parca - earned value management practitioners' (evmp) forum · office of performance...
TRANSCRIPT
1APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
PARCA
DoD EVM Policy Initiatives
Mr. John McGregor
PARCA Deputy Director for EVM
EVM Practitioners Symposium August 2017
2APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
� PARCA
� IPMR2 EVM Reporting Future
� EVM Application & the Updated DoDI 5000.02
� Policy & Guidance Status
� EVM-CR
3APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
PARCA was brought into existence via the reforms in the
Weapon Systems Acquisition Reform Act (WSARA) of 2009
Director, Performance Assessments and Root Cause Analyses
(PARCA)
Mr. Gary R. Bliss
Mr. John McGregor
Deputy Director for
Earned Value
Management
Mr. Dave Cadman
Deputy Director for
Root Cause Analyses
Dr. Peter Eggan
Deputy Director for
Performance
Assessments
Dr. Danny Davis
Deputy Director for
Acquisition Policy
Analysis Center
4APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
EVM, as a management discipline for making decisions, depends on governing
the entire EVM value stream from Contractor to Government analyst
“To be successful, EVM practices and competencies must be integrated into the program
manager’s acquisition planning and execution processes”
- PARCA Authorities Memo, Aug 2011
EVM Policy and
Guidance
•Develop, publish, and maintain DoD policy and guidance on Earned Value Management application and reporting
Communications
and Outreach
•Inform Government and Industry stakeholders on EVM policy, reporting, and competency matters
Program Interface
•Determine EVM applicability; Assist programs with EVM use and reporting; Resolve interpretive differences in EVM policy
EVM Central
Repository (CR)
•Manage the EVM-CR as the authoritative EVM data source for ACAT 1 programs; Maintain data governance for EVM data
EVM Functional
Leadership
•Serve as DoD EVM Funct. Lead; Develop and maintain competency model; Guide training, education, and skills for the workforce
5APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
Working to facilitate the effectiveness of EVM for joint
situational awareness and program decision making
PARCA works
across DoD
Services/Agencies,
Federal Agencies,
and Industry
6APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
Status and future of the IPMR update initiative
7APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
� Reduce duplication of data in the IPMR Formats
� Update data transfer mechanism (i.e., XML to JSON)
� Improve traceability between cost and schedule data
� Support DCMA needs as part of automated surveillance activities
Notional data tables
8APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
Proposed restructuring of IPMR formats
• Eliminate Format 1-4; transition to reporting single data packages for IPMR Cost, Schedule, and Variance Analysis
Single EVM Cost Data format removes duplicate reporting
• By receiving control account level data, can remove Format 1-4 reporting requirement
Data reporting based on requirements defined in EVMSIG
• Cost data at the work package level can be rolled into control accounts and used to derive WBS (Format 1) and OBS (Format 2) data
• Enables utilization of IPMR for automated surveillance needs for DCMA
Streamlined Data Exchange Standard improves efficiency and
reduces errors
9APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
Data Standards Concept: Zipped collection of simple JSON files that
encode IPMR cost and schedule data tables
• Initially focused on cost performance data (IPMR 1-4 and 7); expanded to encompass schedule performance data (IPMR 6)
� Utilization of similar approach to data encoding has potential to improve efficiency and reduce data encoding errors
� Simplifying and reducing requirement for non-native data that is not inherently contained in the underlying EVM system/tool
� Exploring potential options to improve existing processes and better align for cost/schedule integration
• Exchange definition captured as a File Format Specification and Data Exchange Instructions documents
10APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
Cost Performance Dataset & Schedule Dataset Standards
• Completed draft file format specifications and DEI in March• Held introductory overview with EVM software vendors on March 31st • Held technical discussion forum with EVM vendors on April 7th • Government review of Industry and vendor feedback through June• Finalized specifications and draft DEI
Policy
• IPMR2 DID development in process, to be consistent with File Specifications • Release date targeted for February 2018
System Development
• Development of Cost Performance and Schedule sample files for August availability• Design and build desktop tools for file test and verification for August availability• Plan to complete EVM-CR integration capabilities by January 2018 prior to DID
Future Extension Considerations
• Custom data tags, WBS Dictionary, link to IMP, improved Variance Analysis Reporting
11APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB
Finalize Initial draft Standard & DEI (Cost)
Release to Industry & Vendors for Review (Cost)
Industry Review/Comment
Gov. Adjudication & Update (Cost)
Final Draft Standard & DEI (Cost)
Form Working Group (Schedule)
Initial Draft Standard & DEI (Schedule)
Release to Industry & Vendors for Review (Sched)
Industry Review/Comment
Gov. Adjudication & Update
Final Draft Standards & DEI
DID & Impl. Guide Dev.
