Id EDT Task Name Duração Início Término

1 A Definition 56 hrs Sex 3/9/99 Seg 13/9/99

2 A.PL Project Planning 24 hrs Sex 3/9/99 Ter 7/9/99

3 A.PL.BEG Begin Project Planning 8 hrs Sex 3/9/99 Sex 3/9/99

4 A.CR.010 Establish Scope, Objectives, and Approach 0 hrs Seg 6/9/99 Seg 6/9/99

5 A.CR.020 Define Control and Reporting Strategies, Standards, and Proce 0 hrs Seg 6/9/99 Seg 6/9/99

6 A.CR.030 Establish Management Plans 0 hrs Seg 6/9/99 Seg 6/9/99

7 A.WM.010 Define Work Management Strategies, Standards, and Procedures 0 hrs Seg 6/9/99 Seg 6/9/99

8 A.WM.020 Establish Workplan 0 hrs Seg 6/9/99 Seg 6/9/99

9 A.WM.030 Establish Finance Plan 0 hrs Seg 6/9/99 Seg 6/9/99

10 A.RM.010 Define Resource Management Strategies, Standards, and Procedu 0 hrs Seg 6/9/99 Seg 6/9/99

11 A.RM.020 Establish Staffing and Organization Plan 0 hrs Seg 6/9/99 Seg 6/9/99

12 A.RM.025 Create Project Orientation Guide 0 hrs Seg 6/9/99 Seg 6/9/99

13 A.RM.030 Implement Organization 0 hrs Seg 6/9/99 Seg 6/9/99

14 A.RM.040 Establish Physical Resource Plan 0 hrs Seg 6/9/99 Seg 6/9/99

15 A.RM.050 Establish Infrastructure 0 hrs Seg 6/9/99 Seg 6/9/99

16 A.QM.010 Define Quality Management Strategies, Standards, and Procedur 0 hrs Seg 6/9/99 Seg 6/9/99

17 A.CM.010 Define Configuration Management Strategies, Standards, and Pr 0 hrs Seg 6/9/99 Seg 6/9/99

18 A.PL.END End Project Planning 8 hrs Ter 7/9/99 Ter 7/9/99

19 A.BP Business Process Architecture 8 hrs Seg 6/9/99 Seg 6/9/99

20 A.BP.BEG Start Definition Phase Execution 8 hrs Seg 6/9/99 Seg 6/9/99

21 A.BP.010 Define Business and Process Strategy 0 hrs Seg 6/9/99 Seg 6/9/99

22 A.BP.020 Catalog and Analyze Potential Changes 0 hrs Seg 6/9/99 Seg 6/9/99

23 A.BP.030 Determine Data Gathering Requirements 0 hrs Seg 6/9/99 Seg 6/9/99

24 A.BP.040 Develop Current Process Model 0 hrs Seg 6/9/99 Seg 6/9/99

25 A.BP.050 Review Leading Practices 0 hrs Seg 6/9/99 Seg 6/9/99

26 A.BP.060 Develop High-Level Process Vision 0 hrs Seg 6/9/99 Seg 6/9/99

27 A.BP.070 Develop High-Level Process Designs 0 hrs Seg 6/9/99 Seg 6/9/99

28 A.RD Business Requirements Definition 0 hrs Seg 6/9/99 Seg 6/9/99

29 A.RD.010 Identify Current Financial and Operating Structure 0 hrs Seg 6/9/99 Seg 6/9/99

30 A.RD.020 Conduct Current Business Baseline 0 hrs Seg 6/9/99 Seg 6/9/99

31 A.TA Application and Technical Architecture 0 hrs Seg 6/9/99 Seg 6/9/99

3/9

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

7/

6/9

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

Q S S D S T5/Set/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 1

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 2: Oracle Implementation Project Template 1226594305077229 8

