overliner or landfill mining?

30
Building lifetime relationships with our clients and employees. Overliner or Landfill Mining? Best Approach for a Landfill Expansion for an Unlined Landfill Prentiss A. Shaw, P.E. Martin L. Ryan, P.E., P.P. Patrick M. Bell, P.E. Global Waste Symp: June 25, 2014

Upload: cornerstone-environmental

Post on 07-May-2015

416 views

Category:

Engineering


3 download

DESCRIPTION

Best Approach for a Landfill Expansion for an Unlined Landfill

TRANSCRIPT

Page 1: Overliner or Landfill Mining?

Building lifetime relationships with our clients and employees.

Overliner or Landfill Mining?

Best Approach for a Landfill Expansion for an Unlined Landfill

Prentiss A. Shaw, P.E. Martin L. Ryan, P.E., P.P.

Patrick M. Bell, P.E.

Global Waste Symp: June 25, 2014

Page 2: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential 2

Potential of Expanding Unlined Landfills

400 MILLON CUBIC YARDS OF AIRSPACE WITHOUT A SINGLE FACILITY EXPANDING FROM CURRENTLY

PERMITTED AREA

Page 3: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential 3

Introduction

Why Redevelop an Unlined Landfill?

• Capture Available Airspace w/o Lateral Expansion

Two approaches:

1. Overliner: Install containment system above waste and possibly overfill connecting adjacent cells (piggyback)

2. Landfill Mining: Excavate waste and install traditional baseliner system on soil

Page 4: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential 4

Introduction

How do you decide which approach to pursue?

Five Key Decision Making Criteria:

1. Site Life Remaining

2. Groundwater Compliance

3. Existing Grades

4. Age of Waste

5. Economics

Page 5: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential 5

Challenges for Overliner & Landfill Mining

• Comfort Level of Digging into Old Waste

• Unique Design Elements

• Unique Construction Elements

Page 6: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Gaining that Comfort Level

Conduct an Extensive Test Pit Program to Determine Waste Characterization & Delineation of Limits

1. Waste Disruption Permit

2. Numerous test pits at varying depths

3. Testing/Monitoring - BMP, Exposure (O2/LEL/H2S), Composition

4. Visual – decomposition, soil percentage, odor, moisture, perched conditions

Page 7: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Design – Overliner

• Differential Settlement

• Cut-Fill Analysis

• Subgrade Gas

• Liner Tie-ins

• Infrastructure Access /Relocate

Page 8: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Design – Landfill Mining

• Exposed Waste Slopes

• Bottom of waste uncertainty

More traditional baseliner design

• Liner Tie-ins

• Infrastructure Access /Relocate

Page 9: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Construction – Overliner

• Varying Subgrade Conditions

• Defined Waste Excavation – Not Mass Excavation

Soil, Alt Fill, or Waste

Waste

Page 11: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

OCEAN COUNTY LANDFILL CASE STUDY

Page 12: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Introduction

• Ocean County Landfill (OCLF) is a privately owned and operated sanitary landfill located in Manchester Township, New Jersey, approximately 50 miles east of Philadelphia, and 70 miles south of New York City

• The landfill serves the 33 municipalities comprising the County of Ocean

• Area of 915 square miles

• Population of 580,000

Page 13: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Early Analysis of Landfill Reutilization

• Height restrictions of 175*No vertical exp.

• Wetlands & Neighbors*No Lateral exp.

• Focus for expansion then shifted to a 60-acre parcel known as the Existing Landfill.

Page 14: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Test Pit Program

• Waste Disruption Permit – 2006

• Test Pit Program 2007

• Goal: Waste characterization & Cap soil delineation

Key Takeaways:

Biochemical Methane Potential (BMP) testing concludes that waste was largely decomposed

Cover soils above and below the liner were thicker than anticipated

Large amount of daily cover soil used during waste placement

No perched leachate encountered

Page 15: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Overliner Design

DESIGN ELEMENTS:

• Steeper slopes of leachate collection lines to ensure positive drainage of the overliner.

• A rather complex subgrade design with leachate laterals draining the subcells south to north, and west to east in areas.

• Installation of subgrade gas collectors in the Original Landfill waste remaining in place.

• A construction staging plan with a goal of balancing and timing the cuts to fills to the greatest extent possible.

Pursuing overliner design - Sustainable Landfill Project (SLP)

Reasons for that decision:

• Most efficient way to redevelop without large scale waste disruption

• 6,000,000 CY of additional airspace

• Still unknowns about waste mass

Page 16: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

A Change of Direction…?

