OVERVIEW OF THE
OPERATING REACTORS
BUSINESS LINE
July 7, 2016
Michael Johnson
Deputy Executive Director for
Reactor and Preparedness Programs
![Page 2: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/2.jpg)
Program Overview
Bill Dean
Director
Office of Nuclear Reactor
Regulation
2
![Page 3: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/3.jpg)
About Half of the NRC Staff
Works on Operating Reactors
3
FY2016 FTE
![Page 4: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/4.jpg)
About a Quarter of the NRC’s
Budgeted CS&T Supports
Operating Reactors
4
FY 2016 Contract
Support and Travel
Corporate Support, 208,512
Operating Reactors, 111,273
New Reactors, 32,914
Nuclear Materials Users, 23,368
Decommissioning and LLW, 9,266
Fuel Facilities, 5,995
Spent Fuel Storage and Transportation, 5,951
![Page 5: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/5.jpg)
NRC Conducts Thorough and
Responsive Oversight
• Conducted ~ 260,000 inspection
hours
• Completed 564 LAs and 547 OLTs
• Conducted 5 SITs
• Completed 8 supplemental
inspections
• Opened 231 and closed 243
allegation cases
5
![Page 6: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/6.jpg)
Activities that Enhance Safety
and Extend Plant Life
• Compliance with Fukushima Orders –
all 62 audits completed
– Mitigating Strategies – 68 units
– SFP Instrumentation – 89 units
– TI-191 Inspections – 6 sites
• Renewed Licenses
– Byron 1&2
– Davis Besse
– Braidwood 1&2
6
![Page 7: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/7.jpg)
Rule and Guidance Updates
Focusing on Safety Issues
• 15 Rulemaking Activities
– 2 Proposed Rules published
– 1 Advance Notice of Proposed Rulemaking
published
• Generic Correspondence
– 9 Information Notices issued
– 13 Regulatory Information Summaries
issued
– 1 Generic Letter issued
– 5 Regulatory Guides published
7
![Page 8: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/8.jpg)
The Staff Is Engaging the
Commission on Policy Issues
• Fukushima Tier 2 and 3 Papers
(SECY-15-0137, 16-0041, and
16-0074)
• Open Phase (SECY-16-0068)
• Digital I&C (SECY-16-0070)
• NRR/NRO Merger (SECY-16-0075)
8
![Page 9: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/9.jpg)
Major Licensing
Accomplishments
• Licensing and safe startup of Watts
Bar 2
• Issuing the SHINE construction permit
• Renewing licenses for 5 units
• Workload management
9
![Page 10: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/10.jpg)
Other Significant
Accomplishments
• Completing draft of CNS National
Report
• Improving the operator licensing
program
• Enhancing the Reactor Oversight
Process
• Closing generic issue on boiling
water reactor emergency core
cooling system suction (GI-193)10
![Page 11: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/11.jpg)
Several Technical Challenges
Face the Business Line
• Using risk insights in making decisions
• Enhancing safety focus of technical
reviews
• Implementing Digital I&C Action Plan
• Completing remaining Fukushima
activities
• Preparing for subsequent license
renewal
11
![Page 12: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/12.jpg)
Additional Focus on
Organizational Challenges
• Managing workload changes
• Restructuring NRR
• Potentially merging NRR and NRO
• Implementing enhancements to the
Reactor Oversight Process
12
![Page 13: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/13.jpg)
Licensing Topics
Anne Boland, Director
Division of Operating Reactor
Licensing
Office of Nuclear Reactor
Regulation
13
![Page 14: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/14.jpg)
14
Significant Reactor Licensing
Accomplishments
• Seamless transfer of Vermont Yankee,
Crystal River, and SONGS to
Decommissioning and Low Level
Waste Business Line
• Completion of complex licensing
actions (e.g., NFPA-805)
• Reduction of licensing actions > 12
months old
![Page 15: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/15.jpg)
15
1732
15431613
1314
1444
1197
1372
1269
1760
95%94%
93%
90%
96%
95%
87%
88%
95%
200
400
600
800
1000
1200
1400
1600
1800
75%
80%
85%
90%
95%
100%
2008 2009 2010 2011 2012 2013 2014 2015 2016
Completed LAs and OLTs LA 1 Year Timeliness LA 2 Year Timeliness
OLT 1 Year Timeliness OLT 2 Year Timeliness
Substantial Progress in Licensing
Timeliness and Completions
![Page 16: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/16.jpg)
Strengthened Workload
Management
• Applied additional resources
• Greater management oversight on
workflow process
– Periodic status meetings
– Lessons learned on specific
licensing actions
– Review of licensing and acceptance
review processes
16
![Page 17: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/17.jpg)
Updating Data Management and
Tools
• Replacement Reactor Program System
(RRPS)
• Procedure revision
• Workload forecasting - RIS 2015-16
17
![Page 18: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/18.jpg)
Revised Expectations to Staff
• Re-emphasized process adherence and
incorporated lessons learned
• Clarified process for requests for
additional information
– Draft SE prior to RAI issuance
– Consideration of alternatives