Id EDT Task Name Duração Início Término

32 A.TA.010 Define Architecture Requirements & Strategy 0 hrs Seg 6/9/99 Seg 6/9/99

33 A.TA.020 Identify Current Technical Architecture 0 hrs Seg 6/9/99 Seg 6/9/99

34 A.TA.030 Develop Preliminary Conceptual Architecture 0 hrs Seg 6/9/99 Seg 6/9/99

35 A.MD Module Design and Build 0 hrs Seg 6/9/99 Seg 6/9/99

36 A.MD.010 Define Application Extension Strategy 0 hrs Seg 6/9/99 Seg 6/9/99

37 A.CV Data Conversion 0 hrs Seg 6/9/99 Seg 6/9/99

38 A.CV.010 Define Data Conversion Requirements & Strategy 0 hrs Seg 6/9/99 Seg 6/9/99

39 A.DO Documentation 0 hrs Seg 6/9/99 Seg 6/9/99

40 A.DO.010 Define Documentation Requirements & Strategy 0 hrs Seg 6/9/99 Seg 6/9/99

41 A.DO.020 Define Documentation Standards and Procedures 0 hrs Seg 6/9/99 Seg 6/9/99

42 A.DO.030 Prepare Glossary 0 hrs Seg 6/9/99 Seg 6/9/99

43 A.TE Business System Testing 0 hrs Seg 6/9/99 Seg 6/9/99

44 A.TE.010 Define Testing Requirements and Strategy 0 hrs Seg 6/9/99 Seg 6/9/99

45 A.PT Performance Testing 0 hrs Seg 6/9/99 Seg 6/9/99

46 A.PT.010 Define Performance Testing Strategy 0 hrs Seg 6/9/99 Seg 6/9/99

47 A.AP Adoption and Learning 24 hrs Seg 6/9/99 Qui 9/9/99

48 A.AP.010 Define Executive Project Strategy 0 hrs Seg 6/9/99 Seg 6/9/99

49 A.AP.020 Conduct Initial Project Team Orientation 0 hrs Seg 6/9/99 Seg 6/9/99

50 A.AP.030 Develop Project Team Learning Plan 0 hrs Seg 6/9/99 Seg 6/9/99

51 A.AP.040 Prepare Project Team Learning Environment 0 hrs Seg 6/9/99 Seg 6/9/99

52 A.AP.050 Conduct Project Team Learning Events 0 hrs Seg 6/9/99 Seg 6/9/99

53 A.AP.060 Develop Business Unit Managers' Readiness Plan 0 hrs Seg 6/9/99 Seg 6/9/99

54 A.AP.070 Develop Project Readiness Roadmap 0 hrs Seg 6/9/99 Seg 6/9/99

55 A.AP.080 Develop & Execute Communication Campaign 0 hrs Seg 6/9/99 Seg 6/9/99

56 A.AP.END End Definition Phase Execution 8 hrs Qui 9/9/99 Qui 9/9/99

57 A.CT.CTR Phase Control 16 hrs Ter 7/9/99 Qua 8/9/99

58 A.CT.BEG Begin Phase Control 8 hrs Ter 7/9/99 Ter 7/9/99

59 A.CT.SUM Phase Control 0 hrs Ter 7/9/99 Ter 7/9/99

60 A.CT.RES Unallocated Reserve 0 hrs Ter 7/9/99 Ter 7/9/99

61 A.CT.END End Phase Control 8 hrs Qua 8/9/99 Qua 8/9/99

62 A.CO.COMP Phase Completion 16 hrs Sex 10/9/99 Seg 13/9/99

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

6/

7/

Q S S D S T5/Set/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 2

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 3: Oracle Implementation Project Template 1226594305077229 8

