orange vista high school phase - val verde … project is located in perris, ... basketball and...

5
Val Verde Unified School District 975 W. Morgan Street Perris, CA 92571 ORANGE VISTA HIGH SCHOOL PHASE I Monthly Project Progress Report January 2015 Prepared by: 9339 Feron Blvd. Rancho Cucamonga, CA 91730

Upload: vonga

Post on 10-May-2018

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: ORANGE VISTA HIGH SCHOOL PHASE - Val Verde … project is located in Perris, ... Basketball and Volleyball. ... Orange Vista High School – Phase 1

Val Verde Unified School District

975 W. Morgan Street

Perris, CA 92571

ORANGE VISTA

HIGH SCHOOL PHASE I

Monthly Project Progress Report

January 2015

Prepared by:

9339 Feron Blvd.

Rancho Cucamonga, CA 91730

Page 2: ORANGE VISTA HIGH SCHOOL PHASE - Val Verde … project is located in Perris, ... Basketball and Volleyball. ... Orange Vista High School – Phase 1

Val Verde Unified School District

Orange Vista High School – Phase 1

Monthly Project Progress Report – January 2015

I. Project Location and Description

The project is located in Perris, CA within the boundaries in the southeast corner of the Val

Verde Unified School District. The construction is currently underway on the 61.6 acre site

located at the intersection of Orange Ave. and Evans Road. Phase 1 of the high school

construction consists of the following:

Building 100: 27,789 sf New 2-story Administration building

Building 200: 12,422 sf New Kitchen/Cafeteria building

Building 300: 6,000 sf New Health/Science building

Building 400: 6,650 sf New Multi-Use building

Building 500: 43,292 sf New 2-story Classroom building

Building 800: 800 sf New Utility building

The onsite work consists of installation of a 2,200 L.F. Double Box Culvert and Onsite Piping

System for storm water control, the removal and relocation of a 36” domestic waterline,

installation of Shade Structures, Parking Lots, Bio Retention Basins, Irrigation and Landscape

Systems, a Football Field & Track venues including an accessible shot put and discus area, pole

vault, triple jump/long jump, 2 Baseball Fields, 2 Softball Fields, a Soccer Field and several hard

court play areas for Tennis, Basketball and Volleyball. The offsite work consists of constructing the

36” domestic water line from points of connection on Dunlap Dr. and Orange Ave., street

improvements along Orange Ave., Evans Rd. and a driveway on Lemon Ave. to serve the student

parking lots.

II. Project Progress

During the month of January, the construction progressed as follows:

• Administration Building: Framing completed and pick-up work is in progress; Roof and floor

sheeting completed. Mechanical, Electrical, Plumbing, & Fire Suppression Piping completed at

1st floor and in progress at 2nd floor and Roof area.

• Kitchen/Cafeteria Building: Poured and finished the slab on grade; Erected Structural Steel and

completed wall framing & joisting. Sheeting and Roof framing and Electrical rough in are in

progress.

• Health-Science Building: Work at this location is on hold pending changes made by the District that require DSA review.

• Multi-Use Building: Poured footings and roughing in Electrical & Plumbing at slab on grade.

• Two-Story Classroom Building: Erected Structural Steel and poured concrete at the base of

columns.

• Utility Building: Placed and finished footings and slab on grade. • Site Work: Underground electrical work is in progress. Completed chain link fence posts

placement, subgrade preparation, sand placement, formwork, rebar placement and concrete

placement at the Tennis Courts. Completed irrigation sleeving, electrical underground work

and Curb & Gutter placement at North Parking Lot.

2

Page 3: ORANGE VISTA HIGH SCHOOL PHASE - Val Verde … project is located in Perris, ... Basketball and Volleyball. ... Orange Vista High School – Phase 1

Val Verde Unified School District

Orange Vista High School – Phase 1

Monthly Project Progress Report – January 2015

II. Project Progress – Continued from page 2

• Offsite work: No work performed offsite this month.

III. Project Budget

The Post-Bid Construction Budget was set at $39,144,825.30 with a Change Order Contingency

set at 10% or $3,914,482 for a total of $43,059,307.30.

IV. Project Schedule

The project schedule indicated a starting date of March 20, 2014 and a substantial completion

date of March 8, 2016. The High School is scheduled to open for its first session in August 2016.

Governmental delays continue for the Offsite Connections and Improvements, however, the

overall project completion date remains on schedule. Through the month of January the project

is 27.3% complete.

V. 30-Day Forecast

During the month of February the construction is anticipated as follows:

• Administration Building: Start setting doors and window frames, roofing, wrapping exterior

building, plastering, and finish rough Electrical, Plumbing, and Mechanical work.

• Kitchen/Cafeteria Building: Complete roof framing and sheeting. Continue Electrical rough in and start Plumbing, Fire Suppression, & Mechanical rough in.

• Health-Science Building: Due to District implemented changes, work has been put on hold

pending review by DSA.

• Multi-Use Building: Start Electrical and Plumbing underground work at slab on grade. Place and finish concrete slab on grade.

• Two-Story Classroom Building: Start framing work

• Utility Building: Start framing and place and finish concrete slab for switchgear

• Site Work: Start Electrical underground work and Install irrigation sleeves at South Parking

Lot. Place and finish concrete curbs and gutters at South Parking Lot. Start underground

electrical work at Ball Fields.

• Offsite work: 36” Waterline will continue through the production process.

VI. Construction Summary

1. Start Date: March 20, 2014

2. Substantial Completion Date: March 08, 2016

3. Time Elapsed (from the start date): 317 Calendar Days

4. Time Remaining: 402 Calendar Days

5. School Opens: August 2016

3

Page 4: ORANGE VISTA HIGH SCHOOL PHASE - Val Verde … project is located in Perris, ... Basketball and Volleyball. ... Orange Vista High School – Phase 1

Val Verde Unified School District

Orange Vista High School – Phase 1

Monthly Project Progress Report – January 2015

VII. Progress Photos

Bldg. 100 Elevator Installation Bldg. 100 Progress Photo

Bldg. 100 Mechanical Rough In at 1st Floor Bldg. 100 Mechanical Rough In at Roof Top

Bldg. 200 SOG Placement Bldg. 200 Framing Progress

4

Page 5: ORANGE VISTA HIGH SCHOOL PHASE - Val Verde … project is located in Perris, ... Basketball and Volleyball. ... Orange Vista High School – Phase 1

Val Verde Unified School District

Orange Vista High School – Phase 1

Monthly Project Progress Report – January 2015

VII. Progress Photos – Continued

Bldg. 400 Footings Bldg. 500 Structural Steel

Sand Placement @Tennis Courts Bldg. 800 Slab on Grade

Aerial View of the Site 5