Package #2 Pre-SOQ MeetingEast County Advanced Water Purification Project February 11, 2020
Welcome
JPA Formed
• East County AWP JPA formed on Nov. 1, 2020• Project governed by the JPA
• Design, construct, finance, and operate the Project• Padre Dam is the Interim Administrator and Operator of the JPA
Presentation Overview
ECAWP Project Overview
RFQ Key Points
Picking the Right Team
Submittal Requirements
Q & A
Selecting the Right Team
Deliver an extraordinary project as part of a high performing and integrated team!
Select the best Design-Build team for the Project
Integrate as One Team to deliver the Project
Work collaboratively together as a Team
ECAWP Project Overview
ECAWP Project Purpose
Create a new, local, safe, reliable, and drought-proof water supply for East County
Produce up to 30 percent of East County’s potable water supply
Increase water supply resilience and financial certainty related to imported water supply costs and wastewater treatment costs
Reduce discharge to the Pacific Ocean
Goals are Aspirational
Regulatory Compliance Seamless Integration Design Excellence Efficient Pricing Schedule Efficiencies Innovation High Functioning, Integrated
& Collaborative Team
ECAWP Project Description
A water supply project implementing Surface Water Augmentation (SWA)
Treating 15 MGD of wastewater
● Padre Dam
● City of El Cajon
● County of San Diego
Producing 11.5 MGD of advanced treated water for SWA at Lake Jennings
● Supply to R. M. Levy WTP
Package #2 Components
AWP Pipeline
DechlorinationFacility
Cl
New 24 inch AWP Pipeline Approximately 54,000 ft long ~49,000 ft of open-cut ~2,600 ft of above-grade ~2,300 ft of trenchless Rock excavation Welded Steel Pipe
New Dechlorination Facility Located at El Monte Pump Station siteNew Lake Jennings Inlet Rock water feature
Lake Jennings Inlet
Communities Affected
Pipeline route:● City of Santee
● County of San Diego
● Community of Lakeside
● Lake Jennings
Community considerations:● Coordination to minimize temporary
construction impacts
● Scheduling and sequencing of work incorporating community input
● Communication and outreach
Locations of Special Interest
San Diego River Crossing at Lakeside Ave.● Crosses SR67 between Lakeside Ave. and Vine St.
● Trenchless construction method expected
● Permitting
Undeveloped Land west of El Monte Road● Crosses between Mapleview St. and El Monte Road
● Potential for challenging geotechnical conditions
Lake Jennings● Pipeline extends up hillside, along Flume Trail, &
through tunnel
● Potential for challenging geotechnical conditions
● Coordination with State Historic Preservation Officer and Historic Preservation Specialist for tunnel portion
Flume Trail
Proposed pipeline alignment is on Helix land with an easement granted to the County for the Flume Trail
Above ground pipeline evaluated due to geotechnical and site constraints● Possible anchor/saddling requirements
Construction activities along a portion of the Flume Trail
Coordination with the County DPR during final design of the pipeline
Flume Trail Photos
RFQ Key Points
Procurement Overview
Best Value Selection Process
● Two-Step Process (RFQ/RFP)
Phase 1: Design and Pre-construction Services
● Advance design, schedule, and cost estimate
● Cost estimate developed in a transparent and open-book manner
● Establish a GMP
Phase 2: Final Design and Construction Services
● All scope performed by the Design-Builder after GMP
Coordination Between Packages
Package 1: WRF-AWP-Solids
RFQ/RFP
Design
Const.
Startup
Package 2: AWP Pipeline-Dechlorination-Lake Jennings Inlet
RFQ/RFP
Design
Const.
Startup
Package 3: IPS-EMGPS-EMG FM-Bypass
RFQ/RFP
Design
Const.
Startup
2019 2020 2021 2022 2023 2024 2025
Picking the Right Team
Focus on Selection Criteria
• Respond exactly as requested Facilitates Owner evaluation Method to the madness: DO NOT re-
order or re-think the procurement Do not simply regurgitate the
language in the RFQ
• Focus on Project Goals Demonstrate how your team will meet or
EXCEED each goal
• Graphics are nice, but . . . Substance over pretty visuals
• Avoid boilerplate language Project specific information
Stand Out From the Crowd
Address Deficiencies
• Add people/subs to your Team
Lack Experience?
• Show how you have created your Team
Haven’t worked together?
Considerations
Past Performance
Experience with Projects of Similar Scope and Complexity
Approach to issues that are specific to the Project
Safety Oriented
Effective Communicator
Collaborative Approach
Collaboration
Develop and promote a high functioning, trustworthy, communicative, collaborative, and integrated Team
Foster a collaborative environment for the entire Design-Build Team, JPA, and Project Stakeholders
Submittal Requirements
PossibleInterviews
SOQs Received
Response to RFIs
Two Step Progressive Design-Build Procurement
Pre-SOQ MeetingRFQ IssuedIndustry Day
Step 1
Shortlist
InterviewsProposals ReceivedRFIsProprietary
MeetingsRFP Issued
Step 2
Selection
3/18/20202/11/20201/24/2020 2/25/2020 4/15-16/2020
July 2020May 2020 June 2020 August 2020August 2020
April 21,2020
April 2020
Scoring Criteria
Responsiveness
Pass/Fail (Minimum Qualifications)
Evaluation Criteria and Weighting● Qualifications of Design-Build Team Members
and Key Personnel (35 Points)
● Project Experience (45 Points)
● Permitting Experience (10 Points)
● Safety (10 Points)
Required SOQ Organization
Volume 1
● Transmittal Letter
● Qualifications of Design-Build Team Members and Key Personnel
● Project Experience
● Permitting Experience
● Safety
Required SOQ Organization
Volume 2: Financial Submittal Requirements
● Financial Statements
● Material Changes in Financial Condition
● Financially Responsible Party Letter of Support
● Off-Balance Sheet Liabilities
● Surety Letter
Required SOQ Organization
Volume 3: Appendices and Forms
● Minimum Qualifications
● SOQ Forms
● Safety Record Documentation
● Resumes of Design-Build Team
● Identification of Projects Table
● Draft Term Sheet Comments
● Executed Teaming Agreements
● Addenda
Submittal Instructions
Due No Later Than 3 PM, PST on March 18, 2020
In Person
Engineering Counter in Padre Dam’s Administration Office9300 Fanita Parkway
Santee, CA 92071
Mailed
Padre Dam Municipal Water DistrictP.O. Box 719003
Santee, CA 92072ATTN: Clara Cornelius
Questions and Answers