Id EDT Task Name Duração Início Término

63 A.CO.BEG Begin Phase Completion 8 hrs Sex 10/9/99 Sex 10/9/99

64 A.CR.080 Secure Client Phase Acceptance 0 hrs Sex 10/9/99 Sex 10/9/99

65 A.RM.080 Release Staff 0 hrs Sex 10/9/99 Sex 10/9/99

66 A.RM.090 Release Physical Resources 0 hrs Sex 10/9/99 Sex 10/9/99

67 A.QM.050 Perform Quality Assesment 0 hrs Sex 10/9/99 Sex 10/9/99

68 A.CM.060 Audit Key Deliverables 0 hrs Sex 10/9/99 Sex 10/9/99

69 A.CO.END End Phase Completion 8 hrs Seg 13/9/99 Seg 13/9/99

70 B Operations Analysis 64 hrs Qua 8/9/99 Sex 17/9/99

71 B.PL.PLAN Phase Planning 16 hrs Qua 8/9/99 Qui 9/9/99

72 B.PL.BEG Begin Phase Planning 8 hrs Qua 8/9/99 Qua 8/9/99

73 B.PL.SUM Review and Revise Project Plans 0 hrs Qua 8/9/99 Qua 8/9/99

74 B.PL.END End Phase Planning 8 hrs Qui 9/9/99 Qui 9/9/99

75 B.BP Business Process Architecture 8 hrs Sex 10/9/99 Sex 10/9/99

76 B.BP.BEG Start Operations Analysis Execution 8 hrs Sex 10/9/99 Sex 10/9/99

77 B.BP.080 Develop Future Process Model 0 hrs Sex 10/9/99 Sex 10/9/99

78 B.RD Business Requirements Definition 0 hrs Sex 10/9/99 Sex 10/9/99

79 B.RD.030 Establish Process and Mapping Summary 0 hrs Sex 10/9/99 Sex 10/9/99

80 B.RD.040 Gather Business Volumes & Metrics 0 hrs Sex 10/9/99 Sex 10/9/99

81 B.RD.050 Gather Business Requirements 0 hrs Sex 10/9/99 Sex 10/9/99

82 B.RD.060 Determine Audit and Control Requirements 0 hrs Sex 10/9/99 Sex 10/9/99

83 B.RD.070 Identify Business Availability Requirements 0 hrs Sex 10/9/99 Sex 10/9/99

84 B.RD.080 Identify Reporting and Information Access Requirements 0 hrs Sex 10/9/99 Sex 10/9/99

85 B.BR Business Requirements Mapping 0 hrs Sex 10/9/99 Sex 10/9/99

86 B.BR.010 Analyze High-Level Gaps 0 hrs Sex 10/9/99 Sex 10/9/99

87 B.BR.020 Prepare Mapping Environment 0 hrs Sex 10/9/99 Sex 10/9/99

88 B.BR.030 Map Business Requirements 0 hrs Sex 10/9/99 Sex 10/9/99

89 B.BR.040 Map Business Data 0 hrs Sex 10/9/99 Sex 10/9/99

90 B.BR.050 Conduct Integration Fit Analysis 0 hrs Sex 10/9/99 Sex 10/9/99

91 B.BR.060 Create Information Model 0 hrs Sex 10/9/99 Sex 10/9/99

92 B.BR.070 Conduct Reporting Fit Analysis 0 hrs Sex 10/9/99 Sex 10/9/99

93 B.BR.080 Test Business Solutions 0 hrs Sex 10/9/99 Sex 10/9/99

Q S S D S T5/Set/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 3

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 4: Oracle Implementation Project Template 1226594305077229 8

Id EDT Task Name Duração Início Término

94 B.BR.090 Confirm Integrated Business Solutions 0 hrs Sex 10/9/99 Sex 10/9/99

95 B.TA Application and Technical Architecture 0 hrs Sex 10/9/99 Sex 10/9/99

96 B.TA.040 Define Application Architecture 0 hrs Sex 10/9/99 Sex 10/9/99

97 B.TA.050 Define System Availability Strategy 0 hrs Sex 10/9/99 Sex 10/9/99

98 B.TA.060 Define Reporting and Information Access Strategy 0 hrs Sex 10/9/99 Sex 10/9/99

99 B.TA.070 Revise Conceptual Architecture 0 hrs Sex 10/9/99 Sex 10/9/99

100 B.MD Module Design and Build 0 hrs Sex 10/9/99 Sex 10/9/99

101 B.MD.020 Define and Estimate Application Extensions 0 hrs Sex 10/9/99 Sex 10/9/99

102 B.DO Documentation 0 hrs Sex 10/9/99 Sex 10/9/99

103 B.DO.040 Prepare Documentation Environment 0 hrs Sex 10/9/99 Sex 10/9/99

104 B.DO.050 Produce Documentation Prototypes and Templates 0 hrs Sex 10/9/99 Sex 10/9/99

105 B.PT Performance Testing 0 hrs Sex 10/9/99 Sex 10/9/99

106 B.PT.020 Identify Performance Test Scenarios 0 hrs Sex 10/9/99 Sex 10/9/99

107 B.PT.030 Identify Performance Test Transaction Models 0 hrs Sex 10/9/99 Sex 10/9/99

108 B.AP Adoption and Learning 0 hrs Sex 10/9/99 Sex 10/9/99

109 B.AP.090 Develop Manager's Readiness Plan 0 hrs Sex 10/9/99 Sex 10/9/99

110 B.PM Production Migration 24 hrs Sex 10/9/99 Qua 15/9/99

111 B.PM.010 Define Transition Strategy 0 hrs Sex 10/9/99 Sex 10/9/99

112 B.PM.END End Operations Analysis Execution 8 hrs Qua 15/9/99 Qua 15/9/99

113 B.CT.CTR Phase Control 16 hrs Seg 13/9/99 Ter 14/9/99

114 B.CT.BEG Begin Phase Control 8 hrs Seg 13/9/99 Seg 13/9/99

115 B.CT.SUM Phase Control 0 hrs Seg 13/9/99 Seg 13/9/99

116 B.CT.RES Unallocated Reserve 0 hrs Seg 13/9/99 Seg 13/9/99

117 B.CT.END End Phase Control 8 hrs Ter 14/9/99 Ter 14/9/99

118 B.CO.COMP Phase Completion 16 hrs Qui 16/9/99 Sex 17/9/99

119 B.CO.BEG Begin Phase Completion 8 hrs Qui 16/9/99 Qui 16/9/99

120 B.CR.080 Secure Client Phase Acceptance 0 hrs Qui 16/9/99 Qui 16/9/99

121 B.RM.080 Release Staff 0 hrs Qui 16/9/99 Qui 16/9/99

122 B.RM.090 Release Physical Resources 0 hrs Qui 16/9/99 Qui 16/9/99

123 B.QM.050 Perform Quality Assesment 0 hrs Qui 16/9/99 Qui 16/9/99

124 B.CM.060 Audit Key Deliverables 0 hrs Qui 16/9/99 Qui 16/9/99

Q S S D S T5/Set/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 4

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 5: Oracle Implementation Project Template 1226594305077229 8