– Enhanced management involvement
– Review of responses for scope
changes
18
![Page 19: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/19.jpg)
Rebaselining – Efficiency Efforts
in Progress
• Eliminated commitment audits and
UFSAR Reviews
• 2.206 process enhancements
• Implementing electronic
correspondence and concurrence
• Streamlined briefing packages
19
![Page 20: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/20.jpg)
Changing Environment Creates
New Opportunities
• Aligning the organization for future work
• Continuing to identify licensing process
efficiencies in order to sustain
performance
• Harmonizing processes and procedures
between operating and new reactors
• Integrating greater use of risk insights
into processes and procedures
• Maintaining focus on safety, security, and
preparedness
20
![Page 21: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/21.jpg)
A Risk-Informed Approach for
Addressing Low Risk
Compliance Issues
Rob Elliott
Division of Safety Systems
Office of Nuclear Reactor
Regulation
21
![Page 22: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/22.jpg)
Continued Progress Integrating
Risk-Informed Decision-making
• Current risk-informed programs:
– Reactor Oversight Program
– Risk-informed completion time and
surveillance frequency control programs
– Notices of enforcement discretion
• Some licensing basis design issues
are not immediate safety concerns
• TS-driven urgency to resolve these
issues may not result in best solution
or use of staff and licensee resources
22
![Page 23: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/23.jpg)
Applying Risk-Informed Solutions
• Tornado Missile Protection:
– Generic problem identified
– Low probability event
– Significantly lower probability
of loss of safety function
– Timely compliance concerns
drove plant and NRC response
actions
• Solution:
– Enforcement Guidance
Memorandum (EGM) 2015-002
– Risk informed to allow
appropriate time to take
corrective actions
23
![Page 24: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/24.jpg)
A New Risk-Informed Regulatory
Tool is Under Consideration
• Applying TS completion times to low risk, low
safety-significant design issues can lead to
unnecessary regulatory burden
• Working group with staff from NRR, OGC, OE,
and the Regions
• Considering a new plant-specific process:
– Evaluation of risk, defense-in-depth, safety
margins, compensatory measures and risk
management actions
– Potential for enforcement discretion
• Stakeholder involvement during process
development
24
![Page 25: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/25.jpg)
Potential Benefits
• Implement timely corrective action
commensurate with safety significance
• Ensure continued safe operation
• Focus resources on safety significant
issues
• Complementary to existing regulatory
processes
• Consistent with existing Enforcement
Policy
25
![Page 26: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/26.jpg)
Next Steps
• Continue consideration of a new risk-
informed process that:
– addresses low risk/low safety significance
design issues affecting operability
– potentially utilizes enforcement discretion
– ensures safe operation while the licensee
implements corrective action
• Continued stakeholder engagement
• Keep Commission informed
26
![Page 27: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/27.jpg)
Regional Perspective
Len Wert, Deputy Regional
Administrator for Operations
Region II
27
![Page 28: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/28.jpg)
28
Regional Focus on Safety
• Maintaining Vigilance
• Identifying Issues
![Page 29: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/29.jpg)
29
ROP Provides Framework for
Assuring Safety
• Effective
Oversight
• Program
Refinement
• Reliability/
Consistency
![Page 30: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/30.jpg)
30
Regional Sites with Special
Focus
• Units in
Column 4
• Watts Bar 2
![Page 31: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/31.jpg)
31
Regional Implementation of
Specialized Inspections
• Fukushima
─ 14 TI 191 inspections planned or
completed
• Cyber Inspections
─ Milestone 8 inspections 2017
![Page 32: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/32.jpg)
32
Our Employees: Vital to Success
• Maintaining Capacity
and Expertise
• Resource Sharing
• Enhancing Flexibility
![Page 33: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/33.jpg)
33
Effectively Managing Change
• Changes:
─ Activities
─ Staffing and
Organization
• Employee
Engagement
![Page 34: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/34.jpg)
Ensuring Safety
Through Research
David L. Rudland, Branch Chief
Division of Engineering
Office of Nuclear Regulatory
Research
34
![Page 35: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/35.jpg)
35
Research Confirms Safety
Integrity
Analysis
Tools
Digital I&C
Thermal
Hydraulic
Analyses
Severe
Accident
Analyses
High Energy
Arc Faults
Flooding
![Page 36: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/36.jpg)
36
Implementing Re-Baselining
Alloy 52M
Weld Overlay
Part 50
Appendix G
Technical Basis
