AABC Commissioning Group AIA Provider Number 50111116 Owner Project Requirement (OPR) Workshop AIA Course Number CXENERGY1529 Jorge Torres Coto, PE, LEED AP BD+C, CxA Empirical Engineering April 29, 2015

Upload: vuongphuc

Post on 23-May-2018

217 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

AABC Commissioning GroupAIA Provider Number 50111116

Owner Project Requirement (OPR) WorkshopAIA Course Number CXENERGY1529

Jorge Torres Coto, PE, LEED AP BD+C, CxAEmpirical EngineeringApril 29, 2015

Page 2: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Credit(s) earned on completion of this course will be reported to AIA CES for AIA members. Certificates of Completion for both AIA members and non‐AIA members are available upon request.

This course is registered with AIA

CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner ofhandling, using, distributing, or dealing in any material or product._______________________________________Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.

Page 3: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

In this two-part session, attendees will engage in an Owners Project Requirement Workshop of a "fictitious" project, taking active participation as key stakeholders and experts. The workshop will guide the participants through the creation of an OPR for a specific project with all the team members: Owner, CxA, Contractors, O&M Personnel and others. The workshop will cover evaluation of requirements for documenting OPR for codes and rating systems, explore the importance and benefits of starting the commissioning process during the conceptual phase, and address the key aspects of any OPR as they relate to project goals.

CourseDescription

Page 4: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

LearningObjectives

1. Attendees will evaluate the current requirements for documenting the OPR both for mandatory and voluntary methods (code vs. rating systems).

2. Attendees will identify the importance of starting the Cx Process, thus the OPR, during the conceptual phase.

3. Attendees will participate in an actual OPR workshops.

4. Attendees will be able to identify the key aspects of any OPR and how the definition helps or interferes with meeting the projects goals.

At the end of the this course, participants will be able to:

Page 5: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

A Little history• Product of the Energy Crisis of 1973

• First draft in 1974

• Standard 90‐1975 issued on January 14, 1975

• In 2004 the Standard would also apply to:• Envelope• Mechanical Systems• Lighting Systems• Additions to Existing Buildings

• Excluded:• Low‐Rise Residential• Industrial• Manufacturing

• In 2007 the Standard would also apply to:• Envelope• HVAC• Domestic Hot Water• Lighting

Page 6: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

A Little history• Has been adopted into Code

• Is “Code” by reference in Certification schemes (worldwide)

• Requires Commissioning as part of the Completion Requirements in section 6.7.2.4

Page 7: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,
Page 8: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

A Little history• ASHRAE Guideline 1 pubished in 1989

• NIBS / ASHRAE Guideline 0 published in 2005

GUIDELINE = Best Practices

STANDARD = Min. Requirements

Guidelines CANNOT be utilized in Standards (per ASHRAE)

Page 9: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

ASHRAE 202ASHRAE Standard 202

The Commissioning Process for Buildings and Systems

Page 10: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

DEFINITIONS

•A quality focused process for enhancing the delivery of a Project.

•The process focuses upon verifying and documenting that the facility and all of its systems and assemblies are planned, designed, installed, tested, operated, and maintained to meet the OWNER’S PROJECT REQUIREMENTS.

ASHRAE’s definition of Commissioning Process per Guideline 0 and Standard 202

Page 11: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

DEFINITIONS

•The advancement of an installation from the stage of static completion to full working order to specified requirements

• It includes the setting to work of an installation, the regulation (TAB) of the system and the fine tuning of the system.

CIBSE’s definition of Commissioning per Commissioning Code M ‐Management

Page 12: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

RESPONSIBILITIES

•The building owner has statutory duty to ensure compliance with the requirements of Part L. 

• It is therefore essential that they ensure that the construction programmeincorporates a sufficient time element to enable commissioning to be competed prior to handover.

CIBSE’s importance of the Commissioning Process

Page 13: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

RESPONSIBILITIES

•All works approved under Part L are required to be commissioned in accordance with the design intent.

CIBSE’s importance of the Commissioning Process

Page 14: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

DEFINITIONS

•The Commissioning Process assumes that the Owner, Programmers, Designers, Contractors, and Operations and Maintenance entities are fully accountable for the quality of their work.

ASHRAE’s importance of the Commissioning Process

Page 15: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

DEFINITIONS

•The Commissioning Process is adopted by the Owner and begins at the project inception and continues for the life of the facility.

ASHRAE’s importance of the Commissioning Process

Page 16: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

RESPONSIBILITIES

•At initiation of the Commissioning Process, the Owner is responsible for determining the scope of the Cx Plan (what systems and assemblies are to be included), selection of the CxTeam Leader, selection of the Cx Team, assigning Cx Team roles & responsibilities, establish the Cx budget, and providing direction of the CxTeam throughout the project.

ASHRAE’s importance of the Commissioning Process

Page 17: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 101

•Have you ever been given an Owner’s Project Requirement at the beginning of your Project?