Id EDT Task Name Duração Início Término

125 B.CO.END End Phase Completion 8 hrs Sex 17/9/99 Sex 17/9/99

126 C Solution Design 72 hrs Seg 13/9/99 Qui 23/9/99

127 C.PL.PLAN Phase Planning 16 hrs Seg 13/9/99 Ter 14/9/99

128 C.PL.BEG Begin Phase Planning 8 hrs Seg 13/9/99 Seg 13/9/99

129 C.PL.SUM Review and Revise Project Plans 0 hrs Seg 13/9/99 Seg 13/9/99

130 C.PL.END End Phase Planning 8 hrs Ter 14/9/99 Ter 14/9/99

131 C.BP Business Process Architecture 8 hrs Qui 16/9/99 Qui 16/9/99

132 C.BP.BEG Start Solution Design Execution 8 hrs Qui 16/9/99 Qui 16/9/99

133 C.BP.090 Document Business Procedures 0 hrs Qui 16/9/99 Qui 16/9/99

134 C.BR Business Requirements Mapping 0 hrs Qui 16/9/99 Qui 16/9/99

135 C.BR.100 Define Application Setups 0 hrs Qui 16/9/99 Qui 16/9/99

136 C.BR.110 Design Security Profiles 0 hrs Qui 16/9/99 Qui 16/9/99

137 C.TA Application and Technical Architecture 0 hrs Qui 16/9/99 Qui 16/9/99

138 C.TA.080 Define Application Security Architecture 0 hrs Qui 16/9/99 Qui 16/9/99

139 C.MD Module Design and Build 0 hrs Qui 16/9/99 Qui 16/9/99

140 C.MD.030 Define Design Standards 0 hrs Qui 16/9/99 Qui 16/9/99

141 C.MD.040 Define Build Standards 0 hrs Qui 16/9/99 Qui 16/9/99

142 C.MD.050 Create Application Extensions Functional Design 0 hrs Qui 16/9/99 Qui 16/9/99

143 C.MD.060 Design Database Extensions 0 hrs Qui 16/9/99 Qui 16/9/99

144 C.MD.070 Create Application Extensions Technical Design 0 hrs Qui 16/9/99 Qui 16/9/99

145 C.MD.080 Review Functional and Technical Designs 0 hrs Qui 16/9/99 Qui 16/9/99

146 C.CV Data Conversion 0 hrs Qui 16/9/99 Qui 16/9/99

147 C.CV.020 Define Conversion Standards 0 hrs Qui 16/9/99 Qui 16/9/99

148 C.CV.030 Prepare Conversion Environment 0 hrs Qui 16/9/99 Qui 16/9/99

149 C.CV.040 Perform Conversion Data Mapping 0 hrs Qui 16/9/99 Qui 16/9/99

150 C.CV.050 Define Manual Conversion Procedures 0 hrs Qui 16/9/99 Qui 16/9/99

151 C.CV.060 Design Conversion Programs 0 hrs Qui 16/9/99 Qui 16/9/99

152 C.CV.070 Prepare Conversion Test Plans 0 hrs Qui 16/9/99 Qui 16/9/99

153 C.TE Business System Testing 0 hrs Qui 16/9/99 Qui 16/9/99

154 C.TE.020 Develop Unit Test Script 0 hrs Qui 16/9/99 Qui 16/9/99

155 C.TE.030 Develop Link Test Script 0 hrs Qui 16/9/99 Qui 16/9/99

Q S S D S T5/Set/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 5

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 6: Oracle Implementation Project Template 1226594305077229 8