Weld Mitigation
Technical Basis
Reduced analyses
for evaluating new
techniques
Evaluate using
existing expertise
and experience
Continue to
Implement existing
requirements
Shed Impact Path Forward
Forgo plans to
update Appendix G
![Page 37: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/37.jpg)
Ensuring Piping Integrity
37
• PFM analyses not standardized
– Computer codes written for case
specific application
• 10 CFR 50, App A, GDC 4
– No active material degradation
– Leak-before-break (LBB)
– No quantitative probabilistic
solution available
![Page 38: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/38.jpg)
xLPR –Probabilistic Pressure
Boundary Integrity Software
Large Cooperative effort with
EPRINuclear-
grade Quality
Assurance
Modular for
flexibility
Technically vetted
Rigorous Verification
and Validation
Aligned with DOE
efforts
Developing Robust Analysis Tools
38
![Page 39: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/39.jpg)
xLPR
Leak-before-break
Prioritize Research Activities
Risk informed
ISIIntegrity-based relief
requests
Seismic loading on
integrity
Significance Determination
Process
Using xLPR to Ensure Safety
39
Near term use
Future use
![Page 40: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/40.jpg)
• Production version (2.0) to be
released in Aug 2016
– Currently undergoing verification
and validation
• xLPR maintenance program
under development
– Establishing a Users Group
• Future Plans
– LBB Sensitivity studies in 2017
– Regulatory guidance in 2018
Rolling Out xLPR Soon
40
![Page 41: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/41.jpg)
Security and Incident Response
Activities in Support of the
Business Line
James Andersen, Director
Cyber Security Directorate
Office of Nuclear Security and
Incident Response
41
![Page 42: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/42.jpg)
Cyber Security Regulatory
Structure Has Been Enhanced
• Staff has endorsed Nuclear Energy
Institute (NEI) guidance document, NEI
13-10, Revision 4
• Industry has implemented Milestones
1-7 of their cyber security plans
• Addressing generic inspection issues
42
![Page 43: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/43.jpg)
Additional Cyber Security
Enhancements Will Be
Implemented
• Preparing for Milestone 8, full
implementation of the cyber
requirements
• Engaging stakeholders to improve
consistency of implementation
• Issued cyber security notification
rule and guidance
43
![Page 44: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/44.jpg)
Improving Emergency
Preparedness Licensing
Effectiveness
• Working with NRR and the
industry
• Maintaining licensing action
submittal plan as a living
document
• Identifying problem areas and the
need for additional guidance
44
![Page 45: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/45.jpg)
Summary
• Executing a business line with
has large breadth and scope
• Responding to challenging
environment with creativity and
dedication
• Ensuring safety and security for
the future
45
![Page 46: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/46.jpg)
46
List of Acronyms
• CFR – Code of Federal
Regulations
• CNS – Convention on Nuclear
Safety
• CS&T – Contract support and
travel
• DOE – Department of Energy
• EPRI – Electric Power Research
Institute
![Page 47: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/47.jpg)
47
List of Acronyms (cont’d)
• FTE – Full Time Equivalent
• FY – Fiscal Year
• GDC – General Design Criteria
• I&C - Instrumentation and Control
• ISI – In-service Inspection
![Page 48: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/48.jpg)
48
List of Acronyms (cont’d)
• LA – Licensing Action
• LBB – Leak Before Break
• LOCA – Loss of Coolant Accident
• MBDBE – Mitigation of Beyond
Design Basis Event
• NFPA – National Fire Protection
Association
![Page 49: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/49.jpg)
49
List of Acronyms (cont’d)
• NRO – Office of New Reactors
• NRR – Office of Nuclear Reactor
Regulation
• OE – Office of Enforcement
• OGC – Office of General Counsel
• OLT – Other Licensing Task
![Page 50: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/50.jpg)
50
List of Acronyms (cont’d)
• PFM – Probabilistic Fracture
Mechanics
• PWSCC – Primary Water Stress
Corrosion Cracking
• RAI – Request for Additional
Information
• RIS – Regulatory Issue Summary
![Page 51: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/51.jpg)
51
List of Acronyms (cont’d)
• ROP – Reactor Oversight Process
• SE – Safety Evaluation
• SFP – Spent Fuel Pool
• SIT – Special Inspection Team
• SONGS – San Onofre Nuclear
Generating Station
![Page 52: OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE...Jul 07, 2016 · released in Aug 2016 –Currently undergoing verification and validation •xLPR maintenance program under development](https://reader034.vdocuments.mx/reader034/viewer/2022050110/5f4798b401d51e3bca3d346d/html5/thumbnails/52.jpg)
52
List of Acronyms (cont’d)
• TI – Temporary Instruction
• TS – Technical Specifications
• UFSAR – Updated Final Safety
Analysis Report
• xLPR – Extremely Low Probability
of Rupture