Figure 1: New trees planted at 'Welcome Sign' - September 2015
Operations Department
Third Quarter 2015
July 1, 2015 – September 30, 2015
General Departmental Summary
The Operations Department directed their energy mainly on regular maintenance this quarter. This quarter
there were no proposals sent to tender. Several capital projects are currently under way. The Pincher
Creek raw water pump house structure has been installed and the internal systems are underway. The
project is expected to be finalized on November 10, 2015. The historic fence replacement at the Lebel
Mansion is in progress and the water and wastewater treatment projects are at the brink of starting.
Over the summer months we experienced higher than average temperatures and the previous winter did
not provide adequate snow pack causing the Town to establish voluntary water restrictions. Citizens were
asked to refrain from watering lawns and gardens in the heat of the day and be aware of the duration and
volume they were consuming. This caused some delays with annual programs including water main
unidirectional flushing and the release of effluent from the wastewater lagoons.
Streets and Water Distribution
July – September 2015
Continuing water main flushing (delays due to water restrictions)
Sewer service repairs at 949 Maple Street, 479 Indian Street, and 1121
Scobie Avenue
Hydrant replacement at Rigaux Drive and Beverley McLachlin Drive
Water main repair at 1035 Deer Avenue
Storm sewer install – approach at Heritage Inn
Completed Rabine (dust control) application
Continuing street sweeping
Continuing street sign maintenance and replacement
Continuing back alley maintenance
Completed parking lot and crosswalk painting
Upcoming Quarter October – December 2015
Figure 2: New Hydrant on the corner of Beverley McLachlin Drive and Rigaux Drive – September 2015
Complete water main flushing
Complete street sweeping for the season
Install Christmas decorations
Continue street sign maintenance and replacement
Snow removal and sanding as required
Figure 3: Deer Avenue water main repairs - September 2015
Facilities and Open Spaces
July, August and September 2015
Zero full graves were dug
Six urn graves dug in July
Four urn graves dug in August
Four urn graves dug in September
One Disinterment in August
Grave yard maintenance
St Michael’s track repairs
Irrigation repairs
Blow out irrigation
Picnic table repairs
Paint kiosk at cemetery
Plant trees
Water grass and trees
Trail repairs
Building maintenance
Snow fence installation
Painted soccer nets and bleachers
Landscaping on Waterton Avenue and Main Street
Figure 4: Trail Maintenance - August 2015
Figure 5: St. Michael's Track Repairs – July 2015
Figure 6: Landscaping on the Corner of Waterton Avenue and Main Street
Figure 4: Trail Maintenance - August 2015
October, November, and December 2015
Clear snow from sidewalks and trails as needed
Dig graves as needed
Finish blowing out irrigation
Water trees
Help the Recreation Department make ice
Make outdoor rink
Building maintenance
Solid Waste and Fleet Services
Equipment repairs on going
Winter preparations
Provincial Inspections (CVIPs)
RFP preparations for future equipment
Parts ordering
Water Treatment and Capital Projects
Sanitary wastewater approval # 95-MUN-080 July 1 – September 30, 2015
Total Volume Flows = 183,186 mᶾ
Water treatment filtered and treated water for distribution July 1 – September 30, 2015
Total Volume Flows = 245,268 mᶾ
July
Had pre start-up meeting for Raw Water Pump
House project (Al Roth, Blaise Bruder &
Contractor Representatives in attendance)
Meeting was held on June 25. Start date set at
July 15, 2015.
