<Insert Picture Here> Primavera Risk Analysis Wesley Gillette Senior Product Manager

Upload: igor-cucek

Post on 29-Nov-2014

175 views

Category:

Documents


11 download

TRANSCRIPT

Page 1: Oracle Primavera Risk Analysis Overview (Full)1

<Insert Picture Here>

Primavera Risk Analysis

Wesley GilletteSenior Product Manager

Page 2: Oracle Primavera Risk Analysis Overview (Full)1

Agenda

• Value of Project Risk Analysis

• Solution Overview

• Summary

© 2009 Oracle Corporation

Page 3: Oracle Primavera Risk Analysis Overview (Full)1

<Insert Picture Here>

Value of Risk Analysis

Page 4: Oracle Primavera Risk Analysis Overview (Full)1

© 2009 Oracle Corporation

Who needs Risk Analysis?

• Executives/Program Managers– Need to assess bid viability– Need to assess risk during project selection

• Project Managers/Project Controls– Need to understand the impact of risk on the project schedule

and cost– Need to perform a cost/benefit analysis on mitigation plans– Need to satisfy a contractual/regulatory requirement for risk

analysis

Page 5: Oracle Primavera Risk Analysis Overview (Full)1

© 2009 Oracle Corporation

Benefits of Effective Risk Analysis

• Increased confidence in bids & project selection

• Increased awareness of project assumptions

• Increased project success by enabling better project management

Page 6: Oracle Primavera Risk Analysis Overview (Full)1

<Insert Picture Here>

Solution Overview

Page 7: Oracle Primavera Risk Analysis Overview (Full)1

© 2009 Oracle Corporation

Primavera Risk Analysis

• Methodology based risk analysis • Schedule Quality Assessment• Comprehensive Risk Modeling• Qualitative and quantitative Risk Register• Standard Analysis Reports• Scenario Comparison Reports• Risk Adjusted Schedule and Cash flow Report

Page 8: Oracle Primavera Risk Analysis Overview (Full)1

Risk Analysis Methodology

Risk Planning

Risk Identification

Risk Assessment

Risk Response

Risk Reporting

© 2009 Oracle Corporation

Based on: PMBOK Chapter 11, APM PRAM Guide, AS/NZ S4360

Page 9: Oracle Primavera Risk Analysis Overview (Full)1

Schedule Quality Assessment

Verify schedule quality by checking for scheduling best

practices

© 2009 Oracle Corporation

A poor quality schedule affects the quality and

reliability of the risk analysis

Select the checks to run against the schedule

Page 10: Oracle Primavera Risk Analysis Overview (Full)1

Schedule Quality Assessment

© 2009 Oracle Corporation

Creates an interactive report with links to drill

down into the detail

Page 11: Oracle Primavera Risk Analysis Overview (Full)1

Risk Modeling

• Estimate Uncertainty– Distributions (e.g. 3pt estimate)– User defined fields– Templates

• Risk Events– Discrete events which may impact the project schedule– Modeled with a probability and impact

© 2009 Oracle Corporation

Page 12: Oracle Primavera Risk Analysis Overview (Full)1

Appling Risk Uncertainty to Schedule

© 2009 Oracle Corporation

Can note the assumptions & rationale supporting the

assessmentCan assess uncertainty

at a summary level

Apply estimate uncertainty consistently

through the use of templates

Page 13: Oracle Primavera Risk Analysis Overview (Full)1

Building Risk Register – Qualitative Assessment

© 2009 Oracle Corporation

Priložnosti in nevarnosti

Izdelava in kvalitativna ocena tveganj

Page 14: Oracle Primavera Risk Analysis Overview (Full)1

Building Risk Register – Quantitative Assessment

© 2009 Oracle Corporation

Then assess risks quantitatively

Page 15: Oracle Primavera Risk Analysis Overview (Full)1

Building Risk Register – Linking Risks to Schedule

© 2009 Oracle Corporation

Mapiranje vpliva tveganj na aktivnosti in celoten

plan

Kvalitativna ocena tveganj

Page 16: Oracle Primavera Risk Analysis Overview (Full)1

© 2009 Oracle Corporation

Building Scenarios & Running the Analysis

Create risk scenarios

Run the analysis and view the reports

Page 17: Oracle Primavera Risk Analysis Overview (Full)1

Running the Analysis

• Monte Carlo simulation– Random simulation of probable outcomes– Not a guarantee of what will happen

• Sensitivity Analysis– Identifies what is likely to drive the project schedule

© 2009 Oracle Corporation

Page 18: Oracle Primavera Risk Analysis Overview (Full)1

Results – Analyzing Contingency

© 2009 Oracle Corporation

View results for the entire project or selected WBS

or activity

Shows probability of success and contingency

needed

See the impact of risk on project & activity dates

and cost

Page 19: Oracle Primavera Risk Analysis Overview (Full)1

Results – Project Drivers

© 2009 Oracle Corporation

Criticality Index shows how often activities are on

the critical path

Alternate critical path activities

Page 20: Oracle Primavera Risk Analysis Overview (Full)1

Results – Project Drivers

© 2009 Oracle Corporation

Displays schedule & cost drivers

(sensitivity analysis)

Drivers can be schedule uncertainty or risk events

Page 21: Oracle Primavera Risk Analysis Overview (Full)1

Evaluating Risk Response Plans

• Understand pre-response results

• Develop Risk Response plan

• Analyze

• Cost/Benefit analysis

• Track and report status

© 2009 Oracle Corporation

Page 22: Oracle Primavera Risk Analysis Overview (Full)1

Risk Register – Mitigation Planning

© 2009 Oracle Corporation

Pre-Mitigation: Current assessment

of the risk

Mitigation: What can be done to reduce the

impact the risk

Post-Mitigation: Assessment of the risk after mitigation

Page 23: Oracle Primavera Risk Analysis Overview (Full)1

Results – Updated Contingency

© 2009 Oracle Corporation

Evaluate the change in contingency from pre-

mitigated scenario

Page 24: Oracle Primavera Risk Analysis Overview (Full)1

© 2009 Oracle Corporation

Results – Scenario Comparison

Primerjava učinkov tveganj in učinkov zmanjševanja tveganj

Page 25: Oracle Primavera Risk Analysis Overview (Full)1

Results – Probabilistic Cash Flow

Shows the difference between what was planned

and what is probable

Shows the impact of uncertainty and risks on cash flow and resources Probabilistic spend

curves

25© 2009 Oracle Corporation

Page 26: Oracle Primavera Risk Analysis Overview (Full)1

Results – Risk Adjusted Schedule

© 2009 Oracle Corporation

Compare deterministic schedule vs. a

probabilistic schedule(e.g. P50 & P80)

Page 27: Oracle Primavera Risk Analysis Overview (Full)1

<Insert Picture Here>

Summary

© 2009 Oracle Corporation

Page 28: Oracle Primavera Risk Analysis Overview (Full)1

© 2009 Oracle Corporation

Primavera Risk Analysis

• Methodology based risk analysis • Schedule Quality Assessment• Comprehensive Risk Modeling• Qualitative and quantitative Risk Register• Standard Analysis Reports• Scenario Comparison Reports• Risk Adjusted Schedule and Cash flow Report

Page 29: Oracle Primavera Risk Analysis Overview (Full)1

Benefits of Effective Risk Analysis

• Increased confidence in bids & project selection– Validation of schedule– Appropriate contingency at project level (not activity level)

• Increased awareness of project assumptions– Realistic project schedule– Common understanding of project schedule and risks

• Increased project success by enabling better project management– Understanding of project drivers– Validate risk response plans

© 2009 Oracle Corporation