Id EDT Task Name Duração Início Término

156 C.TE.040 Develop System Test Script 0 hrs Qui 16/9/99 Qui 16/9/99

157 C.TE.050 Develop Systems Integration Test Script 0 hrs Qui 16/9/99 Qui 16/9/99

158 C.PT Performance Testing 0 hrs Qui 16/9/99 Qui 16/9/99

159 C.PT.040 Create Performance Test Scripts 0 hrs Qui 16/9/99 Qui 16/9/99

160 C.PT.050 Design Performance Test Transaction Programs 0 hrs Qui 16/9/99 Qui 16/9/99

161 C.PT.060 Design Performance Test Data 0 hrs Qui 16/9/99 Qui 16/9/99

162 C.PT.070 Design Test Database Load Programs 0 hrs Qui 16/9/99 Qui 16/9/99

163 C.AP Adoption and Learning 24 hrs Qui 16/9/99 Ter 21/9/99

164 C.AP.100 Identify Business Process Impact on Organization 0 hrs Qui 16/9/99 Qui 16/9/99

165 C.AP.110 Align Human Performance Support Systems 0 hrs Qui 16/9/99 Qui 16/9/99

166 C.AP.120 Align Information Technology Groups 0 hrs Qui 16/9/99 Qui 16/9/99

167 C.AP.130 Conduct User Learning Needs Analysis 0 hrs Qui 16/9/99 Qui 16/9/99

168 C.AP.140 Develop User Learning Plan 0 hrs Qui 16/9/99 Qui 16/9/99

169 C.AP.END End Solution Design Execution 8 hrs Ter 21/9/99 Ter 21/9/99

170 C.CT.CTR Phase Control 16 hrs Sex 17/9/99 Seg 20/9/99

171 C.CT.BEG Begin Phase Control 8 hrs Sex 17/9/99 Sex 17/9/99

172 C.CT.SUM Phase Control 0 hrs Sex 17/9/99 Sex 17/9/99

173 C.CT.RES Unallocated Reserve 0 hrs Sex 17/9/99 Sex 17/9/99

174 C.CT.END End Phase Control 8 hrs Seg 20/9/99 Seg 20/9/99

175 C.CO.COMP Phase Completion 16 hrs Qua 22/9/99 Qui 23/9/99

176 C.CO.BEG Begin Phase Completion 8 hrs Qua 22/9/99 Qua 22/9/99

177 C.CR.080 Secure Client Phase Acceptance 0 hrs Qua 22/9/99 Qua 22/9/99

178 C.RM.080 Release Staff 0 hrs Qua 22/9/99 Qua 22/9/99

179 C.RM.090 Release Physical Resources 0 hrs Qua 22/9/99 Qua 22/9/99

180 C.QM.050 Perform Quality Assesment 0 hrs Qua 22/9/99 Qua 22/9/99

181 C.CM.060 Audit Key Deliverables 0 hrs Qua 22/9/99 Qua 22/9/99

182 C.CO.END End Phase Completion 8 hrs Qui 23/9/99 Qui 23/9/99

183 D Build 72 hrs Sex 17/9/99 Qua 29/9/99

184 D.PL.PLAN Phase Planning 16 hrs Sex 17/9/99 Seg 20/9/99

185 D.PL.BEG Begin Phase Planning 8 hrs Sex 17/9/99 Sex 17/9/99

186 D.PL.SUM Review and Revise Project Plans 0 hrs Sex 17/9/99 Sex 17/9/99

Q S S D S T5/Set/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 6

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 7: Oracle Implementation Project Template 1226594305077229 8