DID Review & Release
Sample Files (Cost)
Sample Files (Schedule)
Test Tools & Utilities
EVM-CR Data Integration Design
EVM-CR IPMR2 Dev.
2017 2018
TASK
Cost Performance Standards
ScheduleStandards
Policy
System Development
12APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
Applying EVM per the new DoD Instruction 5000.02
13APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
� Table 8: EVM Application Requirements (reflects $100M
EVMS threshold)
� Table 9: EVM Reporting (maintains $50M reporting
tailoring threshold)
DFARS update to reflect polices in new DoDI 5000.02 is in
the rule making process
�
14APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
• Contract is Cost Plus or Incentive
• Contract > $20M (including known options)
• Contract has at least 18 months period of performance
Step 1. Contract Criteria Review
If all Yes
If any NoEVM Not Applicable*
EVM placed on contract; option to have
applicability determination based on nature of work (Step 2)
• Does EVM apply based on review of SOW, PWS, WBS, & CDRLs (i.e., work discretely measurable & schedulable)
¾ PARCA & Services - ACAT ID & IAM for DAE/MDA decision
¾ Services - other ACATs for SAE/CAE decision
Step 2 (Optional). Work Attributes Review
Yes
No
EVM does not apply* EVM not on contract; no
deviation/waiver required
EVM does apply EVM is placed on contract; PMO
has option to seek waiver/deviation
* The PM has the option to make a business case to apply EVM outside the thresholds and application decision
2 Step EVM Application Process
15APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
� EVM-CR: “For ACAT I contracts…IPMR data will be delivered to the EVM Central Repository”
� OTB/OTS: “The initiation of an over-target baseline or over-target schedule must be approved by the Government program manager”
� IDIQ: 2 part application on IDIQ contracts:
1. Include EVM requirement on total base IDIQ contract if it meets or is expected the EVM thresholds in 5000.02
2. Apply EVM on task/delivery orders, or group(s) of related task/delivery orders, per thresholds and workscope
16APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
Status of current and ongoing EVM policies in DoD
17APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
� PARCA met with Govt compliance constituents to adjudicate comments
� Plan to release Fall 2017
� Updated draft document released and PARCA received 152 Industry comments and an additional 34 Govtcomments
� PARCA met with NDIA Board to discuss Industry comments
18APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
� Updated: Aircraft Systems (combined with Unmanned Aircraft), Electronic Systems, Missile Systems (combined with Ordnance Systems), ICBM (new appendix), Space Systems, Surface Vehicle Systems, AIS Systems, Common WBS Elements� No Update: Sea Systems, Unmanned Maritime Systems
� Other information• Cybersecurity and Sustainment to be reflected in all appendices• Lower level WBS can be developed; link to cost estimating model
templates to be provided as examples• Handling of items such as Warranty and Rate Tooling adjudicated
� Document out for review August 2017
19APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
� PARCA has updated the document based on comments fromIndustry and Government; document going through review
� Navy document completed; purpose of DoD document is to house DoD EVM guidance and interpretation in a singular place
� PARCA working on update to guide to cover IBR and further explain relationship of metrics
� PARCA is interested in having Industry and Government participate in review of the update
20APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
� Update of OMB Capital Programming Guide provides link between EVM and Agile:
“EVM is not tied to any specific development methodology and does
not prevent the use of other risk management techniques such as
agile development. EVM and agile development are complementary
and can be used on the same project. Agile development can be used
to incrementally deliver functionality to the customer while EVM
provides a standard method for measuring progress.”
21APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
22APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
Discussion of the EVM Central Repository
23APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
�Public Website http://cade.osd.mil/
� CADE Users
� Policy & Guidance (Sample CDRLs & DIDs, link to PARCA Policy)
�EVM-CR My Contracts
� Quick access to contracts you have permission to view
� Industry Reviewer Role
� Access for Industry Corporate focal points to reporting compliance and data quality reports as well as submissions delivered by their Data Managers
Separate Session Next:
DOD EVM - Central Repository and Industry Reviewer Roles Training
24APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
PARCA EVM Website:
http://www.acq.osd.mil/evm/
PARCA EVM Email:
PARCA Acquisition Exchange Program (AEP) provides a unique career-development
experience for high-caliber Government civilians or military personnel interested in
acquisition and/or EVM.
http://www.acq.osd.mil/evm/aep.program.html
25APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
Just in Case
26APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
EVM is applied to cost reimbursable or incentive contracts, inclusive of options, with 18 months or greater period of performance, and based on the
nature of the work scope
27APPROVED FOR PUBLIC RELEASE DISTRIBUTIONUNLIMITED: 17-S-2299 August 15, 2017Office of Performance Assessments and Root Cause Analyses (PARCA)
EVMPS AUG 2017
Note – reporting maintains $50M reporting tailoring threshold