package b - fourth lane widening
DESCRIPTION
proposed work program for fourth lane widening project - package bTRANSCRIPT
Activity ID Activity Name OriginalDuration
Early Start Early Finish Late Start Late Finish TotalFloat
PACKAGE B : FOURTH LANE WIDENINGPACKAGE B : FOURTH LANE WIDENING 593 06-Jul-12 05-Jul-14 06-Jul-12 05-Jul-14 0
MilestonesMilestones 593 06-Jul-12 05-Jul-14 06-Jul-12 05-Jul-14 0
BA1000 Letter of Award 0 06-Jul-12 06-Jul-12 0
BA1010 Site Possession 0 06-Jul-12 06-Jul-12 0
BA1060 Section Completion of Package B Section 1 (East Bound) Work 0 05-Oct-13 05-Jul-14 221
BA1150 Section Completion of Package B Section 2 (West Bound) Work 0 05-Jul-14 05-Jul-14 0
BA2000 Completion of PLUS Package B 0 05-Jul-14 05-Jul-14 0
Section 2 (West Bound)Section 2 (West Bound) 375 01-Apr-13 05-Jul-14 05-Jul-14 05-Jul-14 0
BA4000 Commencement Stage 1 0 01-Apr-13 05-Jul-14 375
BA4010 Completion Stage 1 0 14-Apr-14 05-Jul-14 68
BA4020 Commencement Stage 2 0 15-Apr-14 05-Jul-14 68
BA4030 Completion Stage 2 0 05-Jul-14 05-Jul-14 0
Section 1 (East Bound)Section 1 (East Bound) 372 06-Jul-12 05-Oct-13 05-Jul-14 05-Jul-14 221
BA3000 Commencement Stage 1 0 06-Jul-12 05-Jul-14 593
BA3010 Completion Stage 1 0 05-Jun-13 05-Jul-14 321
BA3020 Commencement Stage 2 0 06-Jun-13 05-Jul-14 321
BA3030 Completion Stage 2 0 05-Oct-13 05-Jul-14 221
General ItemsGeneral Items 588 06-Jul-12 30-Jun-14 06-Jul-12 05-Jul-14 5
BB1000 Preliminaries Start 0 06-Jul-12 06-Jul-12 0
BB1010 Initial Site Survey 50 06-Jul-12 06-Sep-12 06-Jul-12 06-Sep-12 0
BB1020 Mobilisation 50 06-Jul-12 06-Sep-12 12-Jul-12 12-Sep-12 5
BB1030 Preliminaries Finish 0 30-Jun-14 05-Jul-14 5
BB4000 Testing of Materials and Works 542 03-Sep-12 30-Jun-14 06-Sep-12 03-Jul-14 3
Method Related ItemsMethod Related Items 578 18-Jul-12 30-Jun-14 24-Jul-12 05-Jul-14 5
BB3030 Construction Plant 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8
Contractor's Accommodation and BuildingsContractor's Accommodation and Buildings 578 18-Jul-12 30-Jun-14 24-Jul-12 05-Jul-14 5
BB3000 Establishment of the Contractor's Offices 35 18-Jul-12 30-Aug-12 24-Jul-12 06-Sep-12 5
BB3010 Removal of the Contractor's Offices 24 03-Jun-14 30-Jun-14 09-Jun-14 05-Jul-14 5
BB3020 Maintenance of the Contractor's Offices 575 18-Jul-12 26-Jun-14 24-Jul-12 02-Jul-14 5
Temporary WorksTemporary Works 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8
BB3100 Temporary Access and Haul Roads 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8
BB3110 Temporary Facilities 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8
BB3120 Project Signboard 6 18-Jul-12 24-Jul-12 27-Jul-12 02-Aug-12 8
BB3130 Metal Deck Hoardings 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8
Specified RequirementsSpecified Requirements 578 18-Jul-12 30-Jun-14 24-Jul-12 05-Jul-14 5
BB2000 Progress Reports 575 18-Jul-12 26-Jun-14 24-Jul-12 02-Jul-14 5
BB2010 Progress Photographs 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8
BB2020 Progress Videos 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8
BB2030 As-Built Drawings 46 06-May-14 30-Jun-14 12-May-14 05-Jul-14 5
BB2040 Operation & Maintenance Manual (O&M) 46 06-May-14 30-Jun-14 12-May-14 05-Jul-14 5
BB2050 Occupational, Safety adn Health Requirements 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8
BB2060 Setting Out 575 18-Jul-12 26-Jun-14 27-Jul-12 05-Jul-14 8
Land AcquisitionLand Acquisition 52 06-Jul-12 08-Sep-12 18-Sep-12 04-Dec-12 70
BB5000 Access from Desa Park City to Edinburgh Estate CH.3380 52 06-Jul-12 08-Sep-12 02-Oct-12 04-Dec-12 70
BB5010 Segambut Dalam Encumbrances at CH.5480 52 06-Jul-12 08-Sep-12 18-Sep-12 20-Nov-12 58
Phase 1 (East Bound)Phase 1 (East Bound) 320 03-Sep-12 28-Sep-13 03-Sep-12 05-Jul-14 227
Site Clearance and Fencing (EB)Site Clearance and Fencing (EB) 317 03-Sep-12 25-Sep-13 03-Sep-12 05-Jul-14 230
BC1005 Site Clearance and Fencing Start (EB) 0 03-Sep-12 03-Sep-12 0
BC1015 Site Clearance and Fencing Finish (EB) 0 25-Sep-13 05-Jul-14 230
Site Clearing and Fencing (CH.0-CH.1400)Site Clearing and Fencing (CH.0-CH.1400) 206 03-Sep-12 10-May-13 03-Sep-12 12-Aug-13 75
BC1000 Site Clearing & Demolition Works 38 03-Sep-12 17-Oct-12 03-Sep-12 17-Oct-12 0
BC1010 Demolition Works 38 03-Sep-12 17-Oct-12 26-Jun-13 12-Aug-13 243
BC1020 Relocation & Installation of Temporary Signage & Gantry 38 03-Sep-12 17-Oct-12 26-Jun-13 12-Aug-13 243
BC1030 Fencing and Gate 37 28-Mar-13 10-May-13 03-Apr-13 16-May-13 5
BC1040 Miscellaneous Dismantling, Demolition and Excavation 38 03-Sep-12 17-Oct-12 26-Jun-13 12-Aug-13 243
Site Clearing and Fencing (CH.1400-CH.2800)Site Clearing and Fencing (CH.1400-CH.2800) 205 18-Oct-12 25-Jun-13 18-Oct-12 27-Sep-13 76
BC1100 Site Clearing & Demolition Works 38 18-Oct-12 04-Dec-12 18-Oct-12 04-Dec-12 0
BC1110 Demolition Works 38 18-Oct-12 04-Dec-12 13-Aug-13 27-Sep-13 243
BC1120 Relocation & Installation of Temporary Signage & Gantry 38 18-Oct-12 04-Dec-12 13-Aug-13 27-Sep-13 243
BC1130 Fencing and Gate 37 11-May-13 25-Jun-13 17-May-13 01-Jul-13 5
BC1140 Miscellaneous Dismantling, Demolition and Excavation 38 18-Oct-12 04-Dec-12 13-Aug-13 27-Sep-13 243
Site Clearing and Fencing (CH.2800-CH.4200)Site Clearing and Fencing (CH.2800-CH.4200) 204 05-Dec-12 10-Aug-13 05-Dec-12 14-Nov-13 77
BC1200 Site Clearing & Demolition Works 38 05-Dec-12 19-Jan-13 05-Dec-12 19-Jan-13 0
BC1210 Demolition Works 38 05-Dec-12 19-Jan-13 28-Sep-13 14-Nov-13 243
BC1220 Relocation & Installation of Temporary Signage & Gantry 38 05-Dec-12 19-Jan-13 28-Sep-13 14-Nov-13 243
BC1230 Fencing and Gate 37 26-Jun-13 10-Aug-13 02-Jul-13 16-Aug-13 5
BC1240 Miscellaneous Dismantling, Demolition and Excavation 38 05-Dec-12 19-Jan-13 28-Sep-13 14-Nov-13 243
Site Clearing and Fencing (CH.4200-CH.5600)Site Clearing and Fencing (CH.4200-CH.5600) 203 21-Jan-13 25-Sep-13 21-Jan-13 31-Dec-13 78
BC1300 Site Clearing & Demolition Works 38 21-Jan-13 07-Mar-13 21-Jan-13 07-Mar-13 0
BC1310 Demolition Works 38 21-Jan-13 07-Mar-13 28-Jan-13 13-Mar-13 5
BC1320 Relocation & Installation of Temporary Signage & Gantry 38 21-Jan-13 07-Mar-13 28-Jan-13 13-Mar-13 5
BC1330 Fencing and Gate 37 12-Aug-13 25-Sep-13 17-Aug-13 01-Oct-13 5
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014
05-Jul-14, PACKAGE B : FOURTH LANE WIDENING
05-Jul-14, Milestones
Letter of Award
Site Possession
Section Completion of Package B Section 1 (East Bound) Work
Section Completion of Package B Section 2 (West Bound) Work
Completion of PLUS Package B
05-Jul-14, Section 2 (West Bound)
Commencement Stage 1
Completion Stage 1
Commencement Stage 2
Completion Stage 2
05-Oct-13, Section 1 (East Bound)
Commencement Stage 1
Completion Stage 1
Commencement Stage 2
Completion Stage 2
30-Jun-14, General Items
Preliminaries Start
Initial Site Survey
Mobilisation
Preliminaries Finish
Testing of Materials and Works
30-Jun-14, Method Related Items
Construction Plant
30-Jun-14, Contractor's Accommodation and Buildings
Establishment of the Contractor's Offices
Removal of the Contractor's Offices
Maintenance of the Contractor's Offices
26-Jun-14, Temporary Works
Temporary Access and Haul Roads
Temporary Facilities
Project Signboard
Metal Deck Hoardings
30-Jun-14, Specified Requirements
Progress Reports
Progress Photographs
Progress Videos
As-Built Drawings
Operation & Maintenance Manual (O&M)
Occupational, Safety adn Health Requirements
Setting Out
08-Sep-12, Land Acquisition
Access from Desa Park City to Edinburgh Estate CH.3380
Segambut Dalam Encumbrances at CH.5480
28-Sep-13, Phase 1 (East Bound)
25-Sep-13, Site Clearance and Fencing (EB)
Site Clearance and Fencing Start (EB)
Site Clearance and Fencing Finish (EB)
10-May-13, Site Clearing and Fencing (CH.0-CH.1400)
Site Clearing & Demolition Works
Demolition Works
Relocation & Installation of Temporary Signage & Gantry
Fencing and Gate
Miscellaneous Dismantling, Demolition and Excavation
25-Jun-13, Site Clearing and Fencing (CH.1400-CH.2800)
Site Clearing & Demolition Works
Demolition Works
Relocation & Installation of Temporary Signage & Gantry
Fencing and Gate
Miscellaneous Dismantling, Demolition and Excavation
10-Aug-13, Site Clearing and Fencing (CH.2800-CH.4200)
Site Clearing & Demolition Works
Demolition Works
Relocation & Installation of Temporary Signage & Gantry
Fencing and Gate
Miscellaneous Dismantling, Demolition and Excavation
25-Sep-13, Site Clearing and Fencing (CH.4200-CH.5600)
Site Clearing & Demolition Works
Demolition Works
Relocation & Installation of Temporary Signage & Gantry
Fencing and Gate
NORTH-SOUTH EXPRESSWAY (PLUS)
PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Remaining Work
Critical Remaining Work
Milestone
Summary 1 of 13
WORK PROGRAMME
Date Revision Checked Approved
30-Jul-12 Rev.0
11-Sep-12 Rev.1
Activity ID Activity Name OriginalDuration
Early Start Early Finish Late Start Late Finish TotalFloat
BC1340 Miscellaneous Dismantling, Demolition and Excavation 38 21-Jan-13 07-Mar-13 15-Nov-13 31-Dec-13 243
Earthworks (EB)Earthworks (EB) 309 15-Sep-12 28-Sep-13 22-Sep-12 05-Jul-14 227
BD0010 Earthwork Start (EB) 0 15-Sep-12 08-Nov-12 44
BD0020 Earthwork Finish (EB) 0 28-Sep-13 05-Jul-14 227
Stage 1Stage 1 175 15-Sep-12 16-Apr-13 22-Sep-12 14-Oct-13 147
CH.2800-CH.4200CH.2800-CH.4200 61 18-Dec-12 02-Mar-13 12-Jan-13 28-Aug-13 147
BD1200 Excavate to Toe of Slope (CH.2800-CH.4200) 38 18-Dec-12 02-Feb-13 05-Jul-13 21-Aug-13 164
BD1210 Fill to Formation Level (CH.2800-CH.4200) 38 07-Jan-13 21-Feb-13 12-Jan-13 27-Feb-13 5
BD1220 Turf ing 38 16-Jan-13 02-Mar-13 18-Mar-13 30-Apr-13 50
BD1230 Instrumentation and Monitoring 44 07-Jan-13 28-Feb-13 05-Jul-13 28-Aug-13 149
BD1240 Soil Investigation 38 18-Dec-12 02-Feb-13 05-Jul-13 21-Aug-13 164
CH.0-CH.1400CH.0-CH.1400 61 15-Sep-12 29-Nov-12 22-Sep-12 27-May-13 147
BD1000 Excavate to Toe of Slope (CH.0-CH.1400) 38 15-Sep-12 31-Oct-12 22-Sep-12 06-Nov-12 5
BD1010 Fill to Formation Level (CH.0-CH.1400) 38 04-Oct-12 20-Nov-12 10-Oct-12 26-Nov-12 5
BD1020 Turf ing 38 13-Oct-12 29-Nov-12 14-Dec-12 30-Jan-13 50
BD1030 Instrumentation and Monitoring 44 04-Oct-12 27-Nov-12 04-Apr-13 27-May-13 149
BD1040 Soil Investigation 38 15-Sep-12 31-Oct-12 04-Apr-13 18-May-13 164
CH.1400-CH.2800CH.1400-CH.2800 61 01-Nov-12 15-Jan-13 27-Nov-12 11-Jul-13 147
BD1100 Excavate to Toe of Slope (CH.1400-CH.2800) 38 01-Nov-12 17-Dec-12 20-May-13 04-Jul-13 164
BD1110 Fill to Formation Level (CH.1400-CH.2800) 38 21-Nov-12 05-Jan-13 27-Nov-12 11-Jan-13 5
BD1120 Turf ing 38 30-Nov-12 15-Jan-13 31-Jan-13 16-Mar-13 50
BD1130 Instrumentation and Monitoring 44 21-Nov-12 12-Jan-13 20-May-13 11-Jul-13 149
BD1140 Soil Investigation 38 01-Nov-12 17-Dec-12 20-May-13 04-Jul-13 164
CH.4200-CH.5600CH.4200-CH.5600 61 04-Feb-13 16-Apr-13 28-Feb-13 14-Oct-13 147
BD1300 Excavate to Toe of Slope (CH.4200-CH.5600) 38 04-Feb-13 20-Mar-13 22-Aug-13 07-Oct-13 164
BD1310 Fill to Formation Level (CH.4200-CH.5600) 38 22-Feb-13 06-Apr-13 28-Feb-13 12-Apr-13 5
BD1320 Turf ing 38 04-Mar-13 16-Apr-13 02-May-13 17-Jun-13 50
BD1330 Instrumentation and Monitoring 44 22-Feb-13 13-Apr-13 22-Aug-13 14-Oct-13 149
BD1340 Soil Investigation 38 04-Feb-13 20-Mar-13 22-Aug-13 07-Oct-13 164
Stage 2Stage 2 142 08-Apr-13 28-Sep-13 30-Apr-13 07-Feb-14 104
CH.4200-CH.5600CH.4200-CH.5600 46 02-Aug-13 28-Sep-13 27-Aug-13 07-Feb-14 104
BD2300 Removal of Existing Pavement 32 02-Aug-13 11-Sep-13 27-Aug-13 04-Oct-13 19
BD2310 Turf ing (Remaining Works) 32 21-Aug-13 28-Sep-13 28-Dec-13 07-Feb-14 104
BD2320 Treatment of Existing Subsoil Drain 32 13-Aug-13 20-Sep-13 19-Dec-13 28-Jan-14 104
CH.1400-CH.2800CH.1400-CH.2800 46 16-May-13 10-Jul-13 10-Jun-13 18-Nov-13 104
BD2100 Removal of Existing Pavement 32 16-May-13 24-Jun-13 10-Jun-13 16-Jul-13 19
BD2110 Turf ing (Remaining Works) 32 04-Jun-13 10-Jul-13 09-Oct-13 18-Nov-13 104
BD2120 Treatment of Existing Subsoil Drain 32 25-May-13 02-Jul-13 01-Oct-13 09-Nov-13 104
CH.2800-CH.4200CH.2800-CH.4200 46 25-Jun-13 20-Aug-13 17-Jul-13 27-Dec-13 104
BD2200 Removal of Existing Pavement 32 25-Jun-13 01-Aug-13 17-Jul-13 26-Aug-13 19
BD2210 Turf ing (Remaining Works) 32 11-Jul-13 20-Aug-13 19-Nov-13 27-Dec-13 104
BD2220 Treatment of Existing Subsoil Drain 32 03-Jul-13 12-Aug-13 11-Nov-13 18-Dec-13 104
CH.0-CH.1400CH.0-CH.1400 46 08-Apr-13 03-Jun-13 30-Apr-13 08-Oct-13 104
BD2000 Removal of Existing Pavement 32 08-Apr-13 15-May-13 30-Apr-13 08-Jun-13 19
BD2010 Turf ing (Remaining Works) 32 24-Apr-13 03-Jun-13 30-Aug-13 08-Oct-13 104
