OUR SCHOOLS OUR FUTURE
OUR SCHOOLS OUR FUTURE
Bringing our vision to life
CREATE APPROVE FUND PLAN IMPLEMENT
Phase 110-12 years
Future Phases 12 years &
beyond
Our work is focused on Phase 1, but with an understanding that there will still need to be work in future phases to address all needs.
Based on available funding, master plan needs to be split into multiple phases.
Project Management Team MEP concerns.
• IMPLEMENTATION PLAN• PROJECT VERIFICATION• TRANSFER/DELIVERY
EQUITY
EFFICIENCY EXCELLENCE
Framework for Success
Goals:• Immediately address highest-
priority items (safety, accessibility, temporary classrooms)
• Group for cost-efficiencies• Prioritize work, equitably• Fits within funding capacity• Fits within local design &
construction market capacity
34Building projects
Prioritization
IMMEDIATE
Design begins in
3-6 months
EARLYINTER-
MEDIATELONG-TERM
186 work-in-progress
Design begins in
6-12 monthsDesign begins in
1-5 yearsDesign begins in
5+ years
IMMEDIATE
6-12 months 1 – 5 years 5+ years
EARLY INTER-MEDIATE
LONG-TERM
186 work-in-progress
• Safety & security upgrades and HLS work
• Replace portable classrooms with additions at• Fairview• Black Hawk • Sandburg
• Accessibility and program equity upgrades at• Butler • Dubois • Harvard Park
• Additions to replace portable classrooms and expand cafeterias at middle schools• Washington • Jefferson
Prioritization
• Franklin • Grant
IMMEDIATE
3-6 months 1 – 5 years 5+ years
EARLY INTER-MEDIATE
LONG-TERM
186 in-progress
• Lanphier High: Replace Edison wing and comprehensive renovation• Southeast High: Auditorium, locker room, kitchen lab, restrooms and HLS• Springfield High: Secure entry, roofing, restrooms and HLS• New Laketown / Hazel Dell Elementary
Prioritization
IMMEDIATE
3-6 months 6-12 months
• New Owen Marsh Elementary• Southeast High Fieldhouse• Springfield High Fieldhouse• Lanphier High Fieldhouse
5+ years
EARLY INTER-MEDIATE
LONG-TERM
186 in-progress Prioritization
• HLS at Lindsay and Southern View• Paving and playgrounds at
Graham, Iles and Lindsay
IMMEDIATE
3-6 months 6-12 months 1 – 5 years
EARLY INTER-MEDIATE
LONG-TERM
186 in-progress
• Springfield High comprehensive renovation• Wanless upgrades for alternative programming• Lincoln Magnet upgrades• Later HLS work
Prioritization
IMMEDIATE
$44,200,000
EARLYINTER-
MEDIATELONG-TERM
186 work in-progress
$90,700,000 $106,700,000 $3,800,000
Prioritization
Goals:• Define equitable programs within
educational groupings (PK-5, MS, HS)• Refine scope and budgets• Set district-wide standards for
building materials and systems
Educational Space StandardsPrincipals Workshop
Educational Space StandardsWhat spaces should be standard?
Elementary Schools• Classrooms• Media Center• Fine and Applied Arts• Special Education• Athletics / Phys Ed• Learning Labs• Admin & Faculty Support• Health Services• Dining and Food Service• Community Spaces• Facilities Management
Middle Schools• Classrooms• Collaboration• Media Center• Fine and Applied Arts• STEM/STEAM• Special Education• Athletics / Phys Ed• Learning Labs• Welcome / Reception• Admin & Faculty Support• Health Services• Dining and Food Service• Community Spaces• Facilities Management Spaces
High Schools• Up next!
Systems & Material StandardsDistrict standards for all work in master plan
Architecture• Procurement and Contract • General Requirements• Existing Conditions• Concrete • Masonry• Metals • Wood & Plastics • Thermal & Moisture Protection • Doors and Windows • Finishes • Specialties • Equipment • Furnishings • Special Construction • Conveying Systems
Engineering• Fire Suppression • Plumbing Systems • HVAC Systems • Electrical • Communications • Electronic Safety & Security • Sitework
Goals:• Clearly communicate project details • Provide consistency and equity
through course of master plan implementation
• Develop pool of qualified architects through RFQ (in progress)
Plan Design Documents Bid Construction
BUILDING PROCESS
Project MgmtTeam
Architectural Pool
(selection in progress)
Transfer Package Contents
• Our Schools Our Future Master Plan Overview– District Mission– Master Plan Vision Narrative– Work to Date– Educational Drivers & Design
Considerations– District Building Portfolio
• Master Schedules– by Package– by Building
PROJECT SPECIFIC• Project Summary• Building Program• Project Budget• Design Intent
– Design & Scope Diagrams– HPD/IDNR Plan
• Project Schedule• Existing Conditions (site &
building plans)• Systems and Materials
Standards
Fairview Elementary
Design teams (from architectural pool) will: • Engage principals, staff and students in the final development of designs• Community can provide feedback on proposed design solutions• Generate final solutions for District approval• Generate final solutions within project definition parameters, for district approval• Complete documents, bidding and construction administration
PACKAGES: 1-19
IMMEDIATE EARLY INTERMEDIATE LONG-TERM
• 1: Security Cameras• 2: Secure Entry Work• 3: Early HLS • 4: HVAC Controllers• 5: Butler, Dubois,
Harvard Park Elem• 6: Fairview, Blackhawk,
Sandburg Elem• 7: Washington,
Jefferson MS• 8: Franklin, Grant MS
• 9: LHS Edison Wing, Reno &Field House
• 10: New Laketown/ Hazel Dell
• 12: SHS / SSHS Renovations
• 11: New Owen Marsh• 13: Lindsay• 14: SHS Reno & Field
House• 15: SSHS Field House• 18: Paving &
Playgrounds• 19: HLS at Southern
View
• 16: Wanless & Lincoln Magnet
• 17: Later HLS
NEXT STEPS• Transfer Packages #1-8 Complete
by Dec 2• Transfer Packages #9-19 Complete by
March 2020• Selection of Architectural Pool by Dec 2• Communications Plan & Support• Telling Our Story