Peregrino – Statoil’s largest operatorship outside NorwayThore E. Kristiansen
Senior Vice President & Head of the South Atlantic Region
ONS, 2010
From Norway to the international scene…
Statfjord Gullfaks/ Oseberg Angola Troll Lufeng
…1974
Grane Ormen Lange Peregrino Arctic Marcellus
2010 →
Why Brazil?
• Company well positioned for further growth
• Political stability
• Good investment climate
• Significant proven reserves and new pre-salt discoveries
Statoil in Brazil
• Offices in Rio de Janeiro and Niterói with 200 employees
• More than 400 offshore contractors (Peregrino)
• Operator for the Peregrino Field in the Campos Basin
• Diverse exploration portfolio
Statoil Brazil portfolio
Statoil operator
Statoil partner
Bids won in 8th Round
BM-J-3 Petrobras (Op) 60% Statoil 40%
Santos
Campos
Espirito-Santo
Camamu-Almada
Rio de Janeiro
BM-C-7 Peregrino Statoil (OP) 100%
SM-1109 Petrobras (Op) 40%Statoil 30% Repsol 30%
SM–1105 Repsol (Op) 40% Statoil 30% Petrobras 30%
SM-1233 Statoil (Op) 40% Petrobras 30% Repsol 30%
BM-C-33Repsol (Op) 35% Statoil 35%Petrobras 30%
BM-CAL-10 Statoil (Op) 60% Petrobras 40%
BM-CAL-8 Statoil (Op) 100%
BM-CAL-7 Petrobras (Op) 60% Statoil 40%
BM-C-47 Statoil (Op) 100%
BM-ES-29Repsol (Op) 40% Statoil 30%Ecopetrol 30%
BM-ES-32Petrobras (Op) 60% Statoil 40%
Jequitinhonha
Peregrino oil field offshore Brazil
• First operatorship in the country
and the largest outside the
Norwegian Continental Shelf
• World class asset with about 2.5
billion barrels of oil in place
• First oil expected early 2011.
Peak production of 100,000 bpd
Main contractors
FPSO
Brasco Shore Base
4 x Supply vessels
2 Helicopters
Main Office Heliport
Peregrino Field
Brasco shore base (200 km)
Maca
é a
irport (1
20 k
m)
Rio de Janeiro
Macaé
Niteroi
Peregrino project milestones
• Modules produced in Corpus Christi (Texas) and towed to Brazilian waters
• Peregrino jackets installed and lifting jobs completed
• Wellhead plattforms installed
• Offshore construction and commissioning ongoing
Peregrino Project milestones
Drilling platform
Peregrino Project milestones
Sailing route from Texas to BrazilEquipment Barge
HERMOD Under Tow
Jacket A MWB403
Piles A L-400
Deck A H405
DR1 Marti J
Jacket B H541
Piles B Juli B
Deck B H406
DR2 C455-3
LQ's A&B C420
Jacket A
HermodPiles A
Jacket B
Piles BDeck A
LQ A&B, Deck B and DR2
DR1
Peregrino Project milestones
Drilling rig
Peregrino Project milestones
Installation vessel (Hermod)
Peregrino Project milestones
Jacket A installation
Peregrino Project milestones
Platforms installed
Peregrino B with Dan Swift Vessel Peregrino A
Peregrino Project milestones
FPSO modules installed at Keppel FELS
Peregrino Project Status
HSE training of 1100 offshore personnel
• High safety standard is top priority
• Multicultural working environment
BM-C-7BM-C-4
7
10 km
-
BM-C-7BM-C-4
7
10 km
-
Main
South-west
N
South
Peregrino Asset Area
Sinochem to Become 40% Partner of Peregrino
• Sinochem to pay a total of USD 3,070 million for the 40% share*
• Confirms the high quality of the Peregrino asset
• Demonstrates Statoil’s ability to leverage its industrial competence
• Realises value for our shareholders
• Gives flexibility to further develop the company
*The transaction is subject to government approvals in Brazil and China
Summing up
• Brazil a country with opportunities
• Experience transfer from Norway to the international scene
• Proven ability to execute mega projects
• Project on track to start up early 2011
• Peregrino upsides
• Partnership deal signed with Sinochem