•Have you ever written an Owner’s Project Requirements document prior to the Design Phase?

•Did you receive it or write it prior to Design Phase?

Page 18: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 101

• If you answered NO to any of the  questions, Did you encounter more problems than you expected?

•Do these problems reflect lack of proper definition from the Owner?

Page 19: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 101

•THINK LIKE AN OWNER•WHAT DO YOU WANT•HOW WILL IT WORK•EXPECTATIONS

RULES OF THE GAME

Page 20: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 101

•THINK LIKE AN OWNER•WHAT DO YOU WANT•HOW WILL IT WORK•EXPECTATIONS

RULES OF THE GAME

Page 21: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 101

•HOTEL / RESIDENTIAL / RETAIL PROJECT

• LOCATED IN GUADALAJARA, MEXICO

•33 STORY TOWER•COMMUNICATED TO EXISTING PARKING

•COMMUNICATED TO EXISTING SHOPPING CENTER

Think like an Owner, not an Engineer

Page 22: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 101

•OPR should:• Be prepared by the owner• Detail the functional requirements• Expectations of how it will be used and operated

Think like an Owner, not an Engineer

Page 23: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 101

•OPR:• Should include:

• Project goals• Performance criteria• Cost considerations• Benchmarks• Success criteria• Supporting information

Think like an Owner, not an Engineer

You have 10 min to write it down

Page 24: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

DEFINITIONS

•A written document that details the functional requirements of a project and the expectations of how it will be used and operated.

•These include: project goals, measurable performance criteria, cost considerations, benchmarks, success criteria, and supporting information.

ASHRAE’s definition of Owner’s Project Requirements per Guideline 0 and Standard 202

(aka Project Intent)

Page 25: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

RESPONSIBILITIES

•The Owner shall ensure development of the OPR as described in Chapter 6 of this Standard (202) prior to the development of the architectural program. 

•The Owner shall provide the final updated and approved OPR at substantial completion.

ASHRAE’s importance of the Commissioning Process per Standard 202

Page 26: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

MANDATORY vs 

VOLUNTARY

•ASHRAE 90.1• IECC Energy Code•CA Energy Code (Title 24)

What is the common denominator?

Page 27: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,
Page 28: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,
Page 29: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

MANDATORY vs 

VOLUNTARYWhat is the common denominator?

Page 30: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

MANDATORY vs 

VOLUNTARYWhat is the common denominator?

Page 31: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

MANDATORY vs 

VOLUNTARYHow do you check it?

Page 32: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

MANDATORY vs 

VOLUNTARYHow do you check it?

Page 33: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

COMMISSIONING PROCESS PHASES

•PRE‐DESIGN or PROJECT INITIATION

•DESIGN•CONSTRUCTION•OCCUPANCY & OPERATIONS

Per Standard 202 & Guideline 0

Page 34: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

COMMISSIONING PROCESS FLOWCHARTPer Standard 202 & Guideline 0

Page 35: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

PRE‐DESIGN orPROJECT INITIATION

Page 36: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

DESIGN

Page 37: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

CONSTRUCTION

Page 38: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

CONSTRUCTION

Page 39: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

OCCUPANCY AND OPERATIONS

Page 40: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

OWNER’S PROJECT REQUIREMENTS

•The team members are:• Owner (or representative)• Commissioning Authority• Programming professionals• Design professionals• Project manager• Construction manager• Contractors• O&M personnel• Tenants

Developing the document

Page 41: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

OWNER’S PROJECT REQUIREMENTS

• It is the basis from which all design, construction, acceptance and operational decisions are made.

• It should be a clear, concise and comprehensive document

•Should have information to help the project team properly plan, design, construct, operate and maintain systems and assemblies.

Developing the document

Page 42: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

OWNER’S PROJECT REQUIREMENTS

•CxA facilitates the development

• Input is gathered from all team members

•Each and all items on the OPR shall have defined performance and acceptance criteria

• If a benchmark is applicable to an item it shall be defined in specific terms and means of measurement

Developing the document

Page 43: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

OWNER’S PROJECT REQUIREMENTS

•Project schedule•Project budget•Cx process scope•Cx process budget•Project documentation requirements:

• Submittal format• Training material• Reports• Systems manual

The Document shall include

Page 44: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

OWNER’S PROJECT REQUIREMENTS

•Owner directive• Restrictions and limitations•User requirements•Occupancy requirements and schedules

• Training requirements•Warranty requirements• Benchmarking requirements•Operation and maintenance criteria that reflect the Owner’s expectations and capabilities and the realities of the facility type

The Document shall include

Page 45: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

OWNER’S PROJECT REQUIREMENTS

•Equipment and system maintainability expectations, including limitations of O&M personnel

•Quality requirements for materials & construction

•Allowable tolerance in facility system operation

•Energy efficiency goals•Environmental and sustainability goals

•Community requirements

The Document shall include

Page 46: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

OWNER’S PROJECT REQUIREMENTS

•Adaptability for future facility changes an expansion

• System integration requirements, especially across disciplines

•Health, hygiene, and indoor environment requirements

•Acoustical requirements•Vibration requirements• Seismic requirements•Accessibility requirements• Security requirements

