O&P Streets
Rehabilitation
Project
Public Meeting
March 9, 2011
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 2/19
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 3/19
Project Team
� DDOT Project Manager
Ramesh Mirchandani
202-497-3223
� Construction Management Consultant
Af is Idowu
� Public Outreach Consultant
Dara Ward� Others
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 4/19
Project Description
� O and P Streets between 37th Street and
Wisconsin Avenue require rehabilitation due to
vehicle traff ic and sinkholes f rom century-old
leaking water mains.
� Three key elements:
± Rehabilitating the roadway, sidewalks and streetscape
± Replacing the century-old water mains and local waterservice connections
± Restoring the historic streetcar tracks and yokes
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 5/19
Project Details
Preserving History
� Streetcar tracks, substructure elements,
track manholes and junction boxes will beremoved, ref urbished and re-installed on Oand P Street f rom 35th Street to WisconsinAvenue.
�Tracks and substructure elements on PStreet between 35th and 36th Streets andon 36th Street between O and P Streets willbe permanently removed.
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 6/19
Project Details
Improving Roadways
�
Restore road surf
ace to unif
orm lev
elwith solid base and consistent slopef or adequate drainage
�
Milling and resurf acing on 33
rd
, 34th
,35th and 37th Streets between O and PStreets
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 7/19
Project Details
Improving Roadways
�
Milling and resurf
acing of
O Streetf rom 35th Street to 37th Street
� Total reconstruction with f ull depth
superpave asphalt o
f P Street
f rom35th Street to 37th Street and 36th
Street between O and P Streets
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 8/19
Project Details
Enhancing Pedestrian Access/Amenities
� Rebuild curbs and gutters, as well as
brick sidewalks, using a mix of ref urbished and new materials
� Improve streetlights and drainage
�
Install crosswalks, curb ramps, tree boxesand tree rails
� Reinstall police call and f ire alarm boxes;and tree planting
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 9/19
Project Details
Improving Utility Services
�
Water mains will be replaced and lateralservice connections on O and P Street
between 37th Street and Wisconsin
Avenue.
� Washington Gas will install new gas lines.
Work started today.
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 10/19
Limiting Project
Impacts
� At least one lane of traff ic open at all times
when a given block is under construction
�Advance notice given toresidents/businesses prior to start of work
on their block
�When a block is under construction, noparking will be available on that block
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 11/19
Limiting Project
Impacts
� Metrobuses will be detoured only when
necessary and af ter community is inf ormed
�Project workers encouraged to carpool
� Access to alleys will be maintained at all
times
±If there is a need to brief ly close it, residents willbe notif ied ahead of time
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 12/19
Limiting Project
Impacts
� Vibratory monitoring devices will be utilizedthroughout the project to monitor impact onbuildings
± There is a restriction on vibration and the typeof equipment that can be used
� Noise monitoring equipment will also be used
to ensure noise level is within legal limits
f orresidential areas
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 13/19
Spring 2011/Summer 2011 Spring 2012/Summer 2012
Fall 2011/Winter 2012 Summer 2012/Fall 2012
Project Area & Phasing
Estimated time frames for all phases are dependent on weather conditions.
Time frames may change due to conflicts involving utility work.
Standard work hours are 7:00 a.m. to 7:00 p.m. Monday to Friday. Depending on work progress, construction
may also occur from 7:00 a.m. to 7:00 p.m. on Saturdays. No work will be performed on Sundays.
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 14/19
Communications
Channels
� Project Website
www.f ixingOandPstreets.com
� Project Off ice
3632 N Street NW
Washington, DC 20007
202-525-3637
�
DDOT Facebookwww.f acebook.com/DDOTDC
� DDOT Twitter
twitter.com/ddotdc
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 15/19
Project Status
� Traff ic control signs installed
� Test pits dug to determine existing conditionsbelow road pavement
± P St. between 36th St. and 37th St.
± To f acilitate installation of 12-inch water main
� Ongoing - Survey of buildings f or existing
conditions� Ongoing - One lane closed on the north side of
P St between 36th St. and 37th St.
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 16/19
Current Work
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 17/19
8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011
http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 18/19
Questions?
3632 N Street NW
Washington, DC 20007
202-525-3637
inf o@f ixingOandPstreets.com
Public Hours
www.f ixingOandPstreets.com
Please email or call DDOT Project Manager Ramesh Mirchandani.
Mondays 9:00a.m. 12:00 p.m.
Wednesdays 1:00p.m. 4:00 p.m.
Or by appointment