BD2020 Treatment of Existing Subsoil Drain 32 16-Apr-13 23-May-13 22-Aug-13 30-Sep-13 104
Drainage Works (EB)Drainage Works (EB) 309 15-Sep-12 28-Sep-13 10-Nov-12 05-Jul-14 227
BE0010 Drainage Works Start (EB) 0 15-Sep-12 10-Nov-12 46
BE0030 Drainage Works Finish (EB) 0 28-Sep-13 05-Jul-14 227
Stage 1Stage 1 309 15-Sep-12 28-Sep-13 10-Nov-12 05-Jul-14 227
Pipe Culverts ExtensionsPipe Culverts Extensions 250 28-Nov-12 28-Sep-13 02-Sep-13 05-Jul-14 227
Culvert 4 (CH.1293)Culvert 4 (CH.1293) 25 28-Feb-13 28-Mar-13 03-Dec-13 03-Jan-14 227
BE3300 Pipe Culvert Extension 11 28-Feb-13 12-Mar-13 03-Dec-13 16-Dec-13 227
BE3310 RC Box Joints 3 13-Mar-13 15-Mar-13 17-Dec-13 19-Dec-13 227
BE3320 Inlet/Outlet Structures 11 16-Mar-13 28-Mar-13 20-Dec-13 03-Jan-14 227
Culvert 1 (CH.94)Culvert 1 (CH.94) 25 28-Nov-12 27-Dec-12 02-Sep-13 01-Oct-13 227
BE3000 Pipe Culvert Extension 11 28-Nov-12 10-Dec-12 02-Sep-13 13-Sep-13 227
BE3010 RC Box Joints 3 11-Dec-12 13-Dec-12 14-Sep-13 18-Sep-13 227
BE3020 Inlet/Outlet Structures 11 14-Dec-12 27-Dec-12 19-Sep-13 01-Oct-13 227
Culvert 2 (CH.625)Culvert 2 (CH.625) 25 28-Dec-12 28-Jan-13 02-Oct-13 31-Oct-13 227
BE3100 Pipe Culvert Extension 11 28-Dec-12 10-Jan-13 02-Oct-13 14-Oct-13 227
BE3110 RC Box Joints 3 11-Jan-13 14-Jan-13 16-Oct-13 18-Oct-13 227
BE3120 Inlet/Outlet Structures 11 15-Jan-13 28-Jan-13 19-Oct-13 31-Oct-13 227
Culvert 3 (CH.927)Culvert 3 (CH.927) 25 29-Jan-13 27-Feb-13 01-Nov-13 02-Dec-13 227
BE3200 Pipe Culvert Extension 11 29-Jan-13 09-Feb-13 01-Nov-13 15-Nov-13 227
BE3210 RC Box Joints 3 12-Feb-13 14-Feb-13 16-Nov-13 19-Nov-13 227
BE3220 Inlet/Outlet Structures 11 15-Feb-13 27-Feb-13 20-Nov-13 02-Dec-13 227
Culvert 5 (CH.2365)Culvert 5 (CH.2365) 25 29-Mar-13 26-Apr-13 04-Jan-14 05-Feb-14 227
BE3400 Pipe Culvert Extension 11 29-Mar-13 10-Apr-13 04-Jan-14 17-Jan-14 227
BE3410 RC Box Joints 3 11-Apr-13 13-Apr-13 18-Jan-14 21-Jan-14 227
BE3420 Inlet/Outlet Structures 11 15-Apr-13 26-Apr-13 22-Jan-14 05-Feb-14 227
Culvert 6 (CH.2926)Culvert 6 (CH.2926) 25 27-Apr-13 28-May-13 06-Feb-14 07-Mar-14 227
BE3500 Pipe Culvert Extension 11 27-Apr-13 10-May-13 06-Feb-14 19-Feb-14 227
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014
Miscellaneous Dismantling, Demolition and Excavation
28-Sep-13, Earthworks (EB)
Earthwork Start (EB)
Earthwork Finish (EB)
16-Apr-13, Stage 1
02-Mar-13, CH.2800-CH.4200
Excavate to Toe of Slope (CH.2800-CH.4200)
Fill to Formation Level (CH.2800-CH.4200)
Turfing
Instrumentation and Monitoring
Soil Investigation
29-Nov-12, CH.0-CH.1400
Excavate to Toe of Slope (CH.0-CH.1400)
Fill to Formation Level (CH.0-CH.1400)
Turf ing
Instrumentation and Monitoring
Soil Investigation
15-Jan-13, CH.1400-CH.2800
Excavate to Toe of Slope (CH.1400-CH.2800)
Fill to Formation Level (CH.1400-CH.2800)
Turf ing
Instrumentation and Monitoring
Soil Investigation
16-Apr-13, CH.4200-CH.5600
Excavate to Toe of Slope (CH.4200-CH.5600)
Fill to Formation Level (CH.4200-CH.5600)
Turf ing
Instrumentation and Monitoring
Soil Investigation
28-Sep-13, Stage 2
28-Sep-13, CH.4200-CH.5600
Removal of Existing Pavement
Turf ing (Remaining Works)
Treatment of Existing Subsoil Drain
10-Jul-13, CH.1400-CH.2800
Removal of Existing Pavement
Turf ing (Remaining Works)
Treatment of Existing Subsoil Drain
20-Aug-13, CH.2800-CH.4200
Removal of Existing Pavement
Turf ing (Remaining Works)
Treatment of Existing Subsoil Drain
03-Jun-13, CH.0-CH.1400
Removal of Existing Pavement
Turf ing (Remaining Works)
Treatment of Existing Subsoil Drain
28-Sep-13, Drainage Works (EB)
Drainage Works Start (EB)
Drainage Works Finish (EB)
28-Sep-13, Stage 1
28-Sep-13, Pipe Culverts Extensions
28-Mar-13, Culvert 4 (CH.1293)
Pipe Culvert Extension
RC Box Joints
Inlet/Outlet Structures
27-Dec-12, Culvert 1 (CH.94)
Pipe Culvert Extension
RC Box Joints
Inlet/Outlet Structures
28-Jan-13, Culvert 2 (CH.625)
Pipe Culvert Extension
RC Box Joints
Inlet/Outlet Structures
27-Feb-13, Culvert 3 (CH.927)
Pipe Culvert Extension
RC Box Joints
Inlet/Outlet Structures
26-Apr-13, Culvert 5 (CH.2365)
Pipe Culvert Extension
RC Box Joints
Inlet/Outlet Structures
28-May-13, Culvert 6 (CH.2926)
Pipe Culvert Extension
NORTH-SOUTH EXPRESSWAY (PLUS)
PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Remaining Work
Critical Remaining Work
Milestone
Summary 2 of 13
WORK PROGRAMME
Date Revision Checked Approved
30-Jul-12 Rev.0
11-Sep-12 Rev.1
Activity ID Activity Name OriginalDuration
Early Start Early Finish Late Start Late Finish TotalFloat
BE3510 RC Box Joints 3 11-May-13 14-May-13 20-Feb-14 22-Feb-14 227
BE3520 Inlet/Outlet Structures 11 15-May-13 28-May-13 24-Feb-14 07-Mar-14 227
Culvert 7 (CH.3640)Culvert 7 (CH.3640) 25 29-May-13 27-Jun-13 08-Mar-14 05-Apr-14 227
BE3600 Pipe Culvert Extension 11 29-May-13 11-Jun-13 08-Mar-14 20-Mar-14 227
BE3610 RC Box Joints 3 12-Jun-13 14-Jun-13 21-Mar-14 24-Mar-14 227
BE3620 Inlet/Outlet Structures 11 15-Jun-13 27-Jun-13 25-Mar-14 05-Apr-14 227
Culvert 8 (CH.4196)Culvert 8 (CH.4196) 25 28-Jun-13 27-Jul-13 07-Apr-14 06-May-14 227
BE3700 Pipe Culvert Extension 11 28-Jun-13 10-Jul-13 07-Apr-14 18-Apr-14 227
BE3710 RC Box Joints 3 11-Jul-13 13-Jul-13 19-Apr-14 22-Apr-14 227
BE3720 Inlet/Outlet Structures 11 15-Jul-13 27-Jul-13 23-Apr-14 06-May-14 227
Culvert 9 (CH.4628)Culvert 9 (CH.4628) 25 29-Jul-13 28-Aug-13 07-May-14 06-Jun-14 227
BE3800 Pipe Culvert Extension 11 29-Jul-13 12-Aug-13 07-May-14 20-May-14 227
BE3810 RC Box Joints 3 13-Aug-13 15-Aug-13 21-May-14 23-May-14 227
BE3820 Inlet/Outlet Structures 11 16-Aug-13 28-Aug-13 24-May-14 06-Jun-14 227
Culvert 10 (CH.4906)Culvert 10 (CH.4906) 25 29-Aug-13 28-Sep-13 07-Jun-14 05-Jul-14 227
BE3900 Pipe Culvert Extension 11 29-Aug-13 11-Sep-13 07-Jun-14 19-Jun-14 227
BE3910 RC Box Joints 3 12-Sep-13 14-Sep-13 20-Jun-14 23-Jun-14 227
BE3920 Inlet/Outlet Structures 11 17-Sep-13 28-Sep-13 24-Jun-14 05-Jul-14 227
Drainage (CH.0-CH.1400)Drainage (CH.0-CH.1400) 43 15-Sep-12 06-Nov-12 10-Nov-12 03-Jan-13 46
BE1000 Excavation 33 15-Sep-12 24-Oct-12 10-Nov-12 20-Dec-12 46
BE1010 Laying of Drain 33 22-Sep-12 31-Oct-12 19-Nov-12 27-Dec-12 46
BE1020 Backfilling 33 28-Sep-12 06-Nov-12 24-Nov-12 03-Jan-13 46
Drainage (CH.1400-CH.2800)Drainage (CH.1400-CH.2800) 43 07-Nov-12 29-Dec-12 04-Jan-13 25-Feb-13 46
BE1100 Excavation 33 07-Nov-12 17-Dec-12 04-Jan-13 13-Feb-13 46
BE1110 Laying of Drain 33 14-Nov-12 22-Dec-12 10-Jan-13 19-Feb-13 46
BE1120 Backfilling 33 21-Nov-12 29-Dec-12 16-Jan-13 25-Feb-13 46
Drainage (CH.2800-CH.4200)Drainage (CH.2800-CH.4200) 43 31-Dec-12 21-Feb-13 26-Feb-13 16-Apr-13 46
BE1200 Excavation 33 31-Dec-12 08-Feb-13 26-Feb-13 04-Apr-13 46
BE1210 Laying of Drain 33 07-Jan-13 15-Feb-13 04-Mar-13 10-Apr-13 46
BE1220 Backfilling 33 12-Jan-13 21-Feb-13 09-Mar-13 16-Apr-13 46
Drainage (CH.4200-CH.5600)Drainage (CH.4200-CH.5600) 43 22-Feb-13 12-Apr-13 17-Apr-13 08-Jun-13 46
BE1300 Excavation 33 22-Feb-13 01-Apr-13 17-Apr-13 27-May-13 46
BE1310 Laying of Drain 33 28-Feb-13 06-Apr-13 23-Apr-13 03-Jun-13 46
BE1320 Backfilling 33 06-Mar-13 12-Apr-13 29-Apr-13 08-Jun-13 46
Stage 2Stage 2 128 13-Apr-13 18-Sep-13 03-Feb-14 05-Jul-14 236
Drains (Remaining Works) and KerbsDrains (Remaining Works) and Kerbs 128 13-Apr-13 18-Sep-13 03-Feb-14 05-Jul-14 236
BE1500 CH.0-CH.1400 32 13-Apr-13 21-May-13 03-Feb-14 12-Mar-14 236
BE1510 CH.1400-CH.2800 32 22-May-13 29-Jun-13 13-Mar-14 18-Apr-14 236
BE1520 CH.2800-CH.4200 32 01-Jul-13 07-Aug-13 19-Apr-14 28-May-14 236
BE1530 CH.4200-CH.5600 32 10-Aug-13 18-Sep-13 29-May-14 05-Jul-14 236
Sub-Base, Roadbase and Pavement (EB)Sub-Base, Roadbase and Pavement (EB) 158 20-Mar-13 28-Sep-13 11-May-13 05-Jul-14 227
BF0010 Sub-Base, Roadbase and Pavement Start (EB) 0 20-Mar-13 11-May-13 44
BF0020 Sub-Base, Roadbase and Pavement Finish (EB) 0 28-Sep-13 05-Jul-14 227
Stage 1Stage 1 96 20-Mar-13 12-Jul-13 13-Mar-14 05-Jul-14 289
BF0500 Saw Cut of CRCP - CH.0-CH.1400 24 20-Mar-13 16-Apr-13 13-Mar-14 09-Apr-14 289
BF0510 Saw Cut of CRCP - CH.1400-CH.2800 24 17-Apr-13 15-May-13 10-Apr-14 08-May-14 289
BF0520 Saw Cut of CRCP - CH.2800-CH.4200 24 16-May-13 14-Jun-13 09-May-14 07-Jun-14 289
BF0530 Saw Cut of CRCP - CH.4200-CH.5600 24 15-Jun-13 12-Jul-13 09-Jun-14 05-Jul-14 289
Stage 2Stage 2 158 20-Mar-13 28-Sep-13 11-May-13 05-Jul-14 227
BF3000 Sub-surface Drainage Improvement (East Bound) 140 20-Mar-13 06-Sep-13 11-May-13 30-Oct-13 44
Sub-Base upto Pavement (CH.0-CH.1400)Sub-Base upto Pavement (CH.0-CH.1400) 38 18-Apr-13 04-Jun-13 11-May-13 16-Apr-14 256
BF1010 Sub-Grade and Prepare Formation 24 18-Apr-13 16-May-13 11-May-13 10-Jun-13 19
BF1020 Laying of Lower Sub-Base 24 20-Apr-13 18-May-13 14-May-13 12-Jun-13 19
BF1030 Laying of Lower Upper-Base 24 23-Apr-13 21-May-13 16-May-13 14-Jun-13 19
BF1040 Laying of CBM 22 25-Apr-13 21-May-13 18-May-13 14-Jun-13 19
BF1050 Laying of WMM 22 27-Apr-13 23-May-13 01-Nov-13 28-Nov-13 152
BF1060 Laying of DBM 22 30-Apr-13 27-May-13 06-Nov-13 30-Nov-13 152
BF1070 Laying of ACBC 22 03-May-13 29-May-13 08-Nov-13 03-Dec-13 152
BF1075 Regulating 22 04-May-13 30-May-13 22-Mar-14 16-Apr-14 259
BF1080 Laying of ACWC 22 06-May-13 31-May-13 11-Nov-13 05-Dec-13 152
BF1090 Laying of SMA 22 08-May-13 04-Jun-13 13-Nov-13 07-Dec-13 152
BF1100 Dismantle Guardrail, NJB Installation & Misc. Works 32 25-Apr-13 04-Jun-13 18-May-13 26-Jun-13 19
BF1110 Temporay Road Marking & Traffic Diversion/Contra Flow 32 25-Apr-13 04-Jun-13 04-Feb-14 13-Mar-14 227
Sub-Base upto Pavement (CH.2800-CH.4200)Sub-Base upto Pavement (CH.2800-CH.4200) 38 05-Jul-13 21-Aug-13 29-Jul-13 05-Jul-14 258
BF1410 Sub-Grade and Prepare Formation 24 05-Jul-13 02-Aug-13 29-Jul-13 27-Aug-13 19
BF1420 Laying of Lower Sub-Base 24 08-Jul-13 05-Aug-13 31-Jul-13 29-Aug-13 19
BF1430 Laying of Lower Upper-Base 24 10-Jul-13 07-Aug-13 02-Aug-13 02-Sep-13 19
BF1440 Laying of CBM 22 12-Jul-13 07-Aug-13 05-Aug-13 02-Sep-13 19
BF1450 Laying of WMM 22 15-Jul-13 12-Aug-13 08-May-14 04-Jun-14 239
BF1460 Laying of DBM 22 17-Jul-13 14-Aug-13 10-May-14 06-Jun-14 239
BF1470 Laying of ACBC 22 19-Jul-13 16-Aug-13 14-May-14 09-Jun-14 239
BF1475 Regulating 22 20-Jul-13 17-Aug-13 15-May-14 10-Jun-14 239
BF1480 Laying of ACWC 22 22-Jul-13 19-Aug-13 09-Jun-14 03-Jul-14 258
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014
RC Box Joints
Inlet/Outlet Structures
27-Jun-13, Culvert 7 (CH.3640)
Pipe Culvert Extension
RC Box Joints
Inlet/Outlet Structures
27-Jul-13, Culvert 8 (CH.4196)
Pipe Culvert Extension
RC Box Joints
Inlet/Outlet Structures
28-Aug-13, Culvert 9 (CH.4628)
Pipe Culvert Extension
RC Box Joints
Inlet/Outlet Structures
28-Sep-13, Culvert 10 (CH.4906)
Pipe Culvert Extension
RC Box Joints
Inlet/Outlet Structures
06-Nov-12, Drainage (CH.0-CH.1400)
Excavation
Laying of Drain
Backfilling
29-Dec-12, Drainage (CH.1400-CH.2800)
Excavation
Laying of Drain
Backfilling
21-Feb-13, Drainage (CH.2800-CH.4200)
Excavation
Laying of Drain
Backfilling
12-Apr-13, Drainage (CH.4200-CH.5600)
Excavation
Laying of Drain
Backfilling
18-Sep-13, Stage 2
18-Sep-13, Drains (Remaining Works) and Kerbs
CH.0-CH.1400
CH.1400-CH.2800
CH.2800-CH.4200
CH.4200-CH.5600
28-Sep-13, Sub-Base, Roadbase and Pavement (EB)
Sub-Base, Roadbase and Pavement Start (EB)
Sub-Base, Roadbase and Pavement Finish (EB)
12-Jul-13, Stage 1
Saw Cut of CRCP - CH.0-CH.1400
Saw Cut of CRCP - CH.1400-CH.2800
Saw Cut of CRCP - CH.2800-CH.4200
Saw Cut of CRCP - CH.4200-CH.5600
28-Sep-13, Stage 2
Sub-surface Drainage Improvement (East Bound)
04-Jun-13, Sub-Base upto Pavement (CH.0-CH.1400)
Sub-Grade and Prepare Formation
Laying of Lower Sub-Base
Laying of Lower Upper-Base
Laying of CBM
Laying of WMM
Laying of DBM
Laying of ACBC
Regulating
Laying of ACWC
Laying of SMA
Dismantle Guardrail, NJB Installation & Misc. Works
Temporay Road Marking & Traffic Diversion/Contra Flow
21-Aug-13, Sub-Base upto Pavement (CH.2800-CH.4200)
Sub-Grade and Prepare Formation
Laying of Lower Sub-Base
Laying of Lower Upper-Base
Laying of CBM
Laying of WMM
Laying of DBM
Laying of ACBC
Regulating
Laying of ACWC
NORTH-SOUTH EXPRESSWAY (PLUS)
PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Remaining Work
Critical Remaining Work
Milestone
Summary 3 of 13
WORK PROGRAMME
Date Revision Checked Approved
30-Jul-12 Rev.0
11-Sep-12 Rev.1
Activity ID Activity Name OriginalDuration
Early Start Early Finish Late Start Late Finish TotalFloat
BF1490 Laying of SMA 22 24-Jul-13 21-Aug-13 11-Jun-14 05-Jul-14 258
BF1500 Dismantle Guardrail, NJB Installation & Misc. Works 32 12-Jul-13 21-Aug-13 05-Aug-13 13-Sep-13 19
