ORANGE VISTA
HIGH SCHOOL PHASE I
Monthly Project Progress Report
January 2015
Prepared by:
9339 Feron Blvd.
Rancho Cucamonga, CA 91730
Val Verde Unified School District
Orange Vista High School – Phase 1
Monthly Project Progress Report – January 2015
I. Project Location and Description
The project is located in Perris, CA within the boundaries in the southeast corner of the Val
Verde Unified School District. The construction is currently underway on the 61.6 acre site
located at the intersection of Orange Ave. and Evans Road. Phase 1 of the high school
construction consists of the following:
Building 100: 27,789 sf New 2-story Administration building
Building 200: 12,422 sf New Kitchen/Cafeteria building
Building 300: 6,000 sf New Health/Science building
Building 400: 6,650 sf New Multi-Use building
Building 500: 43,292 sf New 2-story Classroom building
Building 800: 800 sf New Utility building
The onsite work consists of installation of a 2,200 L.F. Double Box Culvert and Onsite Piping
System for storm water control, the removal and relocation of a 36” domestic waterline,
installation of Shade Structures, Parking Lots, Bio Retention Basins, Irrigation and Landscape
Systems, a Football Field & Track venues including an accessible shot put and discus area, pole
vault, triple jump/long jump, 2 Baseball Fields, 2 Softball Fields, a Soccer Field and several hard
court play areas for Tennis, Basketball and Volleyball. The offsite work consists of constructing the
36” domestic water line from points of connection on Dunlap Dr. and Orange Ave., street
improvements along Orange Ave., Evans Rd. and a driveway on Lemon Ave. to serve the student
parking lots.
II. Project Progress
During the month of January, the construction progressed as follows:
• Administration Building: Framing completed and pick-up work is in progress; Roof and floor
sheeting completed. Mechanical, Electrical, Plumbing, & Fire Suppression Piping completed at
1st floor and in progress at 2nd floor and Roof area.
• Kitchen/Cafeteria Building: Poured and finished the slab on grade; Erected Structural Steel and
completed wall framing & joisting. Sheeting and Roof framing and Electrical rough in are in
progress.
• Health-Science Building: Work at this location is on hold pending changes made by the District that require DSA review.
• Multi-Use Building: Poured footings and roughing in Electrical & Plumbing at slab on grade.
• Two-Story Classroom Building: Erected Structural Steel and poured concrete at the base of
columns.
• Utility Building: Placed and finished footings and slab on grade. • Site Work: Underground electrical work is in progress. Completed chain link fence posts
placement, subgrade preparation, sand placement, formwork, rebar placement and concrete
placement at the Tennis Courts. Completed irrigation sleeving, electrical underground work
and Curb & Gutter placement at North Parking Lot.
2
Val Verde Unified School District
Orange Vista High School – Phase 1
Monthly Project Progress Report – January 2015
II. Project Progress – Continued from page 2
• Offsite work: No work performed offsite this month.
III. Project Budget
The Post-Bid Construction Budget was set at $39,144,825.30 with a Change Order Contingency
set at 10% or $3,914,482 for a total of $43,059,307.30.
IV. Project Schedule
The project schedule indicated a starting date of March 20, 2014 and a substantial completion
date of March 8, 2016. The High School is scheduled to open for its first session in August 2016.
Governmental delays continue for the Offsite Connections and Improvements, however, the
overall project completion date remains on schedule. Through the month of January the project
is 27.3% complete.
V. 30-Day Forecast
During the month of February the construction is anticipated as follows:
• Administration Building: Start setting doors and window frames, roofing, wrapping exterior
building, plastering, and finish rough Electrical, Plumbing, and Mechanical work.
• Kitchen/Cafeteria Building: Complete roof framing and sheeting. Continue Electrical rough in and start Plumbing, Fire Suppression, & Mechanical rough in.
• Health-Science Building: Due to District implemented changes, work has been put on hold
pending review by DSA.
• Multi-Use Building: Start Electrical and Plumbing underground work at slab on grade. Place and finish concrete slab on grade.
• Two-Story Classroom Building: Start framing work
• Utility Building: Start framing and place and finish concrete slab for switchgear
• Site Work: Start Electrical underground work and Install irrigation sleeves at South Parking
Lot. Place and finish concrete curbs and gutters at South Parking Lot. Start underground
electrical work at Ball Fields.
• Offsite work: 36” Waterline will continue through the production process.
VI. Construction Summary
1. Start Date: March 20, 2014
2. Substantial Completion Date: March 08, 2016
3. Time Elapsed (from the start date): 317 Calendar Days
4. Time Remaining: 402 Calendar Days
5. School Opens: August 2016
3
Val Verde Unified School District
Orange Vista High School – Phase 1
Monthly Project Progress Report – January 2015
VII. Progress Photos
Bldg. 100 Elevator Installation Bldg. 100 Progress Photo
Bldg. 100 Mechanical Rough In at 1st Floor Bldg. 100 Mechanical Rough In at Roof Top
Bldg. 200 SOG Placement Bldg. 200 Framing Progress
4
Val Verde Unified School District
Orange Vista High School – Phase 1
Monthly Project Progress Report – January 2015
VII. Progress Photos – Continued
Bldg. 400 Footings Bldg. 500 Structural Steel
Sand Placement @Tennis Courts Bldg. 800 Slab on Grade
Aerial View of the Site 5