oss 2022593 using del note in miro does not work for planned del cost (1)

4
8/9/2019 OSS 2022593 Using Del Note in MIRO Does Not Work for Planned Del Cost (1) http://slidepdf.com/reader/full/oss-2022593-using-del-note-in-miro-does-not-work-for-planned-del-cost-1 1/4 SAP Knowledge Base Article Symptom Using transaction MIRO to post planned delivery costs via option "2 Delivery Note" does not work - system does not return planned delivery costs items. Environment l Materials Management (MM) l SAP R/3 l SAP R/3 Enterprise 4.7 l SAP ERP Core Component l SAP ERP l SAP enhancement package for SAP ERP l SAP enhancement package for SAP ERP, version for SAP HANA Reproducing the Issue 1. Create a PO with material items and planned delivery costs: 2. Create Goods Receipt, filling both fields "Delivery Note" and "Bill of Lading" with different values: 2022593 - Using option Delivery Note in MIRO does not work for Planned Delivery Costs Version 1 Validity: 26.05.2014 - active Language English

Upload: nc27770

Post on 01-Jun-2018

307 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: OSS 2022593 Using Del Note in MIRO Does Not Work for Planned Del Cost (1)

8/9/2019 OSS 2022593 Using Del Note in MIRO Does Not Work for Planned Del Cost (1)

http://slidepdf.com/reader/full/oss-2022593-using-del-note-in-miro-does-not-work-for-planned-del-cost-1 1/4

SAP Knowledge Base Article

Symptom

Using transaction MIRO to post planned delivery costs via option "2 Delivery Note" does not work - system does not return planned deliverycosts items.

Environment l Materials Management (MM)l SAP R/3l SAP R/3 Enterprise 4.7l SAP ERP Core Componentl SAP ERPl SAP enhancement package for SAP ERPl SAP enhancement package for SAP ERP, version for SAP HANA

Reproducing the Issue

1. Create a PO with material items and planned delivery costs:

2. Create Goods Receipt, filling both fields "Delivery Note" and "Bill of Lading" with different values:

2022593 - Using option Delivery Note in MIRO does not work for Planned Delivery Costs

Version 1 Validity: 26.05.2014 - active Language English

Page 2: OSS 2022593 Using Del Note in MIRO Does Not Work for Planned Del Cost (1)

8/9/2019 OSS 2022593 Using Del Note in MIRO Does Not Work for Planned Del Cost (1)

http://slidepdf.com/reader/full/oss-2022593-using-del-note-in-miro-does-not-work-for-planned-del-cost-1 2/4

3. Go to transaction MIRO > choose option '2 Delivery Note' > enter Delivery Note number from the posted Goods Receipt > check that onlymaterial items will return:

Cause

l Functionality of getting the right selection when you select Delivery Note + Planned delivery costs is not programmed in the system.l Planned delivery costs are associated with the Purchase Order, not with the goods receipt at the time of MIGO. For this reason, even with the

indicator "GR-Bsd IV" set in the purchase order, there is no effect on the planned delivery costs at the time of MIRO when choosing DeliveryNote option.

Resolution

There are 3 solutions to obtain Planned Delivery Costs items during MIRO processing, which are:

1. Delivery costs for a Purchase Order:

All open delivery costs for the specified purchase order are listed.

Steps to apply the solution: 1.1 Go to transaction MIRO.1.2 Choose option '1 Purchase Order/Scheduling Agreement' .1.3 Choose '2 Planned delivery costs'.1.4 Enter PO number:

2. Delivery costs for a Vendor: All open delivery costs for the specified vendor are listed.You can limit the selection by entering 'From' and/or 'To' dates; the list then only contains the delivery costs incurred after/within the specifieddate(s).

Additionally, please, read SAP Note 360419 that explains "The invoice relates to several purchase orders with different vendors. You enterseveral PO numbers on the Further Assignment Criteria. screen and select delivery cost items. The system displays only the delivery costitems for the vendor of the first purchase order entered. Delivery cost items for other vendors are not displayed.".

Steps to apply the solution: 2.1 Go to transaction MIRO.2.2 Choose option '5 Vendor' :

2.3 Click at button 'More allocation criteria'.2.4 Enter Vendor, Plant and Dates. Here we are only using delivery as Invoice item:

Page 3: OSS 2022593 Using Del Note in MIRO Does Not Work for Planned Del Cost (1)

8/9/2019 OSS 2022593 Using Del Note in MIRO Does Not Work for Planned Del Cost (1)

http://slidepdf.com/reader/full/oss-2022593-using-del-note-in-miro-does-not-work-for-planned-del-cost-1 3/4

2.5 Click at button 'Adopt':

3. Delivery costs for a Bill of Lading: When goods are received, an external bill of lading number can be entered in the Bill of Lading field - so, you can use this number asreference. The system then lists all the delivery costs for one bill of lading.

Steps to apply the solution: 3.1 Go to transaction MIRO.3.2 Choose option '3 Bill of Lading' .3.3 Enter Bill of Lading number:

See Also

SAP Note 311496 - Default values planned delivery costsSAP Note 360419 - MIRO: Selection of delivery costs relating to purchase orderSAP Note 768573 - MIRO: Del. costs settlmnt w/ ref. to bill of ladng/del. noteSAP Note 1744361 - MIRO: Reference to delivery note is deletedSAP Note 1770914 - MIRO: Delivery note search and data element documentationSAP Note 1817506 - MIR4: Update termination when selecting delivery note

Keywords

ECC, plann., plann, del., del, custos, custo, planejados, planejado, selection, settlement, ladng, freight, frete

Header Data

Product

Released On 28.05.2014 17:03:27Release Status Released to CustomerComponent MM-IV-LIV-CRE Entry MIROPriority NormalCategory How To

Product Product VersionSAP ERP All versions

SAP ERP Core Component All versions

SAP R/3 All versions

SAP R/3 Enterprise 4.7 All versions

SAP enhancement package for SAP ERP All versions

SAP enhancement package for SAP ERP, version for SAP HANA All versions

Page 4: OSS 2022593 Using Del Note in MIRO Does Not Work for Planned Del Cost (1)

8/9/2019 OSS 2022593 Using Del Note in MIRO Does Not Work for Planned Del Cost (1)

http://slidepdf.com/reader/full/oss-2022593-using-del-note-in-miro-does-not-work-for-planned-del-cost-1 4/4

References

This document refers to:

CSS SAP Notes 1817506 MIR4: Update termination when selecting delivery note 1770914 MIRO: Delivery note search and data element documentation 1744361 MIRO: Reference to delivery note is deleted

768573 MIRO: Del. costs settlmnt w/ ref. to bill of ladng/del. note 360419 MIRO: Selection of delivery costs relating to purchase order 311496 Default values planned delivery costs