Optimization of Power System Operation
Introduction
Electricity generating companies and power systems have the problem of deciding how best to meet the varying demand for electricity, which has a daily and weekly cycle.
This study essentially deals with the method of operating Electrical generating sets of different type, to get the economic power from them.
The terms ‘Unit Commitment’, ‘Economic Dispatch’ and ‘Incremental Cost’ are widely used in this study discipline.
The steps for optimization
Long Term System PlanningHourly and Monthly decisions -- Unit CommitmentInstantaneous Dispatch decisions -- Economic DispatchShort term system operation -- Load Flow Model
Economic Dispatch- Covered Earlier
Energy Policy Act defines “Economic Dispatch” to mean “the operation of generation facilities to produce energy at the lowest cost to reliably serve consumers, recognizing any operational limits of generation and transmission facilities.” [EPAct 2005, Sec. 1234 (b)]
Actually, For Power System Economic Operation, the installed generating capacity should be
greater than the load at any specific moment
This topic is covered in earlier presentation
Unit Commitment
The electrical unit commitment problem is the problem of deciding which electricity generation units should be running in each period so as to satisfy a predictably varying demand for electricity.
The problem is interesting because in a typical electrical system there are a variety of units available for generating electricity, and each has its own characteristics.
Unit Commitment- The Constraints
UC problem is a complex optimization problem which requires rigorous enumeration of all feasible combination of the generation units.
The Problem typically involve technological and economic constraints. Spinning Reserve Thermal Unit Constraints
Minimum Up Time Minimum Down Time Start-Up Cost Shut-Down cost
Hydro Constraints Must Run Fuel Constraint
Unit Commitment- Solution Methods
Most common techniques are,
Priority-list Schemes-simplest method but enormous computational time-based on shut down rule-creates a priority list of units by an exhaustive
enumeration
Heuristic Methods-Uses pre-calculated priority list and incorporate all the
operating constraints heuristically.
Mixed Integer Programming
UC - Solution Methods (Continued.)
Dynamic Programming-advantage over PLS is reduction in the
dimensionality of the problem-systematically evaluates a large number of
possible decisions in a multi-step problem Lagrange Relaxation
-based on dual optimization approach
Dynamic Programming-Illustrated
The objective is to find minimum cost from A-N.
K=1,2…5= Hour
At the end of each hour, a decision is taken to enter on which state.
Advances in Unit Commitment Problem
Genetic Algorithm
-The genetic based UC program starts with a random initial population (at T=0) at it computes the fitness of each individual.
-Advanced level of GA is used like Fast Messy Genetic Algorithm (FMGA)
Various algorithms to UC Problem
Ant Colony System ( S. P. Simon, N. P. Padhy and R. S. Anand)
- foraging behavior of the real ants for finding its food from its start (nest) to its destination (food) is simulated to obtain the optimum solution.
A Practical Software: e-terracommit
A Practical Software
Power Generation Machines
GE 9E GAS TURBINE
Rolls-Royce BV16 HFO Engine
Power Generation Machines
Inside a power plant