Primavera Risk Analysis
Wesley GilletteSenior Product Manager
Agenda
• Value of Project Risk Analysis
• Solution Overview
• Summary
© 2009 Oracle Corporation
<Insert Picture Here>
Value of Risk Analysis
© 2009 Oracle Corporation
Who needs Risk Analysis?
• Executives/Program Managers– Need to assess bid viability– Need to assess risk during project selection
• Project Managers/Project Controls– Need to understand the impact of risk on the project schedule
and cost– Need to perform a cost/benefit analysis on mitigation plans– Need to satisfy a contractual/regulatory requirement for risk
analysis
© 2009 Oracle Corporation
Benefits of Effective Risk Analysis
• Increased confidence in bids & project selection
• Increased awareness of project assumptions
• Increased project success by enabling better project management
<Insert Picture Here>
Solution Overview
© 2009 Oracle Corporation
Primavera Risk Analysis
• Methodology based risk analysis • Schedule Quality Assessment• Comprehensive Risk Modeling• Qualitative and quantitative Risk Register• Standard Analysis Reports• Scenario Comparison Reports• Risk Adjusted Schedule and Cash flow Report
Risk Analysis Methodology
Risk Planning
Risk Identification
Risk Assessment
Risk Response
Risk Reporting
© 2009 Oracle Corporation
Based on: PMBOK Chapter 11, APM PRAM Guide, AS/NZ S4360
Schedule Quality Assessment
Verify schedule quality by checking for scheduling best
practices
© 2009 Oracle Corporation
A poor quality schedule affects the quality and
reliability of the risk analysis
Select the checks to run against the schedule
Schedule Quality Assessment
© 2009 Oracle Corporation
Creates an interactive report with links to drill
down into the detail
Risk Modeling
• Estimate Uncertainty– Distributions (e.g. 3pt estimate)– User defined fields– Templates
• Risk Events– Discrete events which may impact the project schedule– Modeled with a probability and impact
© 2009 Oracle Corporation
Appling Risk Uncertainty to Schedule
© 2009 Oracle Corporation
Can note the assumptions & rationale supporting the
assessmentCan assess uncertainty
at a summary level
Apply estimate uncertainty consistently
through the use of templates
Building Risk Register – Qualitative Assessment
© 2009 Oracle Corporation
Priložnosti in nevarnosti
Izdelava in kvalitativna ocena tveganj
Building Risk Register – Quantitative Assessment
© 2009 Oracle Corporation
Then assess risks quantitatively
Building Risk Register – Linking Risks to Schedule
© 2009 Oracle Corporation
Mapiranje vpliva tveganj na aktivnosti in celoten
plan
Kvalitativna ocena tveganj
© 2009 Oracle Corporation
Building Scenarios & Running the Analysis
Create risk scenarios
Run the analysis and view the reports
Running the Analysis
• Monte Carlo simulation– Random simulation of probable outcomes– Not a guarantee of what will happen
• Sensitivity Analysis– Identifies what is likely to drive the project schedule
© 2009 Oracle Corporation
Results – Analyzing Contingency
© 2009 Oracle Corporation
View results for the entire project or selected WBS
or activity
Shows probability of success and contingency
needed
See the impact of risk on project & activity dates
and cost
Results – Project Drivers
© 2009 Oracle Corporation
Criticality Index shows how often activities are on
the critical path
Alternate critical path activities
Results – Project Drivers
© 2009 Oracle Corporation
Displays schedule & cost drivers
(sensitivity analysis)
Drivers can be schedule uncertainty or risk events
Evaluating Risk Response Plans
• Understand pre-response results
• Develop Risk Response plan
• Analyze
• Cost/Benefit analysis
• Track and report status
© 2009 Oracle Corporation
Risk Register – Mitigation Planning
© 2009 Oracle Corporation
Pre-Mitigation: Current assessment
of the risk
Mitigation: What can be done to reduce the
impact the risk
Post-Mitigation: Assessment of the risk after mitigation
Results – Updated Contingency
© 2009 Oracle Corporation
Evaluate the change in contingency from pre-
mitigated scenario
© 2009 Oracle Corporation
Results – Scenario Comparison
Primerjava učinkov tveganj in učinkov zmanjševanja tveganj
Results – Probabilistic Cash Flow
Shows the difference between what was planned
and what is probable
Shows the impact of uncertainty and risks on cash flow and resources Probabilistic spend
curves
25© 2009 Oracle Corporation
Results – Risk Adjusted Schedule
© 2009 Oracle Corporation
Compare deterministic schedule vs. a
probabilistic schedule(e.g. P50 & P80)
<Insert Picture Here>
Summary
© 2009 Oracle Corporation
© 2009 Oracle Corporation
Primavera Risk Analysis
• Methodology based risk analysis • Schedule Quality Assessment• Comprehensive Risk Modeling• Qualitative and quantitative Risk Register• Standard Analysis Reports• Scenario Comparison Reports• Risk Adjusted Schedule and Cash flow Report
Benefits of Effective Risk Analysis
• Increased confidence in bids & project selection– Validation of schedule– Appropriate contingency at project level (not activity level)
• Increased awareness of project assumptions– Realistic project schedule– Common understanding of project schedule and risks
• Increased project success by enabling better project management– Understanding of project drivers– Validate risk response plans