BF1510 Temporay Road Marking & Traffic Diversion/Contra Flow 32 12-Jul-13 21-Aug-13 21-Apr-14 29-May-14 227
Sub-Base upto Pavement (CH.4200-CH.5600)Sub-Base upto Pavement (CH.4200-CH.5600) 37 15-Aug-13 28-Sep-13 07-Sep-13 05-Jul-14 227
BF1610 Sub-Grade and Prepare Formation 24 15-Aug-13 12-Sep-13 07-Sep-13 05-Oct-13 19
BF1620 Laying of Lower Sub-Base 24 17-Aug-13 14-Sep-13 10-Sep-13 08-Oct-13 19
BF1630 Laying of Lower Upper-Base 24 20-Aug-13 18-Sep-13 12-Sep-13 10-Oct-13 19
BF1640 Laying of CBM 22 22-Aug-13 18-Sep-13 14-Sep-13 10-Oct-13 19
BF1650 Laying of WMM 22 24-Aug-13 20-Sep-13 04-Jun-14 28-Jun-14 228
BF1660 Laying of DBM 22 27-Aug-13 23-Sep-13 06-Jun-14 01-Jul-14 228
BF1670 Laying of ACBC 22 29-Aug-13 25-Sep-13 09-Jun-14 03-Jul-14 228
BF1675 Regulating 22 30-Aug-13 26-Sep-13 11-Jun-14 05-Jul-14 229
BF1680 Laying of ACWC 22 30-Aug-13 26-Sep-13 10-Jun-14 04-Jul-14 228
BF1690 Laying of SMA 22 02-Sep-13 27-Sep-13 11-Jun-14 05-Jul-14 228
BF1700 Dismantle Guardrail, NJB Installation & Misc. Works 31 22-Aug-13 28-Sep-13 14-Sep-13 22-Oct-13 19
BF1710 Temporay Road Marking & Traffic Diversion/Contra Flow 31 22-Aug-13 28-Sep-13 30-May-14 05-Jul-14 227
Sub-Base upto Pavement (CH.1400-CH.2800)Sub-Base upto Pavement (CH.1400-CH.2800) 38 28-May-13 11-Jul-13 20-Jun-13 05-Jul-14 290
BF1210 Sub-Grade and Prepare Formation 24 28-May-13 25-Jun-13 20-Jun-13 17-Jul-13 19
BF1220 Laying of Lower Sub-Base 24 30-May-13 27-Jun-13 22-Jun-13 19-Jul-13 19
BF1230 Laying of Lower Upper-Base 24 03-Jun-13 29-Jun-13 25-Jun-13 22-Jul-13 19
BF1240 Laying of CBM 22 05-Jun-13 29-Jun-13 27-Jun-13 22-Jul-13 19
BF1250 Laying of WMM 22 07-Jun-13 02-Jul-13 11-Apr-14 07-May-14 249
BF1260 Laying of DBM 22 10-Jun-13 04-Jul-13 14-Apr-14 09-May-14 249
BF1270 Laying of ACBC 22 12-Jun-13 06-Jul-13 16-Apr-14 12-May-14 249
BF1275 Regulating 22 13-Jun-13 08-Jul-13 17-Apr-14 14-May-14 249
BF1280 Laying of ACWC 22 14-Jun-13 09-Jul-13 09-Jun-14 03-Jul-14 290
BF1290 Laying of SMA 22 17-Jun-13 11-Jul-13 11-Jun-14 05-Jul-14 290
BF1300 Dismantle Guardrail, NJB Installation & Misc. Works 32 05-Jun-13 11-Jul-13 27-Jun-13 03-Aug-13 19
BF1310 Temporay Road Marking & Traffic Diversion/Contra Flow 32 05-Jun-13 11-Jul-13 14-Mar-14 19-Apr-14 227
Road Furniture (EB)Road Furniture (EB) 73 01-Jul-13 28-Sep-13 07-Jan-14 05-Jul-14 227
BG0010 Road Furniture Start (EB) 0 01-Jul-13 07-Jan-14 152
BG0020 Road Furniture Finish (EB) 0 28-Sep-13 05-Jul-14 227
Stage 2Stage 2 73 01-Jul-13 28-Sep-13 07-Jan-14 05-Apr-14 152
CH.4200-CH.5600CH.4200-CH.5600 18 07-Sep-13 28-Sep-13 17-Mar-14 05-Apr-14 152
BG1300 Traffic Signs 18 07-Sep-13 28-Sep-13 17-Mar-14 05-Apr-14 152
BG1310 Road Markings 18 07-Sep-13 28-Sep-13 17-Mar-14 05-Apr-14 152
BG1320 Ancillary Finishings 18 07-Sep-13 28-Sep-13 17-Mar-14 05-Apr-14 152
CH.1400-CH.2800CH.1400-CH.2800 18 23-Jul-13 15-Aug-13 30-Jan-14 22-Feb-14 152
BG1100 Traffic Signs 18 23-Jul-13 15-Aug-13 30-Jan-14 22-Feb-14 152
BG1110 Road Markings 18 23-Jul-13 15-Aug-13 30-Jan-14 22-Feb-14 152
BG1120 Ancillary Finishings 18 23-Jul-13 15-Aug-13 30-Jan-14 22-Feb-14 152
CH.2800-CH.4200CH.2800-CH.4200 18 16-Aug-13 06-Sep-13 24-Feb-14 15-Mar-14 152
BG1200 Traffic Signs 18 16-Aug-13 06-Sep-13 24-Feb-14 15-Mar-14 152
BG1210 Road Markings 18 16-Aug-13 06-Sep-13 24-Feb-14 15-Mar-14 152
BG1220 Ancillary Finishings 18 16-Aug-13 06-Sep-13 24-Feb-14 15-Mar-14 152
CH.0-CH.1400CH.0-CH.1400 19 01-Jul-13 22-Jul-13 07-Jan-14 29-Jan-14 152
BG1000 Traffic Signs 19 01-Jul-13 22-Jul-13 07-Jan-14 29-Jan-14 152
BG1010 Road Markings 19 01-Jul-13 22-Jul-13 07-Jan-14 29-Jan-14 152
BG1020 Ancillary Finishings 19 01-Jul-13 22-Jul-13 07-Jan-14 29-Jan-14 152
Utilities and Services (EB)Utilities and Services (EB) 222 02-Jan-13 28-Sep-13 10-Jan-13 05-Jul-14 227
BH0100 Utilities and Services Start (EB) 0 02-Jan-13 10-Jan-13 7
BH0110 Utilities and Services Finish (EB) 0 28-Sep-13 05-Jul-14 227
Overall Stage 1Overall Stage 1 222 02-Jan-13 28-Sep-13 10-Jan-13 05-Jul-14 227
BH0020 Testing and Commissioning 94 06-Jun-13 28-Sep-13 12-Jun-13 04-Oct-13 5
CH.0-CH.1400CH.0-CH.1400 122 02-Jan-13 28-May-13 10-Jan-13 05-Jul-14 327
BH1030 Temporary Works for Exist ing Utilities 104 23-Jan-13 28-May-13 04-Mar-14 05-Jul-14 327
Telecommunication SystemTelecommunication System 36 02-Jan-13 14-Feb-13 10-Jan-13 22-Feb-13 7
BH1000 Lay Duct 36 02-Jan-13 14-Feb-13 10-Jan-13 22-Feb-13 7
CH.1400-CH.2800CH.1400-CH.2800 108 02-Feb-13 12-Jun-13 12-Feb-13 05-Jul-14 315
BH2030 Temporary Works for Exist ing Utilities 90 25-Feb-13 12-Jun-13 20-Mar-14 05-Jul-14 315
Telecommunication SystemTelecommunication System 60 02-Feb-13 13-Apr-13 12-Feb-13 11-Jun-13 47
BH2000 Lay Duct 36 02-Feb-13 16-Mar-13 12-Feb-13 25-Mar-13 7
BH2010 Relocation of OFC 36 18-Feb-13 30-Mar-13 13-Apr-13 27-May-13 47
BH2020 ITS System 36 04-Mar-13 13-Apr-13 27-Apr-13 11-Jun-13 47
CH.2800-CH.4200CH.2800-CH.4200 108 06-Mar-13 12-Jul-13 14-Mar-13 05-Jul-14 289
BH3030 Temporary Works for Exist ing Utilities 90 27-Mar-13 12-Jul-13 20-Mar-14 05-Jul-14 289
Telecommunication SystemTelecommunication System 60 06-Mar-13 15-May-13 14-Mar-13 11-Jun-13 21
BH3000 Lay Duct 36 06-Mar-13 16-Apr-13 14-Mar-13 24-Apr-13 7
BH3010 Relocation of OFC 36 20-Mar-13 30-Apr-13 13-Apr-13 27-May-13 21
BH3020 ITS System 36 03-Apr-13 15-May-13 27-Apr-13 11-Jun-13 21
CH.4200-CH.5600CH.4200-CH.5600 202 02-Jan-13 04-Sep-13 13-Apr-13 05-Jul-14 247
BH4030 Temporary Works for Exist ing Utilities 104 29-Apr-13 04-Sep-13 04-Mar-14 05-Jul-14 247
BH4040 Waterworks, Relocation of Water Mains (CH.5450) 70 02-Jan-13 26-Mar-13 09-Oct-13 04-Jan-14 230
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014
Laying of SMA
Dismantle Guardrail, NJB Installation & Misc. Works
Temporay Road Marking & Traffic Diversion/Contra Flow
28-Sep-13, Sub-Base upto Pavement (CH.4200-CH.5600)
Sub-Grade and Prepare Formation
Laying of Lower Sub-Base
Laying of Lower Upper-Base
Laying of CBM
Laying of WMM
Laying of DBM
Laying of ACBC
Regulating
Laying of ACWC
Laying of SMA
Dismantle Guardrail, NJB Installation & Misc. Works
Temporay Road Marking & Traffic Diversion/Contra Flow
11-Jul-13, Sub-Base upto Pavement (CH.1400-CH.2800)
Sub-Grade and Prepare Formation
Laying of Lower Sub-Base
Laying of Lower Upper-Base
Laying of CBM
Laying of WMM
Laying of DBM
Laying of ACBC
Regulating
Laying of ACWC
Laying of SMA
Dismantle Guardrail, NJB Installation & Misc. Works
Temporay Road Marking & Traffic Diversion/Contra Flow
28-Sep-13, Road Furniture (EB)
Road Furniture Start (EB)
Road Furniture Finish (EB)
28-Sep-13, Stage 2
28-Sep-13, CH.4200-CH.5600
Traffic Signs
Road Markings
Ancillary Finishings
15-Aug-13, CH.1400-CH.2800
Traffic Signs
Road Markings
Ancillary Finishings
06-Sep-13, CH.2800-CH.4200
Traffic Signs
Road Markings
Ancillary Finishings
22-Jul-13, CH.0-CH.1400
Traffic Signs
Road Markings
Ancillary Finishings
28-Sep-13, Utilities and Services (EB)
Utilities and Services Start (EB)
Utilities and Services Finish (EB)
28-Sep-13, Overall Stage 1
Testing and Commissioning
28-May-13, CH.0-CH.1400
Temporary Works for Exist ing Utilities
14-Feb-13, Telecommunication System
Lay Duct
12-Jun-13, CH.1400-CH.2800
Temporary Works for Existing Utilities
13-Apr-13, Telecommunication System
Lay Duct
Relocation of OFC
ITS System
12-Jul-13, CH.2800-CH.4200
Temporary Works for Exist ing Utilities
15-May-13, Telecommunication System
Lay Duct
Relocation of OFC
ITS System
04-Sep-13, CH.4200-CH.5600
Temporary Works for Exist ing Utilities
Waterworks, Relocation of Water Mains (CH.5450)
NORTH-SOUTH EXPRESSWAY (PLUS)
PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Remaining Work
Critical Remaining Work
Milestone
Summary 4 of 13
WORK PROGRAMME
Date Revision Checked Approved
30-Jul-12 Rev.0
11-Sep-12 Rev.1
Activity ID Activity Name OriginalDuration
Early Start Early Finish Late Start Late Finish TotalFloat
Telecommunication SystemTelecommunication System 48 08-Apr-13 05-Jun-13 13-Apr-13 11-Jun-13 5
BH4000 Lay Duct 36 08-Apr-13 20-May-13 13-Apr-13 27-May-13 5
BH4010 Relocation of OFC 36 15-Apr-13 28-May-13 20-Apr-13 04-Jun-13 5
BH4020 ITS System 36 22-Apr-13 05-Jun-13 27-Apr-13 11-Jun-13 5
Bridge Widening (EB)Bridge Widening (EB) 286 15-Sep-12 30-Aug-13 20-Oct-12 05-Jul-14 250
BJ1000 Bridge Widening Start (EB) 0 15-Sep-12 20-Oct-12 29
BJ1010 Bridge Widening Finish (EB) 0 30-Aug-13 05-Jul-14 250
Bridge Extension Over Jalan Damansara (BR B.1)Bridge Extension Over Jalan Damansara (BR B.1) 238 14-Nov-12 30-Aug-13 19-Dec-12 21-Jun-14 238
Section 1 - East BoundSection 1 - East Bound 238 14-Nov-12 30-Aug-13 19-Dec-12 21-Jun-14 238
East AbutmentEast Abutment 52 03-Jan-13 06-Mar-13 29-Apr-13 01-Jul-13 97
BJ2140 Pile Cap Construction 18 03-Jan-13 23-Jan-13 29-Apr-13 20-May-13 97
BJ2150 Abutment Wall 16 25-Jan-13 13-Feb-13 21-May-13 10-Jun-13 97
BJ2160 Wing Wall & Curtail Wall 10 14-Feb-13 25-Feb-13 11-Jun-13 21-Jun-13 97
BJ2170 Approach Slab 8 26-Feb-13 06-Mar-13 22-Jun-13 01-Jul-13 97
Bridge DeckBridge Deck 40 21-Mar-13 07-May-13 16-Jul-13 04-Sep-13 97
BJ2410 Bridge Deck Construction 40 21-Mar-13 07-May-13 16-Jul-13 04-Sep-13 97
MiscellaneousMiscellaneous 106 23-Apr-13 30-Aug-13 21-Aug-13 21-Jun-14 238
BJ2420 Bridge Parapet, Lining to Abutment and Service Ducts 26 23-Apr-13 23-May-13 21-Aug-13 21-Sep-13 97
BJ2430 Installation of Movement Joints in Bridge Deck and Approach Slab 12 17-Aug-13 30-Aug-13 09-Jun-14 21-Jun-14 238
Precast BeamsPrecast Beams 12 07-Mar-13 20-Mar-13 02-Jul-13 15-Jul-13 97
BJ2400 Launching of Pre-tensioned Concrete Beams 12 07-Mar-13 20-Mar-13 02-Jul-13 15-Jul-13 97
PilingPiling 40 14-Nov-12 02-Jan-13 19-Dec-12 27-Apr-13 97
BJ2000 Temporary Sheet Piling 6 14-Nov-12 21-Nov-12 19-Dec-12 26-Dec-12 29
BJ2005 Bored Piling 26 01-Dec-12 02-Jan-13 29-Mar-13 27-Apr-13 97
West AbutmentWest Abutment 52 08-Dec-12 09-Feb-13 24-Apr-13 01-Jul-13 117
BJ2100 Pile Cap Construction 18 08-Dec-12 29-Dec-12 24-Apr-13 15-May-13 113
BJ2110 Abutment Wall 16 31-Dec-12 18-Jan-13 21-May-13 10-Jun-13 117
BJ2120 Wing Wall & Curtail Wall 10 19-Jan-13 31-Jan-13 11-Jun-13 21-Jun-13 117
BJ2130 Approach Slab 8 01-Feb-13 09-Feb-13 22-Jun-13 01-Jul-13 117
Pier 1Pier 1 48 11-Dec-12 07-Feb-13 04-May-13 01-Jul-13 119
BJ2200 Pile Cap Construction 22 11-Dec-12 07-Jan-13 04-May-13 30-May-13 119
BJ2210 Column Construction 26 08-Jan-13 07-Feb-13 31-May-13 01-Jul-13 119
Pier 2Pier 2 54 11-Dec-12 15-Feb-13 26-Apr-13 01-Jul-13 113
BJ2220 Pile Cap Construction 22 11-Dec-12 07-Jan-13 26-Apr-13 22-May-13 113
BJ2230 Column Construction 32 08-Jan-13 15-Feb-13 23-May-13 01-Jul-13 113
Pier 3Pier 3 62 15-Dec-12 01-Mar-13 17-Apr-13 01-Jul-13 101
BJ2240 Pile Cap Construction 22 15-Dec-12 11-Jan-13 17-Apr-13 13-May-13 101
BJ2250 Column Construction 40 12-Jan-13 01-Mar-13 14-May-13 01-Jul-13 101
Pier 4Pier 4 26 18-Dec-12 18-Jan-13 31-May-13 01-Jul-13 135
BJ2260 Pile Cap Construction 22 18-Dec-12 14-Jan-13 31-May-13 26-Jun-13 135
BJ2270 Column Construction 4 15-Jan-13 18-Jan-13 27-Jun-13 01-Jul-13 135
Pier 5Pier 5 48 20-Dec-12 18-Feb-13 04-May-13 01-Jul-13 111
BJ2280 Pile Cap Construction 22 20-Dec-12 16-Jan-13 04-May-13 30-May-13 111
BJ2290 Column Construction 26 17-Jan-13 18-Feb-13 31-May-13 01-Jul-13 111
Bridge Extension Over Segambut Dalam (BR B.2)Bridge Extension Over Segambut Dalam (BR B.2) 236 15-Oct-12 29-Jul-13 21-Nov-12 21-Jun-14 264
Section 1 - East BoundSection 1 - East Bound 236 15-Oct-12 29-Jul-13 21-Nov-12 21-Jun-14 264
PilingPiling 38 15-Oct-12 30-Nov-12 21-Nov-12 28-Mar-13 97
BJ3000 Temporary Sheet Piling 6 15-Oct-12 20-Oct-12 21-Nov-12 27-Nov-12 29
BJ3005 Bored Piling 26 30-Oct-12 30-Nov-12 27-Feb-13 28-Mar-13 97
West AbutmentWest Abutment 52 03-Nov-12 07-Jan-13 16-Apr-13 18-Jun-13 134
BJ3100 Pile Cap Construction 18 03-Nov-12 26-Nov-12 16-Apr-13 07-May-13 134
BJ3110 Abutment Wall 16 27-Nov-12 14-Dec-12 08-May-13 27-May-13 134
BJ3120 Wing Wall & Curtail Wall 10 15-Dec-12 27-Dec-12 28-May-13 08-Jun-13 134
BJ3130 Approach Slab 8 28-Dec-12 07-Jan-13 10-Jun-13 18-Jun-13 134
Pier 1Pier 1 48 08-Nov-12 07-Jan-13 20-Apr-13 18-Jun-13 134
BJ3180 Pile Cap Construction 22 08-Nov-12 05-Dec-12 20-Apr-13 16-May-13 134
BJ3190 Column Construction 26 06-Dec-12 07-Jan-13 17-May-13 18-Jun-13 134
Pier 2Pier 2 62 14-Nov-12 29-Jan-13 04-Apr-13 18-Jun-13 116
BJ3200 Pile Cap Construction 22 14-Nov-12 10-Dec-12 04-Apr-13 29-Apr-13 116
BJ3210 Column Construction 40 11-Dec-12 29-Jan-13 30-Apr-13 18-Jun-13 116
Pier 3Pier 3 62 20-Nov-12 02-Feb-13 04-Apr-13 18-Jun-13 112
BJ3220 Pile Cap Construction 22 20-Nov-12 14-Dec-12 04-Apr-13 29-Apr-13 112
BJ3230 Column Construction 40 15-Dec-12 02-Feb-13 30-Apr-13 18-Jun-13 112
