overview of roads management system (rms) use …transportconferencekenya.org/proceedings/use of rms...

18
OVERVIEW OF ROADS MANAGEMENT SYSTEM (RMS) USE IN KENYA Presentation By: ENG. JULIUS K. GAKUBIA; MANAGER-MAINTENANCE (KERRA) REPUBLIC OF KENYA MINISTRY OF TRANSORT AND INFRASTRUCTURE INTERNATIONAL CONFERENCE ON TRANSPORT & ROAD RESEARCH MOMBASA – KENYA, MARCH 2016

Upload: hamien

Post on 15-May-2018

230 views

Category:

Documents


2 download

TRANSCRIPT

OVERVIEW OF ROADS MANAGEMENT SYSTEM (RMS) USE IN KENYA

Presentation By:

ENG. JULIUS K. GAKUBIA; MANAGER-MAINTENANCE (KERRA)

REPUBLIC OF KENYA MINISTRY OF TRANSORT AND INFRASTRUCTURE

INTERNATIONAL CONFERENCE ON TRANSPORT & ROAD RESEARCH

MOMBASA – KENYA, MARCH 2016

Presentation Overview Introduction………………………………….....3RMS Structure……………………………….….4RMS Functionalities..…………………………13Standard Reports.……………………………14RMS Challenges .…………………………….17

2

INTRODUCTIONPreparation of Work plans, progress and Expenditure

reports by the then MoR and KRB was in most cases uncoordinated and resulting in various reports for the same content in different formats for different purpose.

The then Provincial and District Roads Engineers’ found themselves searching paper files, compiling and transmitting the same data many times. This meant that the reports often contained different figures for the same period of time and many inaccuracies.

3

INTRODUCTION – Cont’dIn 2004 and in an effort to address some of these

challenges, the then MoR, KRB and the Consultants under the SIDA Funded Roads 2000 Nyanza Programme began to formulate a system of compiling the data and producing the required reports in a customised system. This customised system is what over the years has evolved to what is now the RMS.

The first version of RMS(RMMS 3.0) in Nyanza Province, currently the Counties of Kisumu, Siaya, Homabay, Kisii and Migori. RMMS was also used in Roads 2000 Central Kenya Phase 1 (AfD)

4

INTRODUCTION – Cont’dKeRRA adopted the RMMS as it’s Planning,

Management and reporting tool for all maintenance works in FY2009/10. KeNHA & KURA started using the system in FY2010/11.

The system has undergone improvements up to the current version 5.0. With available local capacities this has not been a challenge over the years

Going forward it is our intention to make the system web based and integrate it with GIS data.

5

RMS Structure/Basic Tables

LVSR STATUS PRESENTATION - MOTI

6 Road Inventory

RMS Structure/Basic Tables

LVSR STATUS PRESENTATION - MOTI

7 Road Sections

RMS Structure/Basic Tables

LVSR STATUS PRESENTATION - MOTI

8 Planning/Administrative Units

RMS Structure/Basic Tables

LVSR STATUS PRESENTATION - MOTI

9 Road Maintenance Activity List/Planning Rates

RMS Functions

LVSR STATUS PRESENTATION - MOTI

10 I. Preparation of Work Plans

RMS Functions

LVSR STATUS PRESENTATION - MOTI

11 II: Packaging of Contracts

RMS Functions

LVSR STATUS PRESENTATION - MOTI

12 III: Contract Details Input

RMS Functions

LVSR STATUS PRESENTATION - MOTI

13 IV: Progress Reporting

RMS Reports

LVSR STATUS PRESENTATION - MOTI

14 V: Standard Reports

RMS Reports

LVSR STATUS PRESENTATION - MOTI

15 VII: Sample Work Plan Report

RMS Reports16 VII: Sample Interim Payment Certificate

RMS Challenges

The current RMS as structured cannot support the following activities;Needs assessment for the Road NetworksStrategic Planning, that includes budgeting for

Development and Maintenance PurposesData collection and updating;We are in the process of pursuing options available to incorporate some of these modules et al..

17

18