o&p streets rehabilitation project, public meeting on march 9, 2011

19
O&P Streets Rehabilitation Project Public Meeting March 9, 2011

Upload: district-department-of-transportation

Post on 08-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 1/19

O&P Streets

Rehabilitation

Project

Public Meeting

March 9, 2011

Page 2: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 2/19

Page 3: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 3/19

Project Team

� DDOT Project Manager

Ramesh Mirchandani

202-497-3223

� Construction Management Consultant

Af is Idowu

� Public Outreach Consultant

Dara Ward� Others

Page 4: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 4/19

Project Description

� O and P Streets between 37th Street and

Wisconsin Avenue require rehabilitation due to

vehicle traff ic and sinkholes f rom century-old

leaking water mains.

� Three key elements:

± Rehabilitating the roadway, sidewalks and streetscape

± Replacing the century-old water mains and local waterservice connections

± Restoring the historic streetcar tracks and yokes

Page 5: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 5/19

Project Details

Preserving History

� Streetcar tracks, substructure elements,

track manholes and junction boxes will beremoved, ref urbished and re-installed on Oand P Street f rom 35th Street to WisconsinAvenue.

�Tracks and substructure elements on PStreet between 35th and 36th Streets andon 36th Street between O and P Streets willbe permanently removed.

Page 6: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 6/19

Project Details

Improving Roadways

Restore road surf 

ace to unif 

orm lev

elwith solid base and consistent slopef or adequate drainage

Milling and resurf acing on 33

rd

, 34th

,35th and 37th Streets between O and PStreets

Page 7: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 7/19

Project Details

Improving Roadways

Milling and resurf 

acing of 

O Streetf rom 35th Street to 37th Street

� Total reconstruction with f ull depth

superpave asphalt o

f P Street

f rom35th Street to 37th Street and 36th

Street between O and P Streets

Page 8: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 8/19

Project Details

Enhancing Pedestrian Access/Amenities

� Rebuild curbs and gutters, as well as

brick sidewalks, using a mix of  ref urbished and new materials

� Improve streetlights and drainage

Install crosswalks, curb ramps, tree boxesand tree rails

� Reinstall police call and f ire alarm boxes;and tree planting

Page 9: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 9/19

Project Details

Improving Utility Services

Water mains will be replaced and lateralservice connections on O and P Street

between 37th Street and Wisconsin

Avenue.

� Washington Gas will install new gas lines.

Work started today.

Page 10: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 10/19

Limiting Project

Impacts

� At least one lane of traff ic open at all times

when a given block is under construction

�Advance notice given toresidents/businesses prior to start of work

on their block

�When a block is under construction, noparking will be available on that block

Page 11: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 11/19

Limiting Project

Impacts

� Metrobuses will be detoured only when

necessary and af ter community is inf ormed

�Project workers encouraged to carpool

� Access to alleys will be maintained at all

times

±If there is a need to brief ly close it, residents willbe notif ied ahead of time

Page 12: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 12/19

Limiting Project

Impacts

� Vibratory monitoring devices will be utilizedthroughout the project to monitor impact onbuildings

± There is a restriction on vibration and the typeof equipment that can be used

� Noise monitoring equipment will also be used

to ensure noise level is within legal limits

f orresidential areas

Page 13: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 13/19

Spring 2011/Summer 2011 Spring 2012/Summer 2012

Fall 2011/Winter 2012 Summer 2012/Fall 2012

Project Area & Phasing

Estimated time frames for all phases are dependent on weather conditions.

Time frames may change due to conflicts involving utility work.

Standard work hours are 7:00 a.m. to 7:00 p.m. Monday to Friday. Depending on work progress, construction

may also occur from 7:00 a.m. to 7:00 p.m. on Saturdays. No work will be performed on Sundays.

Page 14: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 14/19

Communications

Channels

� Project Website

www.f ixingOandPstreets.com

� Project Off ice

3632 N Street NW

Washington, DC 20007

202-525-3637

DDOT Facebookwww.f acebook.com/DDOTDC

� DDOT Twitter

twitter.com/ddotdc

Page 15: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 15/19

Project Status

� Traff ic control signs installed

� Test pits dug to determine existing conditionsbelow road pavement

± P St. between 36th St. and 37th St.

± To f acilitate installation of 12-inch water main

� Ongoing - Survey of buildings f or existing

conditions� Ongoing - One lane closed on the north side of  

P St between 36th St. and 37th St.

Page 16: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 16/19

Current Work

Page 17: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 17/19

Page 18: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 18/19

Questions?

3632 N Street NW

Washington, DC 20007

202-525-3637

inf o@f ixingOandPstreets.com

Public Hours

www.f ixingOandPstreets.com

Please email or call DDOT Project Manager Ramesh Mirchandani.

Mondays 9:00a.m. 12:00 p.m.

Wednesdays 1:00p.m. 4:00 p.m.

Or by appointment

Page 19: O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

8/7/2019 O&P Streets Rehabilitation Project, Public Meeting on March 9, 2011

http://slidepdf.com/reader/full/op-streets-rehabilitation-project-public-meeting-on-march-9-2011 19/19