Pier 4Pier 4 56 24-Nov-12 31-Jan-13 11-Apr-13 18-Jun-13 114
BJ3240 Pile Cap Construction 22 24-Nov-12 19-Dec-12 11-Apr-13 07-May-13 114
BJ3250 Column Construction 34 20-Dec-12 31-Jan-13 08-May-13 18-Jun-13 114
East AbutmentEast Abutment 52 01-Dec-12 02-Feb-13 16-Apr-13 18-Jun-13 112
BJ3140 Pile Cap Construction 18 01-Dec-12 21-Dec-12 16-Apr-13 07-May-13 112
BJ3150 Abutment Wall 16 22-Dec-12 11-Jan-13 08-May-13 27-May-13 112
BJ3160 Wing Wall & Curtail Wall 10 12-Jan-13 23-Jan-13 28-May-13 08-Jun-13 112
BJ3170 Approach Slab 8 25-Jan-13 02-Feb-13 10-Jun-13 18-Jun-13 112
Precast BeamsPrecast Beams 12 04-Feb-13 18-Feb-13 19-Jun-13 02-Jul-13 112
BJ3410 Launching of Post-tensioned Concrete Beams 12 04-Feb-13 18-Feb-13 19-Jun-13 02-Jul-13 112
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014
05-Jun-13, Telecommunication System
Lay Duct
Relocation of OFC
ITS System
30-Aug-13, Bridge Widening (EB)
Bridge Widening Start (EB)
Bridge Widening Finish (EB)
30-Aug-13, Bridge Extension Over Jalan Damansara (BR B.1)
30-Aug-13, Section 1 - East Bound
06-Mar-13, East Abutment
Pile Cap Construction
Abutment Wall
Wing Wall & Curtail Wall
Approach Slab
07-May-13, Bridge Deck
Bridge Deck Construction
30-Aug-13, Miscellaneous
Bridge Parapet, Lining to Abutment and Service Ducts
Installation of Movement Joints in Bridge Deck and Approach Slab
20-Mar-13, Precast Beams
Launching of Pre-tensioned Concrete Beams
02-Jan-13, Piling
Temporary Sheet Piling
Bored Piling
09-Feb-13, West Abutment
Pile Cap Construction
Abutment Wall
Wing Wall & Curtail Wall
Approach Slab
07-Feb-13, Pier 1
Pile Cap Construction
Column Construction
15-Feb-13, Pier 2
Pile Cap Construction
Column Construction
01-Mar-13, Pier 3
Pile Cap Construction
Column Construction
18-Jan-13, Pier 4
Pile Cap Construction
Column Construction
18-Feb-13, Pier 5
Pile Cap Construction
Column Construction
29-Jul-13, Bridge Extension Over Segambut Dalam (BR B.2)
29-Jul-13, Section 1 - East Bound
30-Nov-12, Piling
Temporary Sheet Piling
Bored Piling
07-Jan-13, West Abutment
Pile Cap Construction
Abutment Wall
Wing Wall & Curtail Wall
Approach Slab
07-Jan-13, Pier 1
Pile Cap Construction
Column Construction
29-Jan-13, Pier 2
Pile Cap Construction
Column Construction
02-Feb-13, Pier 3
Pile Cap Construction
Column Construction
31-Jan-13, Pier 4
Pile Cap Construction
Column Construction
02-Feb-13, East Abutment
Pile Cap Construction
Abutment Wall
Wing Wall & Curtail Wall
Approach Slab
18-Feb-13, Precast Beams
Launching of Post-tensioned Concrete Beams
NORTH-SOUTH EXPRESSWAY (PLUS)
PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Remaining Work
Critical Remaining Work
Milestone
Summary 5 of 13
WORK PROGRAMME
Date Revision Checked Approved
30-Jul-12 Rev.0
11-Sep-12 Rev.1
Activity ID Activity Name OriginalDuration
Early Start Early Finish Late Start Late Finish TotalFloat
Bridge DeckBridge Deck 40 19-Feb-13 05-Apr-13 03-Jul-13 21-Aug-13 112
BJ3420 Bridge Deck Construction 40 19-Feb-13 05-Apr-13 03-Jul-13 21-Aug-13 112
MiscellaneousMiscellaneous 106 23-Mar-13 29-Jul-13 06-Aug-13 21-Jun-14 264
BJ3430 Bridge Parapet, Lining to Abutment and Service Ducts 26 23-Mar-13 22-Apr-13 06-Aug-13 07-Sep-13 112
BJ3440 Installation of Movement Joints in Bridge Deck and Approach Slab 12 15-Jul-13 29-Jul-13 09-Jun-14 21-Jun-14 264
Extension of Viaduct at Edinburgh Estate (BR B.3)Extension of Viaduct at Edinburgh Estate (BR B.3) 268 15-Sep-12 07-Aug-13 20-Oct-12 14-Jun-14 250
Section 1 - East BoundSection 1 - East Bound 268 15-Sep-12 07-Aug-13 20-Oct-12 14-Jun-14 250
PilingPiling 36 15-Sep-12 29-Oct-12 20-Oct-12 26-Feb-13 97
BJ4000 Temporary Sheet Piling 6 15-Sep-12 22-Sep-12 20-Oct-12 27-Oct-12 29
BJ4005 Bored Piling 30 24-Sep-12 29-Oct-12 21-Jan-13 26-Feb-13 97
West AbutmentWest Abutment 58 01-Oct-12 10-Dec-12 13-Apr-13 22-Jun-13 160
BJ4100 Pile Cap Construction 22 01-Oct-12 25-Oct-12 13-Apr-13 09-May-13 160
BJ4110 Abutment Wall 18 27-Oct-12 19-Nov-12 10-May-13 31-May-13 160
BJ4120 Wing Wall & Curtail Wall 12 14-Nov-12 28-Nov-12 28-May-13 11-Jun-13 160
BJ4130 Approach Slab 10 29-Nov-12 10-Dec-12 12-Jun-13 22-Jun-13 160
Pier 1Pier 1 40 03-Oct-12 21-Nov-12 06-May-13 22-Jun-13 176
BJ4200 Pile Cap Construction 22 03-Oct-12 29-Oct-12 06-May-13 31-May-13 176
BJ4210 Column Construction 18 30-Oct-12 21-Nov-12 03-Jun-13 22-Jun-13 176
Pier 2Pier 2 48 05-Oct-12 03-Dec-12 25-Apr-13 22-Jun-13 166
BJ4220 Pile Cap Construction 22 05-Oct-12 31-Oct-12 25-Apr-13 21-May-13 166
BJ4230 Column Construction 26 01-Nov-12 03-Dec-12 22-May-13 22-Jun-13 166
Pier 3Pier 3 58 08-Oct-12 17-Dec-12 13-Apr-13 22-Jun-13 154
BJ4240 Pile Cap Construction 22 08-Oct-12 02-Nov-12 13-Apr-13 09-May-13 154
BJ4250 Column Construction 36 03-Nov-12 17-Dec-12 10-May-13 22-Jun-13 154
Pier 4Pier 4 68 10-Oct-12 02-Jan-13 02-Apr-13 22-Jun-13 142
BJ4260 Pile Cap Construction 22 10-Oct-12 05-Nov-12 02-Apr-13 26-Apr-13 142
BJ4270 Column Construction 46 06-Nov-12 02-Jan-13 27-Apr-13 22-Jun-13 142
Pier 5Pier 5 68 12-Oct-12 04-Jan-13 02-Apr-13 22-Jun-13 140
BJ4280 Pile Cap Construction 22 12-Oct-12 07-Nov-12 02-Apr-13 26-Apr-13 140
BJ4290 Column Construction 46 08-Nov-12 04-Jan-13 27-Apr-13 22-Jun-13 140
Pier 6Pier 6 68 15-Oct-12 07-Jan-13 02-Apr-13 22-Jun-13 138
BJ4300 Pile Cap Construction 22 15-Oct-12 09-Nov-12 02-Apr-13 26-Apr-13 138
BJ4310 Column Construction 46 10-Nov-12 07-Jan-13 27-Apr-13 22-Jun-13 138
Pier 7Pier 7 72 17-Oct-12 14-Jan-13 28-Mar-13 22-Jun-13 132
BJ4320 Pile Cap Construction 22 17-Oct-12 12-Nov-12 28-Mar-13 22-Apr-13 132
BJ4330 Column Construction 50 14-Nov-12 14-Jan-13 23-Apr-13 22-Jun-13 132
Pier 8Pier 8 72 19-Oct-12 16-Jan-13 28-Mar-13 22-Jun-13 130
BJ4340 Pile Cap Construction 22 19-Oct-12 16-Nov-12 28-Mar-13 22-Apr-13 130
BJ4350 Column Construction 50 17-Nov-12 16-Jan-13 23-Apr-13 22-Jun-13 130
Pier 9Pier 9 58 22-Oct-12 02-Jan-13 13-Apr-13 22-Jun-13 142
BJ4360 Pile Cap Construction 22 22-Oct-12 19-Nov-12 13-Apr-13 09-May-13 142
BJ4370 Column Construction 36 20-Nov-12 02-Jan-13 10-May-13 22-Jun-13 142
Pier 10Pier 10 48 24-Oct-12 21-Dec-12 25-Apr-13 22-Jun-13 150
BJ4380 Pile Cap Construction 22 24-Oct-12 21-Nov-12 25-Apr-13 21-May-13 150
BJ4390 Column Construction 26 22-Nov-12 21-Dec-12 22-May-13 22-Jun-13 150
East AbutmentEast Abutment 58 30-Oct-12 09-Jan-13 13-Apr-13 22-Jun-13 136
BJ4150 Pile Cap Construction 22 30-Oct-12 26-Nov-12 13-Apr-13 09-May-13 136
BJ4160 Abutment Wall 18 27-Nov-12 17-Dec-12 10-May-13 31-May-13 136
BJ4170 Wing Wall & Curtail Wall 12 13-Dec-12 27-Dec-12 28-May-13 11-Jun-13 136
BJ4180 Approach Slab 10 28-Dec-12 09-Jan-13 12-Jun-13 22-Jun-13 136
Precast BeamsPrecast Beams 16 17-Jan-13 05-Feb-13 24-Jun-13 11-Jul-13 130
BJ4400 Launching of Post-tensioned Concrete Beams 16 17-Jan-13 05-Feb-13 24-Jun-13 11-Jul-13 130
Bridge DeckBridge Deck 46 06-Feb-13 01-Apr-13 12-Jul-13 07-Sep-13 130
BJ4410 Bridge Deck Construction 46 06-Feb-13 01-Apr-13 12-Jul-13 07-Sep-13 130
MiscellaneousMiscellaneous 118 19-Mar-13 07-Aug-13 24-Aug-13 14-Jun-14 250
BJ4420 Bridge Parapet, Lining to Abutment and Service Ducts 32 19-Mar-13 24-Apr-13 24-Aug-13 02-Oct-13 130
BJ4430 Installation of Movement Joints in Bridge Deck and Approach Slab 18 17-Jul-13 07-Aug-13 24-May-14 14-Jun-14 250
Slope Improvement Works (EB)Slope Improvement Works (EB) 173 01-Oct-12 27-Apr-13 08-Dec-12 05-Jul-14 351
BL0010 Slope Improvement Works Start (EB) 0 01-Oct-12 08-Dec-12 56
BL0020 Slope Improvement Works Finish (EB) 0 27-Apr-13 05-Jul-14 351
Overall Stage 1Overall Stage 1 173 01-Oct-12 27-Apr-13 08-Dec-12 04-Apr-14 275
Fill AreaFill Area 40 13-Mar-13 27-Apr-13 18-Feb-14 04-Apr-14 275
Slope Improvement - Retaining Wall (CH.4300-CH.4540)Slope Improvement - Retaining Wall (CH.4300-CH.4540) 40 13-Mar-13 27-Apr-13 18-Feb-14 04-Apr-14 275
BL2300 Excavation 26 13-Mar-13 11-Apr-13 18-Feb-14 19-Mar-14 275
BL2320 Construction of Wall Base 26 20-Mar-13 18-Apr-13 25-Feb-14 26-Mar-14 275
BL2330 Construction of Retaining Wall 26 25-Mar-13 23-Apr-13 01-Mar-14 31-Mar-14 275
BL2340 Backfill 26 29-Mar-13 27-Apr-13 06-Mar-14 04-Apr-14 275
Cut AreaCut Area 172 01-Oct-12 26-Apr-13 08-Dec-12 04-Jul-13 56
Slope Improvement - Horizontal DrainSlope Improvement - Horizontal Drain 172 01-Oct-12 26-Apr-13 08-Dec-12 04-Jul-13 56
BL1000 Installation of Horizontal Drain (CH.0-CH.1400) 43 01-Oct-12 22-Nov-12 08-Dec-12 30-Jan-13 56
BL1010 Installation of Horizontal Drain (CH.1400-CH.2800) 43 23-Nov-12 14-Jan-13 31-Jan-13 22-Mar-13 56
BL1020 Installation of Horizontal Drain (CH.2800-CH.4200) 43 15-Jan-13 07-Mar-13 23-Mar-13 13-May-13 56
BL1030 Installation of Horizontal Drain (CH.4200-CH.5600) 43 08-Mar-13 26-Apr-13 14-May-13 04-Jul-13 56
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014
05-Apr-13, Bridge Deck
Bridge Deck Construction
29-Jul-13, Miscellaneous
Bridge Parapet, Lining to Abutment and Service Ducts
Installation of Movement Joints in Bridge Deck and Approach Slab
07-Aug-13, Extension of Viaduct at Edinburgh Estate (BR B.3)
07-Aug-13, Section 1 - East Bound
29-Oct-12, Piling
Temporary Sheet Piling
Bored Piling
10-Dec-12, West Abutment
Pile Cap Construction
Abutment Wall
Wing Wall & Curtail Wall
Approach Slab
21-Nov-12, Pier 1
Pile Cap Construction
Column Construction
03-Dec-12, Pier 2
Pile Cap Construction
Column Construction
17-Dec-12, Pier 3
Pile Cap Construction
Column Construction
02-Jan-13, Pier 4
Pile Cap Construction
Column Construction
04-Jan-13, Pier 5
Pile Cap Construction
Column Construction
07-Jan-13, Pier 6
Pile Cap Construction
Column Construction
14-Jan-13, Pier 7
Pile Cap Construction
Column Construction
16-Jan-13, Pier 8
Pile Cap Construction
Column Construction
02-Jan-13, Pier 9
Pile Cap Construction
Column Construction
21-Dec-12, Pier 10
Pile Cap Construction
Column Construction
09-Jan-13, East Abutment
Pile Cap Construction
Abutment Wall
Wing Wall & Curtail Wall
Approach Slab
05-Feb-13, Precast Beams
Launching of Post-tensioned Concrete Beams
01-Apr-13, Bridge Deck
Bridge Deck Construction
07-Aug-13, Miscellaneous
Bridge Parapet, Lining to Abutment and Service Ducts
Installation of Movement Joints in Bridge Deck and Approach Slab
27-Apr-13, Slope Improvement Works (EB)
Slope Improvement Works Start (EB)
Slope Improvement Works Finish (EB)
27-Apr-13, Overall Stage 1
27-Apr-13, Fill Area
27-Apr-13, Slope Improvement - Retaining Wall (CH.4300-CH.4540)
Excavation
Construction of Wall Base
Construction of Retaining Wall
Backfill
26-Apr-13, Cut Area
26-Apr-13, Slope Improvement - Horizontal Drain
Installation of Horizontal Drain (CH.0-CH.1400)
Installation of Horizontal Drain (CH.1400-CH.2800)
Installation of Horizontal Drain (CH.2800-CH.4200)
Installation of Horizontal Drain (CH.4200-CH.5600)
NORTH-SOUTH EXPRESSWAY (PLUS)
PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Remaining Work
Critical Remaining Work
Milestone
Summary 6 of 13
WORK PROGRAMME
Date Revision Checked Approved
30-Jul-12 Rev.0
11-Sep-12 Rev.1
Activity ID Activity Name OriginalDuration
Early Start Early Finish Late Start Late Finish TotalFloat
Ground Treatment Works (EB)Ground Treatment Works (EB) 168 07-Sep-12 30-Mar-13 13-Sep-12 05-Jul-14 375
BM0010 Ground Treatment Works Start (EB) 0 07-Sep-12 13-Sep-12 5
BM0020 Ground Treatment Works Finish (EB) 0 30-Mar-13 05-Jul-14 375
Stage 1Stage 1 168 07-Sep-12 30-Mar-13 13-Sep-12 20-May-13 42
Ground Treatment (CH.4200-CH.5600)Ground Treatment (CH.4200-CH.5600) 42 09-Feb-13 30-Mar-13 01-Apr-13 20-May-13 42
BM1300 Excavation of Unsuitable Material 30 09-Feb-13 16-Mar-13 01-Apr-13 06-May-13 42
BM1310 Laying of Geotextile Separator 30 15-Feb-13 21-Mar-13 05-Apr-13 10-May-13 42
BM1320 Laying of Outlet Drain 30 20-Feb-13 26-Mar-13 10-Apr-13 15-May-13 42
BM1330 Backfilling with Compacted Soil / hardcore Material 30 25-Feb-13 30-Mar-13 15-Apr-13 20-May-13 42
Ground Treatment (CH.1400-CH.2800)Ground Treatment (CH.1400-CH.2800) 42 29-Oct-12 18-Dec-12 19-Dec-12 08-Feb-13 42
BM1100 Excavation of Unsuitable Material 30 29-Oct-12 04-Dec-12 19-Dec-12 25-Jan-13 42
BM1110 Laying of Geotextile Separator 30 02-Nov-12 08-Dec-12 24-Dec-12 30-Jan-13 42
BM1120 Laying of Outlet Drain 30 07-Nov-12 13-Dec-12 29-Dec-12 04-Feb-13 42
BM1130 Backfilling with Compacted Soil / hardcore Material 30 12-Nov-12 18-Dec-12 04-Jan-13 08-Feb-13 42
Ground Treatment (CH.2800-CH.4200)Ground Treatment (CH.2800-CH.4200) 42 19-Dec-12 08-Feb-13 09-Feb-13 30-Mar-13 42
BM1200 Excavation of Unsuitable Material 30 19-Dec-12 25-Jan-13 09-Feb-13 16-Mar-13 42
BM1210 Laying of Geotextile Separator 30 24-Dec-12 30-Jan-13 15-Feb-13 21-Mar-13 42