Id EDT Task Name Duração Início Término

187 D.PL.END End Phase Planning 8 hrs Seg 20/9/99 Seg 20/9/99

188 D.TA Application and Technical Architecture 8 hrs Qua 22/9/99 Qua 22/9/99

189 D.TA.BEG Start Build Phase Execution 8 hrs Qua 22/9/99 Qua 22/9/99

190 D.TA.090 Define Application and Database Server Architecture 0 hrs Qua 22/9/99 Qua 22/9/99

191 D.TA.100 Define & Propose Architecture Subsystems 0 hrs Qua 22/9/99 Qua 22/9/99

192 D.TA.110 Define System Capacity Plan 0 hrs Qua 22/9/99 Qua 22/9/99

193 D.TA.120 Define Platform and Network Architecture 0 hrs Qua 22/9/99 Qua 22/9/99

194 D.TA.130 Define Application Deployment Plan 0 hrs Qua 22/9/99 Qua 22/9/99

195 D.TA.140 Assess Performance Risks 0 hrs Qua 22/9/99 Qua 22/9/99

196 D.TA.150 Define System Management Procedures 0 hrs Qua 22/9/99 Qua 22/9/99

197 D.MD Module Design and Build 0 hrs Qua 22/9/99 Qua 22/9/99

198 D.MD.090 Prepare Development Environment 0 hrs Qua 22/9/99 Qua 22/9/99

199 D.MD.100 Create Database Extensions 0 hrs Qua 22/9/99 Qua 22/9/99

200 D.MD.110 Create Application Extension Modules 0 hrs Qua 22/9/99 Qua 22/9/99

201 D.MD.120 Create Installation Routines 0 hrs Qua 22/9/99 Qua 22/9/99

202 D.CV Data Conversion 0 hrs Qua 22/9/99 Qua 22/9/99

203 D.CV.080 Develop Conversion Programs 0 hrs Qua 22/9/99 Qua 22/9/99

204 D.CV.090 Perform Conversion Unit Tests 0 hrs Qua 22/9/99 Qua 22/9/99

205 D.CV.100 Perform Conversion Business Object Tests 0 hrs Qua 22/9/99 Qua 22/9/99

206 D.CV.110 Perform Conversion Validation Tests 0 hrs Qua 22/9/99 Qua 22/9/99

207 D.DO Documentation 0 hrs Qua 22/9/99 Qua 22/9/99

208 D.DO.060 Publish User Reference Manual 0 hrs Qua 22/9/99 Qua 22/9/99

209 D.DO.070 Publish User Guide 0 hrs Qua 22/9/99 Qua 22/9/99

210 D.DO.080 Publish Technical Reference Manual 0 hrs Qua 22/9/99 Qua 22/9/99

211 D.DO.090 Publish System Management Guide 0 hrs Qua 22/9/99 Qua 22/9/99

212 D.TE Business System Testing 0 hrs Qua 22/9/99 Qua 22/9/99

213 D.TE.060 Prepare Testing Environments 0 hrs Qua 22/9/99 Qua 22/9/99

214 D.TE.070 Perform Unit Test 0 hrs Qua 22/9/99 Qua 22/9/99

215 D.TE.080 Perform Link Test 0 hrs Qua 22/9/99 Qua 22/9/99

216 D.TE.090 Perform Installation Test 0 hrs Qua 22/9/99 Qua 22/9/99

217 D.TE.100 Prepare Key Users for Testing 0 hrs Qua 22/9/99 Qua 22/9/99

Q S S D S T5/Set/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 7

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 8: Oracle Implementation Project Template 1226594305077229 8

Id EDT Task Name Duração Início Término

218 D.TE.110 Perform System Test 0 hrs Qua 22/9/99 Qua 22/9/99

219 D.TE.120 Perform Systems Integration Test 0 hrs Qua 22/9/99 Qua 22/9/99

220 D.PT Performance Testing 0 hrs Qua 22/9/99 Qua 22/9/99

221 D.PT.080 Create Performance Test Transaction Programs 0 hrs Qua 22/9/99 Qua 22/9/99

222 D.PT.090 Create Test Database Load Programs 0 hrs Qua 22/9/99 Qua 22/9/99

223 D.PT.100 Construct Performance Test Database 0 hrs Qua 22/9/99 Qua 22/9/99

224 D.PT.110 Prepare Performance Test Environment 0 hrs Qua 22/9/99 Qua 22/9/99

225 D.PT.120 Execute Performance Test 0 hrs Qua 22/9/99 Qua 22/9/99

226 D.PT.130 Create Performance Test Report 0 hrs Qua 22/9/99 Qua 22/9/99

227 D.AP Adoption and Learning 0 hrs Qua 22/9/99 Qua 22/9/99

228 D.AP.150 Develop User Learningware 0 hrs Qua 22/9/99 Qua 22/9/99

229 D.AP.160 Prepare User Learning Environment 0 hrs Qua 22/9/99 Qua 22/9/99

230 D.PM Production Migration 24 hrs Qua 22/9/99 Seg 27/9/99

231 D.PM.020 Design Production Support Infrastructure 0 hrs Qua 22/9/99 Qua 22/9/99

232 D.PM.030 Develop Transition & Contingency Plan 0 hrs Qua 22/9/99 Qua 22/9/99

233 D.PM.END End Build Phase Execution 8 hrs Seg 27/9/99 Seg 27/9/99

234 D.CT.CTR Phase Control 16 hrs Qui 23/9/99 Sex 24/9/99

235 D.CT.BEG Begin Phase Control 8 hrs Qui 23/9/99 Qui 23/9/99

236 D.CT.SUM Phase Control 0 hrs Qui 23/9/99 Qui 23/9/99

237 D.CT.RES Unallocated Reserve 0 hrs Qui 23/9/99 Qui 23/9/99

238 D.CT.END End Phase Control 8 hrs Sex 24/9/99 Sex 24/9/99

239 D.CO.COMP Phase Completion 16 hrs Ter 28/9/99 Qua 29/9/99

240 D.CO.BEG Begin Phase Completion 8 hrs Ter 28/9/99 Ter 28/9/99

241 D.CR.080 Secure Client Phase Acceptance 0 hrs Ter 28/9/99 Ter 28/9/99

242 D.RM.080 Release Staff 0 hrs Ter 28/9/99 Ter 28/9/99

243 D.RM.090 Release Physical Resources 0 hrs Ter 28/9/99 Ter 28/9/99

244 D.QM.050 Perform Quality Assesment 0 hrs Ter 28/9/99 Ter 28/9/99

245 D.CM.060 Audit Key Deliverables 0 hrs Ter 28/9/99 Ter 28/9/99

246 D.CO.END End Phase Completion 8 hrs Qua 29/9/99 Qua 29/9/99

247 E Transition 72 hrs Qui 23/9/99 Ter 5/10/99

248 E.PL.PLAN Phase Planning 16 hrs Qui 23/9/99 Sex 24/9/99

Q S S D S T5/Set/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 8

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 9: Oracle Implementation Project Template 1226594305077229 8

