operation stimulus final presentation 2017
TRANSCRIPT
Jon Holzberger Ethan Robinson
Rachel Slaker Beth Johnson Chad Johnnie
Richard Miller
4PL
Global Supply Chain & Planning
Trade Services
Freight Services
Logistics & Distribution
WHO WE ARE
BACKGROUND SUPPLIERS PRODUCTION TCO
BACKGROUND SUPPLIERS PRODUCTION TCO
MISSION STATEMENT“Our mission is to offer our clients the ability to achieve successful international trade relations in order to provide their customers a superior value in their product.”
-Atlas Logistics Consulting Company
CASE SNAPSHOT
BACKGROUND SUPPLIERS PRODUCTION TCO
4B
C The Better Baby Boomer Blender Company
SITUATION- 4BC is introducing a new product and wants to invest in expanding their operations internationally.
TASK- Select four countries out of the twelve available options then create a supply chain strategy for those countries chosen.
PROBLEM- Reduce the current domestic inventory cost which is $12.38. Create a production schedule to ensure on-time delivery.
STRATEGY- Develop metrics to compare and contrast each supplier, then rank them accordingly.
• Demand is constant throughout the year.
• Venders supplier will be running 24/7.
• Our suppliers will be on contract and will abide by those terms stated in the contract.
• If Brazil is chosen as a supplier, we will not need to use the Panama Canal and will adjust the lead time accordingly.
CASE ASSUMPTIONS
BACKGROUND SUPPLIERS PRODUCTION TCO
TARIFFS
BACKGROUND SUPPLIERS PRODUCTION TCO
RESEARCH
ASSIGN WEIGHTS
CHOOSE SUPPLIERS
QUANTITATIVE ANALYSIS
BACKGROUND SUPPLIERS PRODUCTION TCO
COUNTRIES CHOSEN
BACKGROUND SUPPLIERS PRODUCTION TCO
SUPPLIERS CHOSEN
BACKGROUND SUPPLIERS PRODUCTION TCO
• Top ten supplier metrics
• Price not deciding
factor
• Bids to chosen suppliers
BACKGROUND SUPPLIERS PRODUCTION TCO
COST OF PRODUCT
BACKGROUND SUPPLIERS PRODUCTION TCO
COST OF PRODUCT
BACKGROUND SUPPLIERS PRODUCTION TCO
ECONOMIC ORDER QUANTITY
Annual Demand 4600000
Order Cost 900
Brazil: Feeder
Brazil: Cover
Brazil: Container
Australia: Glass Jug
Malaysia: Seal
China: Blade
China: Motor
26-Nov1-Dec
6-Dec
11-Dec
16-Dec
21-Dec
26-Dec
31-Dec5-Jan
10-Jan
Start Date
Production
(estimated)
(given)
BACKGROUND SUPPLIERS PRODUCTION TCO
GANTT CHART5
5
7
9
9
9
31
22
2828
7
7
7
7
PRODUCTION SCHEDULE
BACKGROUND SUPPLIERS PRODUCTION TCO
CUSTOMS DOCUMENTATION
BACKGROUND SUPPLIERS PRODUCTION TCO
• Under FCA – Free Carrier• Commercial Invoice
- Proforma invoice • Certifications: - Manufacture: Origin – Department of commerce - Inspection and Analysis: done by third party to
ensure conformity - Analysis: composition i.e. polymers - Free sale: industry regulated standards i.e. USDA & EPA
BACKGROUND SUPPLIERS PRODUCTION TCO
PER ORDER/ANNUAL
BACKGROUND SUPPLIERS PRODUCTION TCO
BACKGROUND SUPPLIERS PRODUCTION TCO
TOTAL COST OF OWNERSHIP
AUDIT FORM
BACKGROUND SUPPLIERS PRODUCTION TCO
• Will perform audits based on how critical supplier is and the part they produce
• Will provide support based on how critical supplier is
• Encourage our suppliers to become ISO Certified
• Work with suppliers to become more lean
CONTINUING RELATIONSHIP
BACKGROUND SUPPLIERS PRODUCTION TCO
BACKGROUND SUPPLIERS PRODUCTION TCO
CONCLUSION