BM1220 Laying of Outlet Drain 30 29-Dec-12 04-Feb-13 20-Feb-13 26-Mar-13 42
BM1230 Backfilling with Compacted Soil / hardcore Material 30 04-Jan-13 08-Feb-13 25-Feb-13 30-Mar-13 42
Ground Treatment (CH.0-CH.1400)Ground Treatment (CH.0-CH.1400) 42 07-Sep-12 27-Oct-12 13-Sep-12 02-Nov-12 5
BM1000 Excavation of Unsuitable Material 30 07-Sep-12 12-Oct-12 13-Sep-12 18-Oct-12 5
BM1010 Laying of Geotextile Separator 30 12-Sep-12 17-Oct-12 19-Sep-12 23-Oct-12 5
BM1020 Laying of Outlet Drain 30 18-Sep-12 22-Oct-12 24-Sep-12 29-Oct-12 5
BM1030 Backfilling with Compacted Soil / hardcore Material 30 22-Sep-12 27-Oct-12 28-Sep-12 02-Nov-12 5
Electrical Works for Street Lighting (EB)Electrical Works for Street Lighting (EB) 219 05-Jan-13 28-Sep-13 09-Oct-13 05-Jul-14 227
BN0010 Electrical Works for Street Lighting Start (EB) 0 05-Jan-13 09-Oct-13 227
BN0020 Electrical Works for Street Lighting Finish (EB) 0 28-Sep-13 05-Jul-14 227
Overall Stage 1Overall Stage 1 219 05-Jan-13 28-Sep-13 09-Oct-13 05-Jul-14 227
BN0100 Testing and Commissioning 60 16-Jul-13 28-Sep-13 24-Apr-14 05-Jul-14 227
CH.1400-CH.2800CH.1400-CH.2800 37 20-Feb-13 03-Apr-13 25-Nov-13 09-Jan-14 227
BN1100 High Mast 37 20-Feb-13 03-Apr-13 25-Nov-13 09-Jan-14 227
BN1110 Street Lighting 37 20-Feb-13 03-Apr-13 25-Nov-13 09-Jan-14 227
CH.0-CH.1400CH.0-CH.1400 37 05-Jan-13 19-Feb-13 09-Oct-13 23-Nov-13 227
BN1000 High Mast 37 05-Jan-13 19-Feb-13 09-Oct-13 23-Nov-13 227
BN1010 Street Lighting 37 05-Jan-13 19-Feb-13 09-Oct-13 23-Nov-13 227
CH.2800-CH.4200CH.2800-CH.4200 37 04-Apr-13 17-May-13 10-Jan-14 26-Feb-14 227
BN1200 High Mast 37 04-Apr-13 17-May-13 10-Jan-14 26-Feb-14 227
BN1210 Street Lighting 37 04-Apr-13 17-May-13 10-Jan-14 26-Feb-14 227
CH.4200-CH.5600CH.4200-CH.5600 37 18-May-13 02-Jul-13 27-Feb-14 10-Apr-14 227
BN1300 High Mast 37 18-May-13 02-Jul-13 27-Feb-14 10-Apr-14 227
BN1310 Street Lighting 37 18-May-13 02-Jul-13 27-Feb-14 10-Apr-14 227
Phase 2 (West Bound)Phase 2 (West Bound) 370 01-Apr-13 01-Jul-14 01-Apr-13 05-Jul-14 5
Site Clearance and Fencing (WB)Site Clearance and Fencing (WB) 370 01-Apr-13 01-Jul-14 01-Apr-13 05-Jul-14 5
BC3000 Site Clearance and Fencing Start (WB) 0 01-Apr-13 05-Jul-14 375
BC3010 Site Clearance and Fencing Finish (WB) 0 01-Jul-14 05-Jul-14 5
Site Clearing and Fencing (CH.4200-CH.2800)Site Clearing and Fencing (CH.4200-CH.2800) 242 04-Jun-13 29-Mar-14 21-Jun-13 04-Apr-14 5
BC2100 Site Clearing & Demolition Works 52 04-Jun-13 03-Aug-13 21-Jun-13 23-Aug-13 15
BC2110 Demolition Works 38 20-Jun-13 03-Aug-13 13-Aug-13 27-Sep-13 43
BC2120 Relocation & Installation of Temporary Signage & Gantry 38 20-Jun-13 03-Aug-13 20-Feb-14 04-Apr-14 195
BC2130 Fencing and Gate 38 13-Feb-14 29-Mar-14 20-Feb-14 04-Apr-14 5
BC2140 Miscellaneous Dismantling, Demolition and Excavation 38 20-Jun-13 03-Aug-13 20-Feb-14 04-Apr-14 195
Site Clearing and Fencing (CH.5600-CH.4200)Site Clearing and Fencing (CH.5600-CH.4200) 256 01-Apr-13 12-Feb-14 01-Apr-13 19-Feb-14 5
BC2000 Site Clearing & Demolition Works 52 01-Apr-13 03-Jun-13 01-Apr-13 03-Jun-13 0
BC2010 Demolition Works 38 17-Apr-13 03-Jun-13 26-Jun-13 12-Aug-13 57
BC2020 Relocation & Installation of Temporary Signage & Gantry 38 17-Apr-13 03-Jun-13 02-Jan-14 19-Feb-14 209
BC2030 Fencing and Gate 38 26-Dec-13 12-Feb-14 02-Jan-14 19-Feb-14 5
BC2040 Miscellaneous Dismantling, Demolition and Excavation 38 17-Apr-13 03-Jun-13 02-Jan-14 19-Feb-14 209
Site Clearing and Fencing (CH.2800-CH.1400)Site Clearing and Fencing (CH.2800-CH.1400) 228 05-Aug-13 15-May-14 24-Aug-13 21-May-14 5
BC2200 Site Clearing & Demolition Works 52 05-Aug-13 08-Oct-13 24-Aug-13 26-Oct-13 15
BC2210 Demolition Works 38 23-Aug-13 08-Oct-13 28-Sep-13 14-Nov-13 29
BC2220 Relocation & Installation of Temporary Signage & Gantry 38 23-Aug-13 08-Oct-13 05-Apr-14 21-May-14 181
BC2230 Fencing and Gate 38 31-Mar-14 15-May-14 05-Apr-14 21-May-14 5
BC2240 Miscellaneous Dismantling, Demolition and Excavation 38 23-Aug-13 08-Oct-13 05-Apr-14 21-May-14 181
Site Clearing and Fencing (CH.1400-CH.0)Site Clearing and Fencing (CH.1400-CH.0) 214 09-Oct-13 30-Jun-14 28-Oct-13 05-Jul-14 5
BC2300 Site Clearing & Demolition Works 52 09-Oct-13 12-Dec-13 28-Oct-13 31-Dec-13 15
BC2310 Demolition Works 38 26-Oct-13 12-Dec-13 15-Nov-13 31-Dec-13 15
BC2320 Relocation & Installation of Temporary Signage & Gantry 38 26-Oct-13 12-Dec-13 15-Nov-13 31-Dec-13 15
BC2330 Fencing and Gate 38 16-May-14 30-Jun-14 22-May-14 05-Jul-14 5
BC2340 Miscellaneous Dismantling, Demolition and Excavation 38 26-Oct-13 12-Dec-13 22-May-14 05-Jul-14 167
Earthworks (WB)Earthworks (WB) 341 02-May-13 26-Jun-14 02-May-13 05-Jul-14 8
BD6500 Earthwork Start (WB) 0 02-May-13 05-Jul-14 349
BD6510 Earthwork Finish (WB) 0 26-Jun-14 05-Jul-14 8
Stage 2Stage 2 133 16-Jan-14 26-Jun-14 16-Jan-14 05-Jul-14 8
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014
30-Mar-13, Ground Treatment Works (EB)
Ground Treatment Works Start (EB)
Ground Treatment Works Finish (EB)
30-Mar-13, Stage 1
30-Mar-13, Ground Treatment (CH.4200-CH.5600)
Excavation of Unsuitable Material
Laying of Geotextile Separator
Laying of Outlet Drain
Backfilling with Compacted Soil / hardcore Material
18-Dec-12, Ground Treatment (CH.1400-CH.2800)
Excavation of Unsuitable Material
Laying of Geotextile Separator
Laying of Outlet Drain
Backfilling with Compacted Soil / hardcore Material
08-Feb-13, Ground Treatment (CH.2800-CH.4200)
Excavation of Unsuitable Material
Laying of Geotextile Separator
Laying of Outlet Drain
Backfilling with Compacted Soil / hardcore Material
27-Oct-12, Ground Treatment (CH.0-CH.1400)
Excavation of Unsuitable Material
Laying of Geotextile Separator
Laying of Outlet Drain
Backfilling with Compacted Soil / hardcore Material
28-Sep-13, Electrical Works for Street Lighting (EB)
Electrical Works for Street Lighting Start (EB)
Electrical Works for Street Lighting Finish (EB)
28-Sep-13, Overall Stage 1
Testing and Commissioning
03-Apr-13, CH.1400-CH.2800
High Mast
Street Lighting
19-Feb-13, CH.0-CH.1400
High Mast
Street Lighting
17-May-13, CH.2800-CH.4200
High Mast
Street Lighting
02-Jul-13, CH.4200-CH.5600
High Mast
Street Lighting
01-Jul-14, Phase 2 (West Bound)
01-Jul-14, Site Clearance and Fencing (WB)
Site Clearance and Fencing Start (WB)
Site Clearance and Fencing Finish (WB)
29-Mar-14, Site Clearing and Fencing (CH.4200-CH.2800)
Site Clearing & Demolition Works
Demolition Works
Relocation & Installation of Temporary Signage & Gantry
Fencing and Gate
Miscellaneous Dismantling, Demolition and Excavation
12-Feb-14, Site Clearing and Fencing (CH.5600-CH.4200)
Site Clearing & Demolition Works
Demolition Works
Relocation & Installation of Temporary Signage & Gantry
Fencing and Gate
Miscellaneous Dismantling, Demolition and Excavation
15-May-14, Site Clearing and Fencing (CH.2800-CH.1400)
Site Clearing & Demolition Works
Demolition Works
Relocation & Installation of Temporary Signage & Gantry
Fencing and Gate
Miscellaneous Dismantling, Demolition and Excavation
30-Jun-14, Site Clearing and Fencing (CH.1400-CH.0)
Site Clearing & Demolition Works
Demolition Works
Relocation & Installation of Temporary Signage & Gantry
Fencing and Gate
Miscellaneous Dismantling, Demolition and Excavation
26-Jun-14, Earthworks (WB)
Earthwork Start (WB)
Earthwork Finish (WB)
26-Jun-14, Stage 2
NORTH-SOUTH EXPRESSWAY (PLUS)
PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Remaining Work
Critical Remaining Work
Milestone
Summary 7 of 13
WORK PROGRAMME
Date Revision Checked Approved
30-Jul-12 Rev.0
11-Sep-12 Rev.1
Activity ID Activity Name OriginalDuration
Early Start Early Finish Late Start Late Finish TotalFloat
CH.4200-CH.2800CH.4200-CH.2800 42 26-Feb-14 15-Apr-14 05-Mar-14 24-Apr-14 8
BD7100 Removal of Existing Pavement 32 26-Feb-14 03-Apr-14 05-Mar-14 10-Apr-14 6
BD7110 Turf ing (Remaining Works) 32 10-Mar-14 15-Apr-14 19-Mar-14 24-Apr-14 8
BD7120 Treatment of Existing Subsoil Drain 32 04-Mar-14 09-Apr-14 19-Mar-14 24-Apr-14 13
CH.2800-CH.1400CH.2800-CH.1400 42 04-Apr-14 24-May-14 11-Apr-14 04-Jun-14 8
BD7200 Removal of Existing Pavement 32 04-Apr-14 12-May-14 11-Apr-14 20-May-14 6
BD7210 Turf ing (Remaining Works) 32 16-Apr-14 24-May-14 25-Apr-14 04-Jun-14 8
BD7220 Treatment of Existing Subsoil Drain 32 10-Apr-14 19-May-14 25-Apr-14 04-Jun-14 13
CH.5600-CH.4200CH.5600-CH.4200 42 16-Jan-14 08-Mar-14 16-Jan-14 18-Mar-14 8
BD7000 Removal of Existing Pavement 32 16-Jan-14 25-Feb-14 16-Jan-14 25-Feb-14 0
BD7010 Turf ing (Remaining Works) 32 28-Jan-14 08-Mar-14 08-Feb-14 18-Mar-14 8
BD7020 Treatment of Existing Subsoil Drain 32 22-Jan-14 03-Mar-14 03-Feb-14 12-Mar-14 8
CH.1400-CH.0CH.1400-CH.0 37 14-May-14 26-Jun-14 21-May-14 05-Jul-14 8
BD7300 Removal of Existing Pavement 27 14-May-14 14-Jun-14 21-May-14 21-Jun-14 6
BD7310 Turf ing (Remaining Works) 27 26-May-14 26-Jun-14 05-Jun-14 05-Jul-14 8
BD7320 Treatment of Existing Subsoil Drain 27 20-May-14 20-Jun-14 05-Jun-14 05-Jul-14 13
Stage 1Stage 1 233 02-May-13 17-Feb-14 02-May-13 05-Jul-14 116
CH.5600-CH.4200CH.5600-CH.4200 77 02-May-13 02-Aug-13 02-May-13 26-Dec-13 116
BD6000 Excavate to Toe of Slope (CH.5600-CH.4200) 52 02-May-13 03-Jul-13 02-May-13 03-Jul-13 0
BD6010 Fill to Formation Level (CH.5600-CH.4200) 52 22-May-13 23-Jul-13 29-May-13 30-Jul-13 5
BD6020 Turf ing 52 03-Jun-13 02-Aug-13 18-Jun-13 20-Aug-13 13
BD6030 Instrumentation and Monitoring 58 22-May-13 31-Jul-13 16-Oct-13 26-Dec-13 118
BD6040 Soil Investigation 52 02-May-13 03-Jul-13 23-Oct-13 26-Dec-13 141
CH.2800-CH.1400CH.2800-CH.1400 77 07-Sep-13 10-Dec-13 07-Sep-13 03-May-14 116
BD6200 Excavate to Toe of Slope (CH.2800-CH.1400) 52 07-Sep-13 11-Nov-13 07-Sep-13 11-Nov-13 0
BD6210 Fill to Formation Level (CH.2800-CH.1400) 52 28-Sep-13 30-Nov-13 14-Oct-13 17-Dec-13 13
BD6220 Turf ing 52 08-Oct-13 10-Dec-13 24-Oct-13 27-Dec-13 13
BD6230 Instrumentation and Monitoring 58 28-Sep-13 07-Dec-13 25-Feb-14 03-May-14 118
BD6240 Soil Investigation 52 07-Sep-13 11-Nov-13 04-Mar-14 03-May-14 141
CH.4200-CH.2800CH.4200-CH.2800 77 04-Jul-13 07-Oct-13 04-Jul-13 03-Mar-14 116
BD6100 Excavate to Toe of Slope (CH.4200-CH.2800) 52 04-Jul-13 06-Sep-13 04-Jul-13 06-Sep-13 0
BD6110 Fill to Formation Level (CH.4200-CH.2800) 52 24-Jul-13 27-Sep-13 12-Aug-13 12-Oct-13 13
BD6120 Turf ing 52 03-Aug-13 07-Oct-13 21-Aug-13 23-Oct-13 13
BD6130 Instrumentation and Monitoring 58 24-Jul-13 04-Oct-13 19-Dec-13 03-Mar-14 118
BD6140 Soil Investigation 52 04-Jul-13 06-Sep-13 27-Dec-13 03-Mar-14 141
CH.1400-CH.0CH.1400-CH.0 77 12-Nov-13 17-Feb-14 12-Nov-13 05-Jul-14 116
BD6300 Excavate to Toe of Slope (CH.1400-CH.0) 52 12-Nov-13 15-Jan-14 12-Nov-13 15-Jan-14 0
BD6310 Fill to Formation Level (CH.1400-CH.0) 52 02-Dec-13 06-Feb-14 18-Dec-13 22-Feb-14 13
BD6320 Turf ing 52 12-Dec-13 17-Feb-14 28-Dec-13 04-Mar-14 13
BD6330 Instrumentation and Monitoring 58 02-Dec-13 13-Feb-14 26-Apr-14 05-Jul-14 118
BD6340 Soil Investigation 52 12-Nov-13 15-Jan-14 05-May-14 05-Jul-14 141
Drainage Works (WB)Drainage Works (WB) 318 04-Jun-13 30-Jun-14 10-Jun-13 05-Jul-14 5
BE4040 Drainage Works Start (WB) 0 04-Jun-13 05-Jul-14 323
BE4050 Drainage Works Finish (WB) 0 30-Jun-14 05-Jul-14 5
Stage 1Stage 1 188 04-Jun-13 22-Jan-14 10-Jun-13 28-Jan-14 5
Drainage (CH.5600-CH.4200)Drainage (CH.5600-CH.4200) 47 04-Jun-13 29-Jul-13 10-Jun-13 03-Aug-13 5
BE2000 Excavation 33 04-Jun-13 11-Jul-13 10-Jun-13 17-Jul-13 5
BE2010 Laying of Drain 33 12-Jun-13 19-Jul-13 18-Jun-13 26-Jul-13 5
BE2020 Backfilling 33 20-Jun-13 29-Jul-13 26-Jun-13 03-Aug-13 5
Drainage (CH.4200-CH.2800)Drainage (CH.4200-CH.2800) 47 30-Jul-13 26-Sep-13 05-Aug-13 02-Oct-13 5
BE2100 Excavation 33 30-Jul-13 09-Sep-13 05-Aug-13 14-Sep-13 5
BE2110 Laying of Drain 33 07-Aug-13 18-Sep-13 15-Aug-13 24-Sep-13 5
BE2120 Backfilling 33 17-Aug-13 26-Sep-13 23-Aug-13 02-Oct-13 5
Drainage (CH.2800-CH.1400)Drainage (CH.2800-CH.1400) 47 27-Sep-13 23-Nov-13 03-Oct-13 29-Nov-13 5
BE2200 Excavation 33 27-Sep-13 07-Nov-13 03-Oct-13 13-Nov-13 5
BE2210 Laying of Drain 33 05-Oct-13 15-Nov-13 11-Oct-13 21-Nov-13 5
BE2220 Backfilling 33 14-Oct-13 23-Nov-13 21-Oct-13 29-Nov-13 5
Drainage (CH.1400-CH.0)Drainage (CH.1400-CH.0) 47 25-Nov-13 22-Jan-14 30-Nov-13 28-Jan-14 5
BE2300 Excavation 33 25-Nov-13 04-Jan-14 30-Nov-13 10-Jan-14 5
BE2310 Laying of Drain 33 03-Dec-13 13-Jan-14 09-Dec-13 20-Jan-14 5
BE2320 Backfilling 33 12-Dec-13 22-Jan-14 18-Dec-13 28-Jan-14 5
Stage 2Stage 2 130 23-Jan-14 30-Jun-14 29-Jan-14 05-Jul-14 5