Id EDT Task Name Duração Início Término

249 E.PL.BEG Begin Phase Planning 8 hrs Qui 23/9/99 Qui 23/9/99

250 E.PL.SUM Review and Revise Project Plans 0 hrs Qui 23/9/99 Qui 23/9/99

251 E.PL.END End Phase Planning 8 hrs Sex 24/9/99 Sex 24/9/99

252 E.CV Data Conversion 8 hrs Ter 28/9/99 Ter 28/9/99

253 E.CV.BEG Start Transition Phase Execution 8 hrs Ter 28/9/99 Ter 28/9/99

254 E.CV.120 Install Conversion Programs 0 hrs Ter 28/9/99 Ter 28/9/99

255 E.CV.130 Convert and Verify Data 0 hrs Ter 28/9/99 Ter 28/9/99

256 E.TE Business System Testing 0 hrs Ter 28/9/99 Ter 28/9/99

257 E.TE.130 Perform Acceptance Test 0 hrs Ter 28/9/99 Ter 28/9/99

258 E.AP Adoption and Learning 0 hrs Ter 28/9/99 Ter 28/9/99

259 E.AP.170 Conduct User Learning Events 0 hrs Ter 28/9/99 Ter 28/9/99

260 E.PM Production Migration 24 hrs Ter 28/9/99 Sex 1/10/99

261 E.PM.040 Prepare Production Environment 0 hrs Ter 28/9/99 Ter 28/9/99

262 E.PM.050 Set Up Applications 0 hrs Ter 28/9/99 Ter 28/9/99

263 E.PM.060 Implement Production Support Infrastructure 0 hrs Ter 28/9/99 Ter 28/9/99

264 E.PM.070 Verify Production Readiness 0 hrs Ter 28/9/99 Ter 28/9/99

265 E.PM.080 Begin Production 0 hrs Ter 28/9/99 Ter 28/9/99

266 E.PM.END End Transition Phase Execution 8 hrs Sex 1/10/99 Sex 1/10/99

267 E.CT.CTR Phase Control 16 hrs Qua 29/9/99 Qui 30/9/99

268 E.CT.BEG Begin Phase Control 8 hrs Qua 29/9/99 Qua 29/9/99

269 E.CT.SUM Phase Control 0 hrs Qua 29/9/99 Qua 29/9/99

270 E.CT.RES Unallocated Reserve 0 hrs Qua 29/9/99 Qua 29/9/99

271 E.CT.END End Phase Control 8 hrs Qui 30/9/99 Qui 30/9/99

272 E.CO.COMP Phase Completion 16 hrs Seg 4/10/99 Ter 5/10/99

273 E.CO.BEG Begin Phase Completion 8 hrs Seg 4/10/99 Seg 4/10/99

274 E.CR.080 Secure Client Phase Acceptance 0 hrs Seg 4/10/99 Seg 4/10/99

275 E.RM.080 Release Staff 0 hrs Seg 4/10/99 Seg 4/10/99

276 E.RM.090 Release Physical Resources 0 hrs Seg 4/10/99 Seg 4/10/99

277 E.QM.050 Perform Quality Assesment 0 hrs Seg 4/10/99 Seg 4/10/99

278 E.CM.060 Audit Key Deliverables 0 hrs Seg 4/10/99 Seg 4/10/99

279 E.CO.END End Phase Completion 8 hrs Ter 5/10/99 Ter 5/10/99

Q S S D S T5/Set/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 9

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 10: Oracle Implementation Project Template 1226594305077229 8