Received new valves for water treatment plant
from Summit Valve
Finished Landscaping Schofield sidewalk project
and placed sod
Ordered materials for Force Main project
Inspected old Pincher Raw water intake with engineer
Figure 7: Winterized Fountain at the Cenotaph Park - September 2015
Figure 8: Picnic Table Repairs - July-September 2015
Figure 9: New Pump House - Project Completion estimated November 10, 2015
Inspected lagoon chambers with engineer
Installed new catch basin and weeping tile at St. Michael’s track
Rebuilt golf course pump at old water treatment plant
Porter Tanner started new pump house project July 13, 2015
BMT Construction working on Lebel Mansion fence reconstruction
August
Hewetson Avenue pathway completed
Obtained quote for installing new valves at Water Treatment Plant, will wait for cooler temperatures
and lower water consumption flows to start project
Local welder has been manufacturing caps for sewage force main repairs, all other parts have
arrived, will be installing when caps are ready. To-date four locations have been repaired and hot
tapping will begin August 19, 2015
Because of low flows in the Pincher Creek it was decided to postpone draining the sewage lagoons
until later in the fall
Wentworth water looping project postponed until 2016
Construction of the new raw water pump house were delayed but have since resumed the building
placement.
Work done for the installation of the new
UV system at the water treatment plant
Upgrades are currently underway on the
sewage force main – corroded fittings are
being capped off and new fittings are
welded on, hot tapping is underway and
air/vacuum valves are being replaced
Had pre startup meeting with contractor
– plans are to install a new hydrant on
Beverley McLachlin, to install new sewer
main and manhole on John Avenue and
creating a new storm sewer system in
Castleview Heights
September
Weld on force main is complete, on
air/vacuum valve is left to install
(backordered) and one sacrificial anode is
left to install
Drainage pipes have been installed at
sports track, landscaping and fence repairs
are currently underway
Figure 10: Completed Schofield Sidewalk - July 2015
Lebel Mansion fence rock work is in progress and will be completed before freeze up
Replaced a hydrant on Beverly McLachlin Drive and will be working on the sewer main on John
Avenue before moving to the storm sewer project in Castleview Heights
An estimate was provided to dredge solids from lagoon cells 1 & 3 for the spring of 2016
Checked all cathodic protection sites at the Castle River pump house and along the pipeline all the
way and including the water treatment plant.
Installation of the UltraViolet unit at the water plant is expected to start in late October. The new
operating valves that were previously purchased will be installed as an extension of this project.
Engineering is under way for the replacement of the concrete chambers at the sewage lagoons.
Replacement will take place in 2016
Porter Tanner Construction has completed all underground piping for the Pincher Creek raw water
pump house. Contractor is currently installing plumbing inside the building. Electrical installations
will begin soon. Completion date is November 10, 2015
Figure 11: Lebel Mansion Historic Fence - August-September 2015
Iworq RequestsJuly - September 2015
Third Quarter
Animal Control - 20 Arena - 3Bylaw Services - 40 Campground - 15Capital/Tendered Projects - 9 Cemetery - Fairview - 22Cemetery - Pioneer - 1 Compliment - 3Developed Flower Beds - 1 Development - 1Drainage - 4 Facility Maintenance - Community Futures/Old RCMP - 1Facility Maintenance - CRC (Bowling/Clubhouse/Joes) - 4 Facility Maintenance - Lebel Mansion - 3Facility Maintenance - MultiPurpose Facility - 3 Facility Maintenance - RCMP Building - 4Facility Maintenance - Town Office - 16 Facility Maintenance - Town Office Daycare - 2Fleet Management - 5 Garbage (Extra Pick-ups) - 3Garbage (General) - 18 Garbage (Missed Collections) - 110Garbage (Bin Repair) - 3 Parks - Bike/Skate Park - 2Parks - Dilmer - 2 Parks - General - 16Parks - South Hill - 1 Parks - Town Hall - 4Poll Response - 9 Sewer - 1Sewer Camera Request - 1 Sidewalks - 7Signs - 14 Sports Fields - Ag Grounds - 1Sports Fields - General - 3 Sports Fields - Juan Teran - 7Sports Fields - Matthew Halton - 3 Sports Fields - Pool Field - 4Sports Fields - Sproule Field - 2 Sports Fields - St. Michael's - 2Streets - 26 Trees/Shrubs/Weeds - 8Utilities - 6 Walkway/Pathway - 6Wastewater Treatment - 1 Water Distribution - 50Water Treatment - 5