Drains (Remaining Works) and KerbsDrains (Remaining Works) and Kerbs 130 23-Jan-14 30-Jun-14 29-Jan-14 05-Jul-14 5
BE4000 CH.5600-CH.4200 32 23-Jan-14 04-Mar-14 29-Jan-14 10-Mar-14 5
BE4010 CH.4200-CH.2800 32 05-Mar-14 10-Apr-14 11-Mar-14 16-Apr-14 5
BE4020 CH.2800-CH.1400 33 11-Apr-14 21-May-14 17-Apr-14 27-May-14 5
BE4030 CH.1400-CH.0 33 22-May-14 30-Jun-14 28-May-14 05-Jul-14 5
Sub-Base, Roadbase and Pavement (WB)Sub-Base, Roadbase and Pavement (WB) 143 06-Jan-14 28-Jun-14 27-Jan-14 05-Jul-14 6
BF3020 Sub-Base, Roadbase and Pavement Start (WB) 0 06-Jan-14 05-Jul-14 149
BF3030 Sub-Base, Roadbase and Pavement Finish (WB) 0 28-Jun-14 05-Jul-14 6
Stage 2Stage 2 143 06-Jan-14 28-Jun-14 27-Jan-14 05-Jul-14 6
BF3010 Sub-surface Drainage Improvement (West Bound) 130 06-Jan-14 13-Jun-14 29-Jan-14 05-Jul-14 19
Sub-Base upto Pavement (CH.5600-CH.4200)Sub-Base upto Pavement (CH.5600-CH.4200) 38 27-Jan-14 14-Mar-14 27-Jan-14 18-Apr-14 30
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014
15-Apr-14, CH.4200-CH.2800
Removal of Existing Pavement
Turf ing (Remaining Works)
Treatment of Existing Subsoil Drain
24-May-14, CH.2800-CH.1400
Removal of Existing Pavement
Turf ing (Remaining Works)
Treatment of Existing Subsoil Drain
08-Mar-14, CH.5600-CH.4200
Removal of Existing Pavement
Turfing (Remaining Works)
Treatment of Existing Subsoil Drain
26-Jun-14, CH.1400-CH.0
Removal of Existing Pavement
Turf ing (Remaining Works)
Treatment of Existing Subsoil Drain
17-Feb-14, Stage 1
02-Aug-13, CH.5600-CH.4200
Excavate to Toe of Slope (CH.5600-CH.4200)
Fill to Formation Level (CH.5600-CH.4200)
Turf ing
Instrumentation and Monitoring
Soil Investigation
10-Dec-13, CH.2800-CH.1400
Excavate to Toe of Slope (CH.2800-CH.1400)
Fill to Formation Level (CH.2800-CH.1400)
Turfing
Instrumentation and Monitoring
Soil Investigation
07-Oct-13, CH.4200-CH.2800
Excavate to Toe of Slope (CH.4200-CH.2800)
Fill to Formation Level (CH.4200-CH.2800)
Turfing
Instrumentation and Monitoring
Soil Investigation
17-Feb-14, CH.1400-CH.0
Excavate to Toe of Slope (CH.1400-CH.0)
Fill to Formation Level (CH.1400-CH.0)
Turf ing
Instrumentation and Monitoring
Soil Investigation
30-Jun-14, Drainage Works (WB)
Drainage Works Start (WB)
Drainage Works Finish (WB)
22-Jan-14, Stage 1
29-Jul-13, Drainage (CH.5600-CH.4200)
Excavation
Laying of Drain
Backfilling
26-Sep-13, Drainage (CH.4200-CH.2800)
Excavation
Laying of Drain
Backfilling
23-Nov-13, Drainage (CH.2800-CH.1400)
Excavation
Laying of Drain
Backfilling
22-Jan-14, Drainage (CH.1400-CH.0)
Excavation
Laying of Drain
Backfilling
30-Jun-14, Stage 2
30-Jun-14, Drains (Remaining Works) and Kerbs
CH.5600-CH.4200
CH.4200-CH.2800
CH.2800-CH.1400
CH.1400-CH.0
28-Jun-14, Sub-Base, Roadbase and Pavement (WB)
Sub-Base, Roadbase and Pavement Start (WB)
Sub-Base, Roadbase and Pavement Finish (WB)
28-Jun-14, Stage 2
Sub-surface Drainage Improvement (West Bound)
14-Mar-14, Sub-Base upto Pavement (CH.5600-CH.4200)
NORTH-SOUTH EXPRESSWAY (PLUS)
PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Remaining Work
Critical Remaining Work
Milestone
Summary 8 of 13
WORK PROGRAMME
Date Revision Checked Approved
30-Jul-12 Rev.0
11-Sep-12 Rev.1
Activity ID Activity Name OriginalDuration
Early Start Early Finish Late Start Late Finish TotalFloat
BF2010 Sub-Grade and Prepare Formation 24 27-Jan-14 26-Feb-14 27-Jan-14 26-Feb-14 0
BF2020 Laying of Lower Sub-Base 24 29-Jan-14 28-Feb-14 29-Jan-14 28-Feb-14 0
BF2030 Laying of Lower Upper-Base 24 03-Feb-14 03-Mar-14 03-Feb-14 03-Mar-14 0
BF2040 Laying of CBM 22 05-Feb-14 03-Mar-14 05-Feb-14 03-Mar-14 0
BF2050 Laying of WMM 22 07-Feb-14 05-Mar-14 07-Feb-14 05-Mar-14 0
BF2060 Laying of DBM 22 10-Feb-14 07-Mar-14 10-Feb-14 07-Mar-14 0
BF2070 Laying of ACBC 22 12-Feb-14 10-Mar-14 12-Feb-14 10-Mar-14 0
BF2075 Regulating 22 13-Feb-14 11-Mar-14 13-Feb-14 11-Mar-14 0
BF2080 Laying of ACWC 22 14-Feb-14 12-Mar-14 14-Feb-14 12-Mar-14 0
BF2090 Laying of SMA 22 18-Feb-14 14-Mar-14 18-Feb-14 14-Mar-14 0
BF2100 Dismantle Guardrail, NJB Installation & Misc. Works 32 05-Feb-14 14-Mar-14 13-Mar-14 18-Apr-14 30
BF2110 Temporay Road Marking & Traffic Diversion/Contra Flow 32 05-Feb-14 14-Mar-14 13-Mar-14 18-Apr-14 30
Sub-Base upto Pavement (CH.4200-CH.2800)Sub-Base upto Pavement (CH.4200-CH.2800) 38 08-Mar-14 21-Apr-14 02-Apr-14 05-Jul-14 62
BF2210 Sub-Grade and Prepare Formation 24 08-Mar-14 04-Apr-14 02-Apr-14 29-Apr-14 21
BF2220 Laying of Lower Sub-Base 24 11-Mar-14 07-Apr-14 04-Apr-14 02-May-14 21
BF2230 Laying of Lower Upper-Base 24 13-Mar-14 09-Apr-14 07-Apr-14 05-May-14 21
BF2240 Laying of CBM 22 15-Mar-14 09-Apr-14 09-Apr-14 05-May-14 21
BF2250 Laying of WMM 22 18-Mar-14 11-Apr-14 11-Apr-14 07-May-14 21
BF2260 Laying of DBM 22 20-Mar-14 14-Apr-14 14-Apr-14 09-May-14 21
BF2270 Laying of ACBC 22 22-Mar-14 16-Apr-14 16-Apr-14 12-May-14 21
BF2275 Regulating 22 24-Mar-14 17-Apr-14 17-Apr-14 14-May-14 21
BF2280 Laying of ACWC 22 25-Mar-14 18-Apr-14 09-Jun-14 03-Jul-14 62
BF2290 Laying of SMA 22 27-Mar-14 21-Apr-14 11-Jun-14 05-Jul-14 62
BF2300 Dismantle Guardrail, NJB Installation & Misc. Works 32 15-Mar-14 21-Apr-14 19-Apr-14 28-May-14 30
BF2310 Temporay Road Marking & Traffic Diversion/Contra Flow 32 15-Mar-14 21-Apr-14 19-Apr-14 28-May-14 30
Sub-Base upto Pavement (CH.2800-CH.1400)Sub-Base upto Pavement (CH.2800-CH.1400) 38 15-Apr-14 30-May-14 28-Apr-14 05-Jul-14 30
BF2410 Sub-Grade and Prepare Formation 24 15-Apr-14 14-May-14 28-Apr-14 27-May-14 11
BF2420 Laying of Lower Sub-Base 24 17-Apr-14 16-May-14 30-Apr-14 29-May-14 11
BF2430 Laying of Lower Upper-Base 24 19-Apr-14 19-May-14 03-May-14 31-May-14 11
BF2440 Laying of CBM 22 22-Apr-14 19-May-14 06-May-14 31-May-14 11
BF2450 Laying of WMM 22 24-Apr-14 21-May-14 08-May-14 04-Jun-14 11
BF2460 Laying of DBM 22 26-Apr-14 23-May-14 10-May-14 06-Jun-14 11
BF2470 Laying of ACBC 22 29-Apr-14 26-May-14 14-May-14 09-Jun-14 11
BF2475 Regulating 22 30-Apr-14 27-May-14 15-May-14 10-Jun-14 11
BF2480 Laying of ACWC 22 02-May-14 28-May-14 09-Jun-14 03-Jul-14 30
BF2490 Laying of SMA 22 05-May-14 30-May-14 11-Jun-14 05-Jul-14 30
BF2500 Dismantle Guardrail, NJB Installation & Misc. Works 32 22-Apr-14 30-May-14 29-May-14 05-Jul-14 30
BF2510 Temporay Road Marking & Traffic Diversion/Contra Flow 32 22-Apr-14 30-May-14 29-May-14 05-Jul-14 30
Sub-Base upto Pavement (CH.1400-CH.0)Sub-Base upto Pavement (CH.1400-CH.0) 35 19-May-14 28-Jun-14 26-May-14 05-Jul-14 6
BF2610 Sub-Grade and Prepare Formation 24 19-May-14 16-Jun-14 26-May-14 23-Jun-14 6
BF2620 Laying of Lower Sub-Base 24 20-May-14 17-Jun-14 27-May-14 24-Jun-14 6
BF2630 Laying of Lower Upper-Base 24 21-May-14 18-Jun-14 28-May-14 25-Jun-14 6
BF2640 Laying of CBM 22 24-May-14 19-Jun-14 31-May-14 26-Jun-14 6
BF2650 Laying of WMM 22 26-May-14 20-Jun-14 03-Jun-14 27-Jun-14 6
BF2660 Laying of DBM 22 27-May-14 21-Jun-14 04-Jun-14 28-Jun-14 6
BF2670 Laying of ACBC 22 29-May-14 24-Jun-14 06-Jun-14 01-Jul-14 6
BF2675 Regulating 22 30-May-14 25-Jun-14 11-Jun-14 05-Jul-14 9
BF2680 Laying of ACWC 22 31-May-14 26-Jun-14 09-Jun-14 03-Jul-14 6
BF2690 Laying of SMA 22 04-Jun-14 28-Jun-14 11-Jun-14 05-Jul-14 6
BF2700 Dismantle Guardrail, NJB Installation & Misc. Works 30 24-May-14 28-Jun-14 31-May-14 05-Jul-14 6
BF2710 Temporay Road Marking & Traffic Diversion/Contra Flow 30 24-May-14 28-Jun-14 31-May-14 05-Jul-14 6
Road Furniture (WB)Road Furniture (WB) 75 01-Apr-14 30-Jun-14 01-Apr-14 05-Jul-14 5
BG3000 Road Furniture Start (WB) 0 01-Apr-14 05-Jul-14 80
BG3010 Road Furniture Finish (WB) 0 30-Jun-14 05-Jul-14 5
Stage 2Stage 2 75 01-Apr-14 30-Jun-14 01-Apr-14 05-Jul-14 5
CH.5600-CH.4200CH.5600-CH.4200 19 01-Apr-14 22-Apr-14 01-Apr-14 28-Apr-14 5
BG2000 Traffic Signs 19 01-Apr-14 22-Apr-14 01-Apr-14 22-Apr-14 0
BG2010 Road Markings 19 01-Apr-14 22-Apr-14 07-Apr-14 28-Apr-14 5
BG2020 Ancillary Finishings 19 01-Apr-14 22-Apr-14 07-Apr-14 28-Apr-14 5
CH.4200-CH.2800CH.4200-CH.2800 19 23-Apr-14 16-May-14 23-Apr-14 22-May-14 5
BG2100 Traffic Signs 19 23-Apr-14 16-May-14 23-Apr-14 16-May-14 0
BG2110 Road Markings 19 23-Apr-14 16-May-14 29-Apr-14 22-May-14 5
BG2120 Ancillary Finishings 19 23-Apr-14 16-May-14 29-Apr-14 22-May-14 5
CH.2800-CH.1400CH.2800-CH.1400 19 17-May-14 09-Jun-14 17-May-14 14-Jun-14 5
BG2200 Traffic Signs 19 17-May-14 09-Jun-14 17-May-14 09-Jun-14 0
BG2210 Road Markings 19 17-May-14 09-Jun-14 23-May-14 14-Jun-14 5
BG2220 Ancillary Finishings 19 17-May-14 09-Jun-14 23-May-14 14-Jun-14 5
CH.1400-CH.0CH.1400-CH.0 18 10-Jun-14 30-Jun-14 10-Jun-14 05-Jul-14 5
BG2300 Traffic Signs 18 10-Jun-14 30-Jun-14 10-Jun-14 30-Jun-14 0
BG2310 Road Markings 18 10-Jun-14 30-Jun-14 16-Jun-14 05-Jul-14 5
BG2320 Ancillary Finishings 18 10-Jun-14 30-Jun-14 16-Jun-14 05-Jul-14 5
Utilities and Services (WB)Utilities and Services (WB) 221 01-Oct-13 30-Jun-14 07-Oct-13 05-Jul-14 5
BH0120 Utilities and Services Start (WB) 0 01-Oct-13 05-Jul-14 226
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014
Sub-Grade and Prepare Formation
Laying of Lower Sub-Base
Laying of Lower Upper-Base
Laying of CBM
Laying of WMM
Laying of DBM
Laying of ACBC
Regulating
Laying of ACWC
Laying of SMA
Dismantle Guardrail, NJB Installation & Misc. Works
Temporay Road Marking & Traffic Diversion/Contra Flow
21-Apr-14, Sub-Base upto Pavement (CH.4200-CH.2800)
Sub-Grade and Prepare Formation
Laying of Lower Sub-Base
Laying of Lower Upper-Base
Laying of CBM
Laying of WMM
Laying of DBM
Laying of ACBC
Regulating
Laying of ACWC
Laying of SMA
Dismantle Guardrail, NJB Installation & Misc. Works
Temporay Road Marking & Traffic Diversion/Contra Flow
30-May-14, Sub-Base upto Pavement (CH.2800-CH.1400)
Sub-Grade and Prepare Formation
Laying of Lower Sub-Base
Laying of Lower Upper-Base
Laying of CBM
Laying of WMM
Laying of DBM
Laying of ACBC
Regulating
Laying of ACWC
Laying of SMA
Dismantle Guardrail, NJB Installation & Misc. Works
Temporay Road Marking & Traffic Diversion/Contra Flow
28-Jun-14, Sub-Base upto Pavement (CH.1400-CH.0)
Sub-Grade and Prepare Formation
Laying of Lower Sub-Base
Laying of Lower Upper-Base
Laying of CBM
Laying of WMM
Laying of DBM
Laying of ACBC
Regulating
Laying of ACWC
Laying of SMA
Dismantle Guardrail, NJB Installation & Misc. Works
Temporay Road Marking & Traffic Diversion/Contra Flow
30-Jun-14, Road Furniture (WB)
Road Furniture Start (WB)
Road Furniture Finish (WB)
30-Jun-14, Stage 2
22-Apr-14, CH.5600-CH.4200
Traffic Signs
Road Markings
Ancillary Finishings
16-May-14, CH.4200-CH.2800
Traffic Signs
Road Markings
Ancillary Finishings
09-Jun-14, CH.2800-CH.1400
Traffic Signs
Road Markings
Ancillary Finishings
30-Jun-14, CH.1400-CH.0
Traffic Signs
Road Markings
Ancillary Finishings
30-Jun-14, Utilities and Services (WB)
Utilities and Services Start (WB)
NORTH-SOUTH EXPRESSWAY (PLUS)
PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Remaining Work
Critical Remaining Work
Milestone
Summary 9 of 13
WORK PROGRAMME
Date Revision Checked Approved
30-Jul-12 Rev.0
11-Sep-12 Rev.1
Activity ID Activity Name OriginalDuration
Early Start Early Finish Late Start Late Finish TotalFloat
BH0130 Utilities and Services Finish (WB) 0 30-Jun-14 05-Jul-14 5
Overall Stage 1Overall Stage 1 221 01-Oct-13 30-Jun-14 07-Oct-13 05-Jul-14 5
BH0010 Testing and Commissioning 63 15-Apr-14 30-Jun-14 21-Apr-14 05-Jul-14 5
CH.5600-CH.4200CH.5600-CH.4200 71 01-Oct-13 27-Dec-13 07-Oct-13 19-Apr-14 92
BH5030 Temporary Works for Exist ing Utilities 71 01-Oct-13 27-Dec-13 24-Jan-14 19-Apr-14 92
BH5040 Waterworks, Relocation of Water Mains (CH.5450) 70 01-Oct-13 26-Dec-13 07-Oct-13 02-Jan-14 5
Telecommunication SystemTelecommunication System 60 01-Oct-13 13-Dec-13 07-Oct-13 22-Jan-14 31
BH5000 Lay Duct 36 01-Oct-13 14-Nov-13 07-Oct-13 20-Nov-13 5
BH5010 Relocation of OFC 36 16-Oct-13 28-Nov-13 23-Nov-13 07-Jan-14 31
BH5020 ITS System 36 30-Oct-13 13-Dec-13 07-Dec-13 22-Jan-14 31
CH.4200-CH.2800CH.4200-CH.2800 71 15-Nov-13 12-Feb-14 21-Nov-13 19-Apr-14 56
BH6030 Temporary Works for Exist ing Utilities 71 15-Nov-13 12-Feb-14 24-Jan-14 19-Apr-14 56
Telecommunication SystemTelecommunication System 60 15-Nov-13 28-Jan-14 21-Nov-13 08-Mar-14 31
BH6000 Lay Duct 36 15-Nov-13 28-Dec-13 21-Nov-13 04-Jan-14 5
BH6010 Relocation of OFC 36 29-Nov-13 13-Jan-14 08-Jan-14 22-Feb-14 31
BH6020 ITS System 36 14-Dec-13 28-Jan-14 23-Jan-14 08-Mar-14 31
CH.2800-CH.1400CH.2800-CH.1400 71 30-Dec-13 27-Mar-14 06-Jan-14 19-Apr-14 20
BH7030 Temporary Works for Exist ing Utilities 71 30-Dec-13 27-Mar-14 24-Jan-14 19-Apr-14 20
Telecommunication SystemTelecommunication System 60 30-Dec-13 14-Mar-14 06-Jan-14 19-Apr-14 31