Id EDT Task Name Duração Início Término

280 F Production 72 hrs Qua 29/9/99 Seg 11/10/99

281 F.PL.PLAN Phase Planning 16 hrs Qua 29/9/99 Qui 30/9/99

282 F.PL.BEG Begin Phase Planning 8 hrs Qua 29/9/99 Qua 29/9/99

283 F.PL.SUM Review and Revise Project Plans 0 hrs Qua 29/9/99 Qua 29/9/99

284 F.PL.END End Phase Planning 8 hrs Qui 30/9/99 Qui 30/9/99

285 F.AP Adoption and Learning 8 hrs Seg 4/10/99 Seg 4/10/99

286 F.AP.BEG Start Production Phase Execution 8 hrs Seg 4/10/99 Seg 4/10/99

287 F.AP.180 Conduct Effectiveness Assessment 0 hrs Seg 4/10/99 Seg 4/10/99

288 F.PM Production Migration 24 hrs Seg 4/10/99 Qui 7/10/99

289 F.PM.090 Measure System Performance 0 hrs Seg 4/10/99 Seg 4/10/99

290 F.PM.100 Maintain System 0 hrs Seg 4/10/99 Seg 4/10/99

291 F.PM.110 Refine Production System 0 hrs Seg 4/10/99 Seg 4/10/99

292 F.PM.120 Decommission Former Systems 0 hrs Seg 4/10/99 Seg 4/10/99

293 F.PM.130 Propose Future Business Direction 0 hrs Seg 4/10/99 Seg 4/10/99

294 F.PM.140 Propose Future Technical Direction 0 hrs Seg 4/10/99 Seg 4/10/99

295 F.PM.END End Production Phase Execution 8 hrs Qui 7/10/99 Qui 7/10/99

296 F.CT.CTR Phase Control 16 hrs Ter 5/10/99 Qua 6/10/99

297 F.CT.BEG Begin Phase Control 8 hrs Ter 5/10/99 Ter 5/10/99

298 F.CT.SUM Phase Control 0 hrs Ter 5/10/99 Ter 5/10/99

299 F.CT.RES Unallocated Reserve 0 hrs Ter 5/10/99 Ter 5/10/99

300 F.CT.END End Phase Control 8 hrs Qua 6/10/99 Qua 6/10/99

301 F.CO.COMP Project Completion 16 hrs Sex 8/10/99 Seg 11/10/99

302 F.CO.BEG Begin Project Completion 8 hrs Sex 8/10/99 Sex 8/10/99

303 F.CR.080 Secure Client Phase Acceptance 0 hrs Sex 8/10/99 Sex 8/10/99

304 F.RM.080 Release Staff 0 hrs Sex 8/10/99 Sex 8/10/99

305 F.RM.090 Release Physical Resources 0 hrs Sex 8/10/99 Sex 8/10/99

306 F.QM.050 Perform Quality Assesment 0 hrs Sex 8/10/99 Sex 8/10/99

307 F.CM.060 Audit Key Deliverables 0 hrs Sex 8/10/99 Sex 8/10/99

308 F.CM.070 Conclude Configuration Management 0 hrs Sex 8/10/99 Sex 8/10/99

309 F.CO.END End Project Completion 8 hrs Seg 11/10/99 Seg 11/10/99

Q S S D S T5/Set/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 10

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 11: Oracle Implementation Project Template 1226594305077229 8

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q12/Set/99 19/Set/99 26/Set/99 3/Out/99 10/Out/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 11

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 12: Oracle Implementation Project Template 1226594305077229 8

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9

9/9

9

7/9

7/9

8/9

Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q12/Set/99 19/Set/99 26/Set/99 3/Out/99 10/Out/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 12

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 13: Oracle Implementation Project Template 1226594305077229 8

10/9

10/9

10/9

10/9

10/9

10/9

13/9

8/9

8/9

9/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q12/Set/99 19/Set/99 26/Set/99 3/Out/99 10/Out/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 13

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 14: Oracle Implementation Project Template 1226594305077229 8

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

10/9

15/9

13/9

13/9

13/9

14/9

16/9

16/9

16/9

16/9

16/9

16/9

Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q12/Set/99 19/Set/99 26/Set/99 3/Out/99 10/Out/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 14

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 15: Oracle Implementation Project Template 1226594305077229 8

17/9

13/9

13/9

14/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q12/Set/99 19/Set/99 26/Set/99 3/Out/99 10/Out/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 15

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 16: Oracle Implementation Project Template 1226594305077229 8

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

16/9

21/9

17/9

17/9

17/9

20/9

22/9

22/9

22/9

22/9

22/9

22/9

23/9

17/9

17/9

Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q12/Set/99 19/Set/99 26/Set/99 3/Out/99 10/Out/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 16

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 17: Oracle Implementation Project Template 1226594305077229 8

20/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q12/Set/99 19/Set/99 26/Set/99 3/Out/99 10/Out/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 17

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 18: Oracle Implementation Project Template 1226594305077229 8

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

22/9

27/9

23/9

23/9

23/9

24/9

28/9

28/9

28/9

28/9

28/9

28/9

29/9

Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q12/Set/99 19/Set/99 26/Set/99 3/Out/99 10/Out/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 18

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 19: Oracle Implementation Project Template 1226594305077229 8

23/9

23/9

24/9

28/9

28/9

28/9

28/9

28/9

28/9

28/9

28/9

28/9

28/9

28/9

28/9

1/10

29/9

29/9

29/9

30/9

4/10

4/10

4/10

4/10

4/10

4/10

5/10

Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q12/Set/99 19/Set/99 26/Set/99 3/Out/99 10/Out/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 19

Project: Generic Oracle Applications ImDate: Qui 13/11/08

Page 20: Oracle Implementation Project Template 1226594305077229 8

29/9

29/9

30/9

4/10

4/10

4/10

4/10

4/10

4/10

4/10

4/10

7/10

5/10

5/10

5/10

6/10

8/10

8/10

8/10

8/10

8/10

8/10

8/10

11/10

Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q Q S S D S T Q12/Set/99 19/Set/99 26/Set/99 3/Out/99 10/Out/99

Task

Split

Progress

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Page 20

Project: Generic Oracle Applications ImDate: Qui 13/11/08