Acquisition and excavation of adjacent “orphaned” landfill

• Manchester Township Landfill

• 600,000 CY of material excavated from 1/2009 – 4/2010

Key Takeaways:

Odor from the excavation activities was negligible.

Extensive air monitoring revealed no health and safety concerns.

Leachate and stormwater issues were easily managed by proper construction staging.

No extensive nuisance control measures were necessary for issues such as vectors, dust or litter.

A large quantity of cover soil was used during the landfilling operations, some of which was able to be recovered for reuse at OCLF.

Page 17: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Back to the Drawing Board: Landfill Mining Considered

Reasons for that decision:

• Comfort level achieved• Overliner needed over 1

million CY of fill material• Ability to change Operational

Sequence• Need for daily cover

Results:

• Additional 1,250,000 CY of waste to be placed in the same envelope of airspace

• 1.5 years of additional site life• 2,000,000 CY of cover soil anticipated

to be generated• The construction cost of an overliner at

Ocean County Landfill is $16.51 per cubic yard while the construction cost of LF mining is $13.99 per cubic yard.

• Mitigate potential liability of an unlined landfill

• More typical cell subgrade design with standard slopes

Page 18: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Status of SLP Redevelopment

The Permitting Process:

• Pre-Application Meeting with NJDEP – 6/2012

• Waste Disruption Permit required for excavation

• Minor Solid Waste Facility Permit Mod. required

• Waste Disruption Permit approved by NJDEP 3/2013

• Solid Waste Permit Mod. approved by NJDEP 11/2013

Page 19: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Status of SLP Redevelopment (cont’d)

OCLF and Cornerstone are currently finalizing construction plans for Phase 1 of the Waste Excavation Project, which entails excavation and screening of approximately 1,500,000 CY, and incorporating temporary capping of exposed slopes, interim gas collection, and necessary stormwater controls.

• OCLF has also filed a permit modification to the facility’s Title V Air Operating Permit, to authorize the large scale screening operation that will occur during the waste excavation activities.

• It is anticipated that excavation activities will commence in Summer 2014, with the first phase of SLP baseliner construction projected for 2020.

Page 20: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

THE DECISION PROCESS

Page 21: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Key Evaluation Criteria

Site Life Remaining

GW Compliance

Existing Grades

Age of Waste

Economics

Landfill Mining Overliner

Decision Process

Page 22: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Remaining Site Life

Greater than 5 YRS

Landfill Mining

Less than 5 YRS

Overliner

Page 23: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Groundwater Monitoring Compliance

Poor Compliance Record

Landfill Mining

Good Compliance Record

Overliner Landfill Mining

Page 24: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Existing Grading of Unlined Cell

Relatively Flat

Landfill Mining

Greater than 10 Percent

Overliner

Page 25: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Age of Existing Waste

Greater Than 20 Years Less Than 20 Years

Landfill MiningOverliner

Page 26: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Economics

• Revenue Additional Airspace• Value Recovered Soil• Value Recyclables Recovered• Avoided Costs• Cost per CY of Airspace Gained

Landfill Mining

• Total Cost of Construction

Overliner

Page 27: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

OCLF Decision Process

Greater than 5 YRS

Landfill Mining

Good Compliance Record

Overliner

Landfill Mining

Relatively Flat

Landfill Mining

Greater Than 20 Years

Landfill Mining

• Revenue Additional Airspace• Value Recovered Soil• Avoided Costs• Cost per CY of Airspace Gained

Landfill Mining

Economics

Site Life GW Compliance Grades

Age of Waste

Page 28: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Factors that could push an owner towards an Overliner

• Need airspace now

• “Dirt-rich” site

• Conducive grading

• Contractual issues for large projects

• Regulatory/Permitting issues (cap/GCCS/air)

• High BMP  

• Stability concerns

• Financial considerations and results of cost/benefit analysis

Page 29: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

Factors that could push an owner towards LF Mining

• Positive site life outlook

• “Dirt-poor” site

• GW issues

• Overliner differential settlement

• Use of own forces (excavation/screening)

• Financial considerations and results of cost/benefit analysis

Page 30: Overliner or Landfill Mining?

© 2014 Cornerstone. All rights reserved. | Confidential

THANK YOU! You can contact me:

Prentiss A. Shaw, P.E.Cornerstone Environmental Group, LLC

[email protected]

Phone: (845) 695-0202