BH7000 Lay Duct 36 30-Dec-13 13-Feb-14 06-Jan-14 20-Feb-14 5
BH7010 Relocation of OFC 36 15-Jan-14 28-Feb-14 24-Feb-14 05-Apr-14 31
BH7020 ITS System 36 29-Jan-14 14-Mar-14 10-Mar-14 19-Apr-14 31
CH.1400-CH.0CH.1400-CH.0 65 14-Feb-14 02-May-14 21-Feb-14 05-Jul-14 53
BH8030 Temporary Works for Exist ing Utilities 65 14-Feb-14 02-May-14 18-Apr-14 05-Jul-14 53
Telecommunication SystemTelecommunication System 50 14-Feb-14 14-Apr-14 21-Feb-14 19-Apr-14 5
BH8000 Lay Duct 36 14-Feb-14 28-Mar-14 21-Feb-14 03-Apr-14 5
BH8010 Relocation of OFC 36 22-Feb-14 04-Apr-14 28-Feb-14 10-Apr-14 5
BH8020 ITS System 36 04-Mar-14 14-Apr-14 10-Mar-14 19-Apr-14 5
Bridge Widening (WB)Bridge Widening (WB) 271 01-Jul-13 31-May-14 05-Aug-13 05-Jul-14 29
BJ1020 Bridge Widening Start (WB) 0 29-Aug-13 05-Jul-14 252
BJ1030 Bridge Widening Finish (WB) 0 31-May-14 05-Jul-14 29
Bridge Extension Over Jalan Damansara (BR B.1)Bridge Extension Over Jalan Damansara (BR B.1) 223 29-Aug-13 31-May-14 14-Oct-13 05-Jul-14 29
Pier 2Pier 2 54 03-Oct-13 07-Dec-13 14-Nov-13 22-Jan-14 35
BJ2760 Pile Cap Construction 22 03-Oct-13 29-Oct-13 14-Nov-13 09-Dec-13 33
BJ2770 Column Construction 32 30-Oct-13 07-Dec-13 13-Dec-13 22-Jan-14 35
Pier 1Pier 1 48 05-Oct-13 03-Dec-13 16-Nov-13 22-Jan-14 39
BJ2780 Pile Cap Construction 22 05-Oct-13 31-Oct-13 16-Nov-13 12-Dec-13 33
BJ2790 Column Construction 26 01-Nov-13 03-Dec-13 20-Dec-13 22-Jan-14 39
Precast BeamsPrecast Beams 12 17-Dec-13 31-Dec-13 23-Jan-14 07-Feb-14 29
BJ2900 Launching of Pre-tensioned Concrete Beams 12 17-Dec-13 31-Dec-13 23-Jan-14 07-Feb-14 29
Bridge DeckBridge Deck 40 02-Jan-14 21-Feb-14 08-Feb-14 27-Mar-14 29
BJ2910 Bridge Deck Construction 40 02-Jan-14 21-Feb-14 08-Feb-14 27-Mar-14 29
PilingPiling 40 29-Aug-13 17-Oct-13 14-Oct-13 22-Nov-13 29
BJ2500 Temporary Sheet Piling 6 29-Aug-13 05-Sep-13 14-Oct-13 21-Oct-13 37
BJ2505 Bored Piling 26 17-Sep-13 17-Oct-13 22-Oct-13 22-Nov-13 29
MiscellaneousMiscellaneous 95 07-Feb-14 31-May-14 14-Mar-14 05-Jul-14 29
BJ2940 Bridge Parapet, Lining to Abutment and Service Ducts 26 07-Feb-14 10-Mar-14 14-Mar-14 12-Apr-14 29
BJ2950 Installation of Movement Joints in Bridge Deck and Approach Slab 12 19-May-14 31-May-14 23-Jun-14 05-Jul-14 29
Pier 5Pier 5 48 26-Sep-13 23-Nov-13 31-Oct-13 22-Jan-14 47
BJ2700 Pile Cap Construction 22 26-Sep-13 22-Oct-13 31-Oct-13 27-Nov-13 29
BJ2710 Column Construction 26 23-Oct-13 23-Nov-13 20-Dec-13 22-Jan-14 47
Pier 4Pier 4 62 28-Sep-13 13-Dec-13 02-Nov-13 22-Jan-14 31
BJ2720 Pile Cap Construction 22 28-Sep-13 24-Oct-13 02-Nov-13 29-Nov-13 29
BJ2730 Column Construction 40 25-Oct-13 13-Dec-13 03-Dec-13 22-Jan-14 31
Pier 3Pier 3 62 01-Oct-13 16-Dec-13 07-Nov-13 22-Jan-14 29
BJ2740 Pile Cap Construction 22 01-Oct-13 26-Oct-13 07-Nov-13 02-Dec-13 29
BJ2750 Column Construction 40 28-Oct-13 16-Dec-13 03-Dec-13 22-Jan-14 29
West AbutmentWest Abutment 52 08-Oct-13 10-Dec-13 19-Nov-13 22-Jan-14 33
BJ2640 Pile Cap Construction 18 08-Oct-13 29-Oct-13 19-Nov-13 09-Dec-13 33
BJ2650 Abutment Wall 16 30-Oct-13 19-Nov-13 10-Dec-13 30-Dec-13 33
BJ2660 Wing Wall & Curtail Wall 10 20-Nov-13 30-Nov-13 31-Dec-13 11-Jan-14 33
BJ2670 Approach Slab 8 02-Dec-13 10-Dec-13 13-Jan-14 22-Jan-14 33
East AbutmentEast Abutment 52 24-Sep-13 26-Nov-13 29-Oct-13 22-Jan-14 45
BJ2600 Pile Cap Construction 18 24-Sep-13 14-Oct-13 29-Oct-13 20-Nov-13 29
BJ2610 Abutment Wall 16 16-Oct-13 02-Nov-13 10-Dec-13 30-Dec-13 45
BJ2620 Wing Wall & Curtail Wall 10 06-Nov-13 16-Nov-13 31-Dec-13 11-Jan-14 45
BJ2630 Approach Slab 8 18-Nov-13 26-Nov-13 13-Jan-14 22-Jan-14 45
Bridge Extension Over Segambut Dalam (BR B.2)Bridge Extension Over Segambut Dalam (BR B.2) 232 30-Jul-13 14-May-14 12-Sep-13 05-Jul-14 44
PilingPiling 38 30-Jul-13 14-Sep-13 12-Sep-13 21-Oct-13 29
BJ3500 Temporary Sheet Piling 6 30-Jul-13 05-Aug-13 12-Sep-13 19-Sep-13 35
BJ3505 Bored Piling 26 15-Aug-13 14-Sep-13 20-Sep-13 21-Oct-13 29
East AbutmentEast Abutment 62 22-Aug-13 07-Nov-13 16-Oct-13 18-Jan-14 58
BJ3600 Pile Cap Construction 22 22-Aug-13 18-Sep-13 16-Oct-13 12-Nov-13 44
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014
Utilities and Services Finish (WB)
30-Jun-14, Overall Stage 1
Testing and Commissioning
27-Dec-13, CH.5600-CH.4200
Temporary Works for Exist ing Utilities
Waterworks, Relocation of Water Mains (CH.5450)
13-Dec-13, Telecommunication System
Lay Duct
Relocation of OFC
ITS System
12-Feb-14, CH.4200-CH.2800
Temporary Works for Exist ing Utilities
28-Jan-14, Telecommunication System
Lay Duct
Relocation of OFC
ITS System
27-Mar-14, CH.2800-CH.1400
Temporary Works for Exist ing Utilities
14-Mar-14, Telecommunication System
Lay Duct
Relocation of OFC
ITS System
02-May-14, CH.1400-CH.0
Temporary Works for Existing Utilities
14-Apr-14, Telecommunication System
Lay Duct
Relocation of OFC
ITS System
31-May-14, Bridge Widening (WB)
Bridge Widening Start (WB)
Bridge Widening Finish (WB)
31-May-14, Bridge Extension Over Jalan Damansara (BR B.1)
07-Dec-13, Pier 2
Pile Cap Construction
Column Construction
03-Dec-13, Pier 1
Pile Cap Construction
Column Construction
31-Dec-13, Precast Beams
Launching of Pre-tensioned Concrete Beams
21-Feb-14, Bridge Deck
Bridge Deck Construction
17-Oct-13, Piling
Temporary Sheet Piling
Bored Piling
31-May-14, Miscellaneous
Bridge Parapet, Lining to Abutment and Service Ducts
Installation of Movement Joints in Bridge Deck and Approach Slab
23-Nov-13, Pier 5
Pile Cap Construction
Column Construction
13-Dec-13, Pier 4
Pile Cap Construction
Column Construction
16-Dec-13, Pier 3
Pile Cap Construction
Column Construction
10-Dec-13, West Abutment
Pile Cap Construction
Abutment Wall
Wing Wall & Curtail Wall
Approach Slab
26-Nov-13, East Abutment
Pile Cap Construction
Abutment Wall
Wing Wall & Curtail Wall
Approach Slab
14-May-14, Bridge Extension Over Segambut Dalam (BR B.2)
14-Sep-13, Piling
Temporary Sheet Piling
Bored Piling
07-Nov-13, East Abutment
Pile Cap Construction
NORTH-SOUTH EXPRESSWAY (PLUS)
PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Remaining Work
Critical Remaining Work
Milestone
Summary 10 of 13
WORK PROGRAMME
Date Revision Checked Approved
30-Jul-12 Rev.0
11-Sep-12 Rev.1
Activity ID Activity Name OriginalDuration
Early Start Early Finish Late Start Late Finish TotalFloat
BJ3610 Abutment Wall 18 19-Sep-13 09-Oct-13 29-Nov-13 20-Dec-13 58
BJ3620 Wing Wall & Curtail Wall 12 10-Oct-13 24-Oct-13 21-Dec-13 06-Jan-14 58
BJ3630 Approach Slab 10 25-Oct-13 07-Nov-13 07-Jan-14 18-Jan-14 58
Pier 4Pier 4 56 27-Aug-13 02-Nov-13 21-Oct-13 18-Jan-14 60
BJ3700 Pile Cap Construction 22 27-Aug-13 23-Sep-13 21-Oct-13 16-Nov-13 44
BJ3710 Column Construction 34 24-Sep-13 02-Nov-13 06-Dec-13 18-Jan-14 60
Pier 3Pier 3 62 29-Aug-13 14-Nov-13 23-Oct-13 18-Jan-14 52
BJ3720 Pile Cap Construction 22 29-Aug-13 25-Sep-13 23-Oct-13 19-Nov-13 44
BJ3730 Column Construction 40 26-Sep-13 14-Nov-13 29-Nov-13 18-Jan-14 52
Bridge DeckBridge Deck 40 09-Dec-13 28-Jan-14 05-Feb-14 24-Mar-14 44
BJ3920 Bridge Deck Construction 40 09-Dec-13 28-Jan-14 05-Feb-14 24-Mar-14 44
Pier 2Pier 2 62 02-Sep-13 16-Nov-13 25-Oct-13 18-Jan-14 50
BJ3740 Pile Cap Construction 22 02-Sep-13 27-Sep-13 25-Oct-13 21-Nov-13 44
BJ3750 Column Construction 40 28-Sep-13 16-Nov-13 29-Nov-13 18-Jan-14 50
West AbutmentWest Abutment 62 09-Sep-13 23-Nov-13 01-Nov-13 18-Jan-14 44
BJ3640 Pile Cap Construction 22 09-Sep-13 04-Oct-13 01-Nov-13 28-Nov-13 44
BJ3650 Abutment Wall 18 05-Oct-13 26-Oct-13 29-Nov-13 20-Dec-13 44
BJ3660 Wing Wall & Curtail Wall 12 28-Oct-13 12-Nov-13 21-Dec-13 06-Jan-14 44
BJ3670 Approach Slab 10 13-Nov-13 23-Nov-13 07-Jan-14 18-Jan-14 44
Pier 1Pier 1 48 04-Sep-13 31-Oct-13 28-Oct-13 18-Jan-14 62
BJ3760 Pile Cap Construction 22 04-Sep-13 30-Sep-13 28-Oct-13 23-Nov-13 44
BJ3770 Column Construction 26 01-Oct-13 31-Oct-13 17-Dec-13 18-Jan-14 62
MiscellaneousMiscellaneous 98 15-Jan-14 14-May-14 11-Mar-14 05-Jul-14 44
BJ3930 Bridge Parapet, Lining to Abutment and Service Ducts 26 15-Jan-14 17-Feb-14 11-Mar-14 09-Apr-14 44
BJ3940 Installation of Movement Joints in Bridge Deck and Approach Slab 12 29-Apr-14 14-May-14 23-Jun-14 05-Jul-14 44
Precast BeamsPrecast Beams 12 25-Nov-13 07-Dec-13 20-Jan-14 04-Feb-14 44
BJ3910 Launching of Post-tensioned Concrete Beams 12 25-Nov-13 07-Dec-13 20-Jan-14 04-Feb-14 44
Extension of Viaduct at Edinburgh Estate (BR B.3)Extension of Viaduct at Edinburgh Estate (BR B.3) 260 01-Jul-13 19-May-14 05-Aug-13 05-Jul-14 40
PilingPiling 36 01-Jul-13 14-Aug-13 05-Aug-13 19-Sep-13 29
BJ4500 Temporary Sheet Piling 6 01-Jul-13 06-Jul-13 05-Aug-13 13-Aug-13 29
BJ4505 Bored Piling 30 08-Jul-13 14-Aug-13 14-Aug-13 19-Sep-13 29
East AbutmentEast Abutment 62 15-Jul-13 30-Sep-13 04-Sep-13 20-Dec-13 66
BJ4600 Pile Cap Construction 22 15-Jul-13 12-Aug-13 04-Sep-13 30-Sep-13 40
BJ4610 Abutment Wall 18 13-Aug-13 03-Sep-13 01-Nov-13 23-Nov-13 66
BJ4620 Wing Wall & Curtail Wall 12 04-Sep-13 18-Sep-13 25-Nov-13 07-Dec-13 66
BJ4630 Approach Slab 10 19-Sep-13 30-Sep-13 09-Dec-13 20-Dec-13 66
Pier 10Pier 10 48 19-Jul-13 18-Sep-13 09-Sep-13 20-Dec-13 76
BJ4700 Pile Cap Construction 22 19-Jul-13 16-Aug-13 09-Sep-13 04-Oct-13 40
BJ4710 Column Construction 26 17-Aug-13 18-Sep-13 20-Nov-13 20-Dec-13 76
Pier 9Pier 9 58 22-Jul-13 02-Oct-13 11-Sep-13 20-Dec-13 64
BJ4720 Pile Cap Construction 22 22-Jul-13 19-Aug-13 11-Sep-13 07-Oct-13 40
BJ4730 Column Construction 36 20-Aug-13 02-Oct-13 08-Nov-13 20-Dec-13 64
Pier 8Pier 8 72 24-Jul-13 22-Oct-13 13-Sep-13 20-Dec-13 48
BJ4740 Pile Cap Construction 22 24-Jul-13 21-Aug-13 13-Sep-13 09-Oct-13 40
BJ4750 Column Construction 50 22-Aug-13 22-Oct-13 21-Oct-13 20-Dec-13 48
Pier 7Pier 7 72 27-Jul-13 24-Oct-13 17-Sep-13 20-Dec-13 46
BJ4760 Pile Cap Construction 22 27-Jul-13 23-Aug-13 17-Sep-13 11-Oct-13 40
BJ4770 Column Construction 50 24-Aug-13 24-Oct-13 21-Oct-13 20-Dec-13 46
Pier 6Pier 6 68 30-Jul-13 22-Oct-13 19-Sep-13 20-Dec-13 48
BJ4780 Pile Cap Construction 22 30-Jul-13 26-Aug-13 19-Sep-13 14-Oct-13 40
BJ4790 Column Construction 46 27-Aug-13 22-Oct-13 25-Oct-13 20-Dec-13 48
Pier 5Pier 5 68 01-Aug-13 24-Oct-13 21-Sep-13 20-Dec-13 46
BJ4800 Pile Cap Construction 22 01-Aug-13 28-Aug-13 21-Sep-13 17-Oct-13 40
BJ4810 Column Construction 46 29-Aug-13 24-Oct-13 25-Oct-13 20-Dec-13 46
Pier 4Pier 4 68 03-Aug-13 26-Oct-13 24-Sep-13 20-Dec-13 44
BJ4820 Pile Cap Construction 22 03-Aug-13 30-Aug-13 24-Sep-13 19-Oct-13 40
BJ4830 Column Construction 46 02-Sep-13 26-Oct-13 25-Oct-13 20-Dec-13 44
Pier 3Pier 3 58 06-Aug-13 17-Oct-13 26-Sep-13 20-Dec-13 52
BJ4840 Pile Cap Construction 22 06-Aug-13 03-Sep-13 26-Sep-13 22-Oct-13 40
BJ4850 Column Construction 36 04-Sep-13 17-Oct-13 08-Nov-13 20-Dec-13 52
Pier 2Pier 2 48 10-Aug-13 07-Oct-13 28-Sep-13 20-Dec-13 60
BJ4860 Pile Cap Construction 22 10-Aug-13 05-Sep-13 28-Sep-13 24-Oct-13 40
BJ4870 Column Construction 26 06-Sep-13 07-Oct-13 20-Nov-13 20-Dec-13 60
Pier 1Pier 1 40 13-Aug-13 30-Sep-13 01-Oct-13 20-Dec-13 66
BJ4880 Pile Cap Construction 22 13-Aug-13 07-Sep-13 01-Oct-13 26-Oct-13 40
BJ4890 Column Construction 18 09-Sep-13 30-Sep-13 29-Nov-13 20-Dec-13 66
West AbutmentWest Abutment 62 17-Aug-13 31-Oct-13 05-Oct-13 20-Dec-13 40
BJ4640 Pile Cap Construction 22 17-Aug-13 12-Sep-13 05-Oct-13 31-Oct-13 40
BJ4650 Abutment Wall 18 13-Sep-13 04-Oct-13 01-Nov-13 23-Nov-13 40
BJ4660 Wing Wall & Curtail Wall 12 05-Oct-13 19-Oct-13 25-Nov-13 07-Dec-13 40
BJ4670 Approach Slab 10 21-Oct-13 31-Oct-13 09-Dec-13 20-Dec-13 40
Precast BeamsPrecast Beams 16 01-Nov-13 21-Nov-13 21-Dec-13 10-Jan-14 40
BJ4900 Launching of Post-tensioned Concrete Beams 16 01-Nov-13 21-Nov-13 21-Dec-13 10-Jan-14 40
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014
Abutment Wall
Wing Wall & Curtail Wall
Approach Slab
02-Nov-13, Pier 4
Pile Cap Construction
Column Construction
14-Nov-13, Pier 3
Pile Cap Construction
Column Construction
28-Jan-14, Bridge Deck
Bridge Deck Construction
16-Nov-13, Pier 2
Pile Cap Construction
Column Construction
23-Nov-13, West Abutment
Pile Cap Construction
Abutment Wall
Wing Wall & Curtail Wall
Approach Slab
31-Oct-13, Pier 1
Pile Cap Construction
Column Construction
14-May-14, Miscellaneous
Bridge Parapet, Lining to Abutment and Service Ducts
Installation of Movement Joints in Bridge Deck and Approach Slab
07-Dec-13, Precast Beams
Launching of Post-tensioned Concrete Beams
19-May-14, Extension of Viaduct at Edinburgh Estate (BR B.3)
14-Aug-13, Piling
Temporary Sheet Piling
Bored Piling
30-Sep-13, East Abutment
Pile Cap Construction
Abutment Wall
Wing Wall & Curtail Wall