The Document shall include

Page 47: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

OWNER’S PROJECT REQUIREMENTS

•Aesthetic requirements•Constructability requirements

•Communication requirements

•Applicable codes and standards

The Document shall include

Page 48: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

OWNER’S PROJECT REQUIREMENTS

• Input required from all key facility users and operators

•Nominal Group Technique workshops, interviews and surveys

Method for obtaining information and criteria

Page 49: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

NOMINAL GROUP TECHNIQUE

•Grab paper & pen individually•Use your flipchart• Bring out the subject to discuss• Clarify until everyone understands the subject

• Each team member writes down as many ideas as possible in a set period of time (5 to 10 minutes)

• Facilitator writes down what each member reads aloud

• Works to quiet out the more vocal team members

• Works to louden the quiet team members

• Creates more participation from ALL members

• Helps create more ideas

• Helps integrate new members more easily

• Helps with controversial or heated conflicts

Page 50: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

NOMINAL GROUP TECHNIQUE

•NO DISCUSSION IS ALLOWED• Ideas do not have to be what was written down (after a while they usually will not be)

•Member may pass their turn, and add ideas on a subsequent turn

•Now you can discuss each idea in turn

•Agreement is required from the originator of idea to change wording

• Discussion should be equally balanced among all ideas

• Facilitator should not allow discussion to turn into argument

• The primary purpose of the discussion is clarification.

• The discussion is not intended to resolve differences of opinion

Page 51: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

NOMINAL GROUP TECHNIQUE

• Ideas may be removed by unanimous agreement.

•Discussions will clarify meaning, explain logic or analysis.

• Discussion should be equally balanced among all ideas

• Facilitator should not allow discussion to turn into argument

• The primary purpose of the discussion is clarification.

• The discussion is not intended to resolve differences of opinion

Page 52: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

NOMINAL GROUP TECHNIQUE

•Prioritize the ideas using multivoting or list reduction

And now the most important part

Page 53: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

OWNER’S PROJECT REQUIREMENTS

1. Project schedule2. Project budget3. Cx process scope4. Cx process budget5. Project documentation 

requirements:

The Document shall include

Page 54: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 201

•Each member of the team shall perform a Role:• Owner• Operations & Maintenance Personnel• Design Team (Arch, Eng)• Construction Team (Contractors)• External Consultants (Specialists)

Page 55: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 201

•Utilize the NOMINAL GROUP TECHNIQUE

Page 56: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 201

•Define:• General Project Description• Key Owner Project Requirements• Project objectives• Functional uses• Occupancy requirements• Budget considerations and/or limitations

Page 57: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 201

•Define Performance Criteria:• General • Economic • User requirements• Construction process• Operations• Systems • Assemblies

Page 58: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 201

•General Project Description•Key Project Requirements

List what is important to the Owner (i.e. Certifications, Commissioning process, Energy, Water, etc.)

•Project ObjectivesAccessibility, maintainability, tolerances, miscellaneous goals, etc.

Page 59: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 201

•Functional Uses• Piggy back from the Architectural Programming Documents• Types of rooms• Area requirements• Lighting requirements• Acoustics• Thermal control, etc.

Page 60: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 201

•Occupancy Requirements• Full Time Employees• Visitors• Special Events• Schedules• Comfort• Health & hygiene

Page 61: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 201

•Budget considerations and limitations• In general• Different systems• For different specialties (Cx, consultants)• Operational• Maintenance• Utilities

Page 62: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 201

•Performance Criteria• General

• Quality requirements of systems and equipment• Community requirements• Acoustical requirements• Seismic requirements• Security• Aesthetics• Sustainability, etc.

Page 63: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 201

•Performance Criteria• Economic 

• Establish benchmarks for:• Operating costs• Life cycle costs• Energy use intensity (cooling, heating, pumps, lighting, etc.)• Water use• Office equipment

Page 64: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 201

•Performance Criteria• Construction Process

• Training requirements (who, what, how much, etc.)• Warranties (how much and for what)• Maintainability of equipment• Adaptability of systems

Page 65: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 201

•Performance Criteria• Operations 

• Experience requirements (of the personnel hired)• Establish benchmarks for:

• Warranties• Occupant complaints• Temperature variations• Availability of spare parts• Response time of warranty and service calls

Page 66: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 201

•Performance Criteria• Systems 

• Integrity• Efficiency

Page 67: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

Owner’s Project Requirements (OPR) 201

•Performance Criteria• Assemblies 

• Envelope• Etc.

Page 68: Owner Project Requirement (OPR) Workshop - … Workshop CxEner… · 3. Attendees will ... architectural program. ... • Lighting requirements • Acoustics • Thermal control,

This concludes The American Institute of Architects Continuing Education Systems Course

Jorge Torres Coto, PE, CxA