time to negotiate Grader, culverts, cattle grid & fence materials

KRRAG Indigo Shire Council Fisheries Victoria & sponsors

3.3 Short term

Kiewa East Rd pedestrian access

Permission from NECMA Security fence materials & labour

KRRAG North East CMA Sponsors

3.4 Short term

Vehicle access riverside reserve

Bollards, fence materials & labour KRRAG Sponsors

2.4 Medium term

Kiewa River footbridge

Bridge contractor est $80,000 Gardiner Foundation Sponsors / grant

3.5 Medium term

Vehicle access riverside reserve

Time to negotiate Grader, culverts & fence material

Developer, Indigo Shire Sponsor

Mahers Rd

Kie

wa

Huo

n

Rd Kie

wa

Val

ley

Hw

y

Jenkins Rd

(closed)

Tangambalanga

Township

Kiewa Track

(western bank

of Kiewa River)

2.4 Kiewa

footbridge

3.1 Restoration

of Yackandandah

Creek

3.2 Vehicle

access via

Jenkins Rd

3.3 Pedestrian

access to

Kiewa East Rd

3.4 Vehicle

access riverside

reserve

M

urr

ay

Val

ley

H

wy

High Country Rail Trail

Kiewa East Rd

Ya

ck

an

da

nd

ah

Cr

ee

k

Kiewa River

3.5 Vehicle

access riverside

reserve

Kiewa Track

(eastern bank

of Kiewa River)

Page 14: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

13

Map 3.2 Jenkins Road (closed) and Riverside Reserve

Map 3.3 Kiewa Waterside Reserve

Kiewa River Reserve Action Group (KRRAG) plans for Crown land near Kiewa township

Jenkins Rd (closed)

Kie

wa

Riv

er

Kiewa East Rd

proposed

waterside

reserve

Public access (vehicle or

pedestrian) to be negotiated

Page 15: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

14

4. Lower Yackandandah Creek

Map 4.1 Kiewa Valley Highway upstream to Lindsay Lane

PRIORITY ACTION RESOURCES PARTNER / STAKEHOLDER

4.1 Short term Restore Creek Chemicals Plants

Baranduda Landcare Group Communities for Nature (DSE)

4.2 Medium term Cultural Heritage Management Plan

Archaeologists Traditional Owner Group(s)

Wodonga Aboriginal Network

4.2 Medium term Walking track Chemicals & chicane gates Sponsor

4.3 Medium term Restore creek Fence materials and plants Sponsor / Grant

W

od

on

ga

Ya

ck

an

da

nd

ah

Rd

Yackandandah Creek

4.2 Potential walking

track on northern bank

when blackberries

controlled

4.1 Significant

infestation of

Blackberry and

Box Elder

Blackberries

Kiewa Valley Hwy

Page 16: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

15

Map 4.2 Kiewa Valley Highway section

Map 4.3 Boundary Road section

Page 17: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

16

Map 4.4 Yackandandah Creek Junction section

Chicane gates to

facilitate walking

4.3 Fence and

revegetate

2.4 Footbridge

over Kiewa River

Page 18: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

17

Progress to date – October 2013

Downstream of Killara

Page 19: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

18

Upstream of Killara (Murray Valley Highway)

Page 20: Parklands Albury Wodonga Ltd The Murray Parkways Corryong ...€¦ · getting in touch; Mail: P O Box 1040, Wodonga VIC 3689 Email: info@parklands-alburywodonga.org.au Telephone:

19

Downstream of Kiewa / Tangambalanga townships