Approach Slab
18-Sep-13, Pier 10
Pile Cap Construction
Column Construction
02-Oct-13, Pier 9
Pile Cap Construction
Column Construction
22-Oct-13, Pier 8
Pile Cap Construction
Column Construction
24-Oct-13, Pier 7
Pile Cap Construction
Column Construction
22-Oct-13, Pier 6
Pile Cap Construction
Column Construction
24-Oct-13, Pier 5
Pile Cap Construction
Column Construction
26-Oct-13, Pier 4
Pile Cap Construction
Column Construction
17-Oct-13, Pier 3
Pile Cap Construction
Column Construction
07-Oct-13, Pier 2
Pile Cap Construction
Column Construction
30-Sep-13, Pier 1
Pile Cap Construction
Column Construction
31-Oct-13, West Abutment
Pile Cap Construction
Abutment Wall
Wing Wall & Curtail Wall
Approach Slab
21-Nov-13, Precast Beams
Launching of Post-tensioned Concrete Beams
NORTH-SOUTH EXPRESSWAY (PLUS)
PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Remaining Work
Critical Remaining Work
Milestone
Summary 11 of 13
WORK PROGRAMME
Date Revision Checked Approved
30-Jul-12 Rev.0
11-Sep-12 Rev.1
Activity ID Activity Name OriginalDuration
Early Start Early Finish Late Start Late Finish TotalFloat
Bridge DeckBridge Deck 46 22-Nov-13 18-Jan-14 11-Jan-14 10-Mar-14 40
BJ4910 Bridge Deck Construction 46 22-Nov-13 18-Jan-14 11-Jan-14 10-Mar-14 40
MiscellaneousMiscellaneous 110 04-Jan-14 19-May-14 25-Feb-14 05-Jul-14 40
BJ4920 Bridge Parapet, Lining to Abutment and Service Ducts 32 04-Jan-14 13-Feb-14 25-Feb-14 02-Apr-14 40
BJ4930 Installation of Movement Joints in Bridge Deck and Approach Slab 18 26-Apr-14 19-May-14 16-Jun-14 05-Jul-14 40
Slope Improvement Works (WB)Slope Improvement Works (WB) 268 03-Jun-13 28-Apr-14 10-Aug-13 05-Jul-14 56
BL0030 Slope Improvement Works Start (WB) 0 03-Jun-13 05-Jul-14 324
BL0040 Slope Improvement Works Finish (WB) 0 28-Apr-14 05-Jul-14 56
Overall Stage 1Overall Stage 1 268 03-Jun-13 28-Apr-14 10-Aug-13 05-Jul-14 56
Cut AreaCut Area 268 03-Jun-13 28-Apr-14 10-Aug-13 05-Jul-14 56
Slope Improvement - Retaining Wall (CH.2300-CH.2080)Slope Improvement - Retaining Wall (CH.2300-CH.2080) 76 14-Dec-13 19-Mar-14 05-Apr-14 05-Jul-14 90
BL3500 Excavation 58 14-Dec-13 26-Feb-14 05-Apr-14 14-Jun-14 90
BL3510 Construction of Wall Base 58 21-Dec-13 05-Mar-14 12-Apr-14 21-Jun-14 90
BL3520 Construction of Retaining Wall 58 30-Dec-13 12-Mar-14 19-Apr-14 28-Jun-14 90
BL3530 Backfill 58 07-Jan-14 19-Mar-14 26-Apr-14 05-Jul-14 90
Slope Improvement - Horizontal DrainSlope Improvement - Horizontal Drain 268 03-Jun-13 28-Apr-14 10-Aug-13 05-Jul-14 56
BL3000 Installation of Horizontal Drain (CH.5600-CH.4200) 67 03-Jun-13 22-Aug-13 10-Aug-13 30-Oct-13 56
BL3010 Installation of Horizontal Drain (CH.4200-CH.2800) 67 23-Aug-13 14-Nov-13 31-Oct-13 23-Jan-14 56
BL3020 Installation of Horizontal Drain (CH.2800-CH.1400) 67 15-Nov-13 07-Feb-14 24-Jan-14 15-Apr-14 56
BL3030 Installation of Horizontal Drain (CH.1400-CH.0) 67 08-Feb-14 28-Apr-14 16-Apr-14 05-Jul-14 56
Fill AreaFill Area 54 24-Jun-13 28-Aug-13 02-May-14 05-Jul-14 252
Slope Improvement - Retaining Wall (CH.5380-CH.5280)Slope Improvement - Retaining Wall (CH.5380-CH.5280) 54 24-Jun-13 28-Aug-13 02-May-14 05-Jul-14 252
BL4000 Excavation 30 24-Jun-13 29-Jul-13 02-May-14 07-Jun-14 252
BL4020 Construction of Wall Base 30 08-Jul-13 14-Aug-13 17-May-14 21-Jun-14 252
BL4030 Construction of Retaining Wall 30 15-Jul-13 21-Aug-13 24-May-14 28-Jun-14 252
BL4040 Backfill 30 22-Jul-13 28-Aug-13 31-May-14 05-Jul-14 252
Ground Treatment Works (WB)Ground Treatment Works (WB) 208 15-May-13 28-Jan-14 21-May-13 05-Jul-14 130
BM0030 Ground Treatment Works Start (WB) 0 15-May-13 05-Jul-14 338
BM0040 Ground Treatment Works Finish (WB) 0 28-Jan-14 05-Jul-14 130
Stage 1Stage 1 208 15-May-13 28-Jan-14 21-May-13 05-Jul-14 130
Ground Treatment (CH.5600-CH.4200)Ground Treatment (CH.5600-CH.4200) 52 15-May-13 16-Jul-13 21-May-13 22-Jul-13 5
BM2000 Excavation of Unsuitable Material 46 15-May-13 09-Jul-13 21-May-13 15-Jul-13 5
BM2010 Laying of Geotextile Separator 46 17-May-13 11-Jul-13 23-May-13 17-Jul-13 5
BM2020 Laying of Outlet Drain 46 20-May-13 13-Jul-13 27-May-13 19-Jul-13 5
BM2030 Backfilling with Compacted Soil / hardcore Material 46 22-May-13 16-Jul-13 29-May-13 22-Jul-13 5
Ground Treatment (CH.4200-CH.2800)Ground Treatment (CH.4200-CH.2800) 52 17-Jul-13 20-Sep-13 27-Dec-13 03-Mar-14 130
BM2100 Excavation of Unsuitable Material 46 17-Jul-13 12-Sep-13 27-Dec-13 24-Feb-14 130
BM2110 Laying of Geotextile Separator 46 19-Jul-13 14-Sep-13 30-Dec-13 26-Feb-14 130
BM2120 Laying of Outlet Drain 46 22-Jul-13 18-Sep-13 02-Jan-14 28-Feb-14 130
BM2130 Backfilling with Compacted Soil / hardcore Material 46 24-Jul-13 20-Sep-13 04-Jan-14 03-Mar-14 130
Ground Treatment (CH.2800-CH.1400)Ground Treatment (CH.2800-CH.1400) 52 21-Sep-13 23-Nov-13 04-Mar-14 03-May-14 130
BM2200 Excavation of Unsuitable Material 46 21-Sep-13 16-Nov-13 04-Mar-14 25-Apr-14 130
BM2210 Laying of Geotextile Separator 46 24-Sep-13 19-Nov-13 06-Mar-14 28-Apr-14 130
BM2220 Laying of Outlet Drain 46 26-Sep-13 21-Nov-13 08-Mar-14 30-Apr-14 130
BM2230 Backfilling with Compacted Soil / hardcore Material 46 28-Sep-13 23-Nov-13 11-Mar-14 03-May-14 130
Ground Treatment (CH.1400-CH.0)Ground Treatment (CH.1400-CH.0) 52 25-Nov-13 28-Jan-14 05-May-14 05-Jul-14 130
BM2300 Excavation of Unsuitable Material 46 25-Nov-13 21-Jan-14 05-May-14 28-Jun-14 130
BM2310 Laying of Geotextile Separator 46 27-Nov-13 23-Jan-14 07-May-14 01-Jul-14 130
BM2320 Laying of Outlet Drain 46 29-Nov-13 25-Jan-14 09-May-14 03-Jul-14 130
BM2330 Backfilling with Compacted Soil / hardcore Material 46 02-Dec-13 28-Jan-14 12-May-14 05-Jul-14 130
Electrical Works for Street Lighting (WB)Electrical Works for Street Lighting (WB) 219 03-Oct-13 30-Jun-14 09-Oct-13 05-Jul-14 5
BN0030 Electrical Works for Street Lighting Start (WB) 0 03-Oct-13 05-Jul-14 224
BN0040 Electrical Works for Street Lighting Finish (WB) 0 30-Jun-14 05-Jul-14 5
Overall Stage 1Overall Stage 1 219 03-Oct-13 30-Jun-14 09-Oct-13 05-Jul-14 5
BN0200 Testing and Commissioning 60 18-Apr-14 30-Jun-14 24-Apr-14 05-Jul-14 5
CH.5600-CH.4200CH.5600-CH.4200 48 03-Oct-13 30-Nov-13 09-Oct-13 06-Dec-13 5
BN2000 High Mast 48 03-Oct-13 30-Nov-13 09-Oct-13 06-Dec-13 5
BN2010 Street Lighting 48 03-Oct-13 30-Nov-13 09-Oct-13 06-Dec-13 5
CH.4200-CH.2800CH.4200-CH.2800 48 02-Dec-13 30-Jan-14 07-Dec-13 07-Feb-14 5
BN2100 High Mast 48 02-Dec-13 30-Jan-14 07-Dec-13 07-Feb-14 5
BN2110 Street Lighting 48 02-Dec-13 30-Jan-14 07-Dec-13 07-Feb-14 5
CH.2800-CH.1400CH.2800-CH.1400 48 03-Feb-14 31-Mar-14 08-Feb-14 05-Apr-14 5
BN2200 High Mast 48 03-Feb-14 31-Mar-14 08-Feb-14 05-Apr-14 5
BN2210 Street Lighting 48 03-Feb-14 31-Mar-14 08-Feb-14 05-Apr-14 5
CH.1400-CH.0CH.1400-CH.0 48 01-Apr-14 28-May-14 07-Apr-14 04-Jun-14 5
BN2300 High Mast 48 01-Apr-14 28-May-14 07-Apr-14 04-Jun-14 5
BN2310 Street Lighting 48 01-Apr-14 28-May-14 07-Apr-14 04-Jun-14 5
Prime Cost and Provisional SumsPrime Cost and Provisional Sums 544 03-Sep-12 02-Jul-14 06-Sep-12 05-Jul-14 3
BP1000 Provisional Sums Start 0 01-Oct-12 05-Jul-14 524
BP1010 Provisional Sums Finish 0 02-Jul-14 05-Jul-14 3
Prime CostPrime Cost 544 03-Sep-12 02-Jul-14 06-Sep-12 05-Jul-14 3
BP3100 Traffic Management 544 03-Sep-12 02-Jul-14 06-Sep-12 05-Jul-14 3
BP3300 Landscaping Works 70 01-Apr-14 24-Jun-14 12-Apr-14 05-Jul-14 10
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014
18-Jan-14, Bridge Deck
Bridge Deck Construction
19-May-14, Miscellaneous
Bridge Parapet, Lining to Abutment and Service Ducts
Installation of Movement Joints in Bridge Deck and Approach Slab
28-Apr-14, Slope Improvement Works (WB)
Slope Improvement Works Start (WB)
Slope Improvement Works Finish (WB)
28-Apr-14, Overall Stage 1
28-Apr-14, Cut Area
19-Mar-14, Slope Improvement - Retaining Wall (CH.2300-CH.2080)
Excavation
Construction of Wall Base
Construction of Retaining Wall
Backfill
28-Apr-14, Slope Improvement - Horizontal Drain
Installation of Horizontal Drain (CH.5600-CH.4200)
Installation of Horizontal Drain (CH.4200-CH.2800)
Installation of Horizontal Drain (CH.2800-CH.1400)
Installation of Horizontal Drain (CH.1400-CH.0)
28-Aug-13, Fill Area
28-Aug-13, Slope Improvement - Retaining Wall (CH.5380-CH.5280)
Excavation
Construction of Wall Base
Construction of Retaining Wall
Backfill
28-Jan-14, Ground Treatment Works (WB)
Ground Treatment Works Start (WB)
Ground Treatment Works Finish (WB)
28-Jan-14, Stage 1
16-Jul-13, Ground Treatment (CH.5600-CH.4200)
Excavation of Unsuitable Material
Laying of Geotextile Separator
Laying of Outlet Drain
Backfilling with Compacted Soil / hardcore Material
20-Sep-13, Ground Treatment (CH.4200-CH.2800)
Excavation of Unsuitable Material
Laying of Geotextile Separator
Laying of Outlet Drain
Backfilling with Compacted Soil / hardcore Material
23-Nov-13, Ground Treatment (CH.2800-CH.1400)
Excavation of Unsuitable Material
Laying of Geotextile Separator
Laying of Outlet Drain
Backfilling with Compacted Soil / hardcore Material
28-Jan-14, Ground Treatment (CH.1400-CH.0)
Excavation of Unsuitable Material
Laying of Geotextile Separator
Laying of Outlet Drain
Backfilling with Compacted Soil / hardcore Material
30-Jun-14, Electrical Works for Street Lighting (WB)
Electrical Works for Street Lighting Start (WB)
Electrical Works for Street Lighting Finish (WB)
30-Jun-14, Overall Stage 1
Testing and Commissioning
30-Nov-13, CH.5600-CH.4200
High Mast
Street Lighting
30-Jan-14, CH.4200-CH.2800
High Mast
Street Lighting
31-Mar-14, CH.2800-CH.1400
High Mast
Street Lighting
28-May-14, CH.1400-CH.0
High Mast
Street Lighting
02-Jul-14, Prime Cost and Provisional Sums
Provisional Sums Start
Provisional Sums Finish
02-Jul-14, Prime Cost
Traffic Management
Landscaping Works
NORTH-SOUTH EXPRESSWAY (PLUS)
PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Remaining Work
Critical Remaining Work
Milestone
Summary 12 of 13
WORK PROGRAMME
Date Revision Checked Approved
30-Jul-12 Rev.0
11-Sep-12 Rev.1
Activity ID Activity Name OriginalDuration
Early Start Early Finish Late Start Late Finish TotalFloat
Provisional SumsProvisional Sums 514 01-Oct-12 24-Jun-14 17-Oct-12 05-Jul-14 10
BP1100 Protection to All Services and Utilities 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14
BP1250 Environmental Management 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14
BP1300 Authority Fee 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14
BP1450 Rock Fences 70 01-Apr-14 24-Jun-14 12-Apr-14 05-Jul-14 10
BP1550 Slope Protection 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14
BP1600 Piled Embankment 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14
BP1700 Telecommunication Services 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14
BP1800 ITS System 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14
BP1900 Utilities Relocation Works Under the Bridges 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14
BP2050 Relocation Works 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14
BP2100 Dayworks 510 01-Oct-12 19-Jun-14 17-Oct-12 05-Jul-14 14
Project CompletionProject Completion 273 02-Aug-13 05-Jul-14 05-May-14 05-Jul-14 0
Section 1 - East BoundSection 1 - East Bound 52 02-Aug-13 05-Oct-13 05-May-14 05-Jul-14 221
BQ1000 Clearing Up of Site 52 02-Aug-13 05-Oct-13 05-May-14 05-Jul-14 221
BQ1010 Final Demobilisation 26 05-Sep-13 05-Oct-13 06-Jun-14 05-Jul-14 221
BQ1020 Completion of Work 0 05-Oct-13 05-Jul-14 221
Section 2 - West BoundSection 2 - West Bound 52 05-May-14 05-Jul-14 05-May-14 05-Jul-14 0
BQ2000 Clearing Up of Site 52 05-May-14 05-Jul-14 05-May-14 05-Jul-14 0
BQ2010 Final Demobilisation 26 06-Jun-14 05-Jul-14 06-Jun-14 05-Jul-14 0
BQ2020 Completion of Work 0 05-Jul-14 05-Jul-14 0
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug2012 2013 2014
24-Jun-14, Provisional Sums
Protection to All Services and Utilities
Environmental Management
Authority Fee
Rock Fences
Slope Protection
Piled Embankment
Telecommunication Services
ITS System
Utilities Relocation Works Under the Bridges
Relocation Works
Dayworks
05-Jul-14, Project Completion
05-Oct-13, Section 1 - East Bound
Clearing Up of Site
Final Demobilisation
Completion of Work
05-Jul-14, Section 2 - West Bound
Clearing Up of Site
Final Demobilisation
Completion of Work
NORTH-SOUTH EXPRESSWAY (PLUS)
PROPOSED FOURTH LANE WIDENING BETWEEN BUKIT LANJAN (KM 22.0) AND JALAN DUTA TOLL PLAZA (KM 29.0), PACKAGE B
Remaining Work
Critical Remaining Work
Milestone
Summary 13 of 13
WORK PROGRAMME
Date Revision Checked Approved
30-Jul-12 Rev.0
11-Sep-12 Rev.1