Example 1: Using the following information prepare a time sheet and calculate whether demurrage or dispatch is due – if dispatch, on the basis of “Laytime Saved”.
Use four decimal places for all calculations.
Statement of facts prepared by M&E Port agents (office open 08:30-17:30).
Cargo loaded per Bill of Lading 82,594.37 mt
M/V Athena Loading at Jakarta
Copyright © 2020 ShipScope Sam
ple
Copy
Onl
y
-
Dry Cargo Laytime Calculation
LIMITLESS POTENTIAL | LIMITLESS IMPACT | LIMITLESS SCOPE | 4
Relevant charter party clauses Laytime to commence at 14:00 if NOR tendered within office hours before noon or
upon commencement of loading whichever occurs first.
Laytime to commence at 08:00 next working day if NOR tendered within office hours after noon or upon commencement of loading whichever occurs first.
Cargo to be loaded at rate of 30,000 mts per WP port working day.
Port stevedores working hours: 07:00-12:00, 13:00-18:00, 19:00-23:30
Laycan 19th-25st February
Time from 18:00 Fridays until 07:00 Mondays not to count UUH (unless used – half laytime)
Time shifting from anchorage to berth not to count as laytime.
Demurrage US$ 17,250 pdpr DHD.
Copyright © 2020 ShipScope Sam
ple
Copy
Onl
y
-
Dry Cargo Laytime Calculation
LIMITLESS POTENTIAL | LIMITLESS IMPACT | LIMITLESS SCOPE | 5
Date Time EventFri 20th Feb 11:00 Vessel arrived at mouth of river and proceeded towards berth
1150 All fast at berth11:55 Master tenders NOR12:55 Charterer’s cargo surveyor approves vessel for loading13:00 Loading commenced18:00 Loading stopped for today
Sat 21th Feb 08:00 Loading resumed10:00-11:20 Rain
00:00 Loading stopped for todaySun 22nd Feb 10:00-23:30 Loading on overtime double pay except usual meal breaks
13:30 Shore crane breakdown15:45 Crane repaired and work then continued
Mon 21th Feb 07:00 Loading resumedTue 22nd Feb 03:30-08:00 RainWed 23rd Feb 17:35 Loading completed
18:25 Port agents M&E on board with B/L for Master to sign18:50 Vessel sailed
Copyright © 2020 ShipScope Sam
ple
Copy
Onl
y
-
Dry Cargo Laytime Calculation
LIMITLESS POTENTIAL | LIMITLESS IMPACT | LIMITLESS SCOPE | 6
Load Port
Date Day Starting Time Ending Time Laytime Used D-H-M Remarks
20-Feb Friday 11:00 - -Vessel arrived at mouth of
river/Proceeded toberth
20-Feb Friday 11:50 - - All fast20-Feb Friday 11:55 - - NOR tendered
20-Feb Friday 13:00 - - Loading commenced, laytime commenced
20-Feb Friday 13:00 14:00 00-01-00 Laytime counting20-Feb Friday 14:00 18:00 00-04-00 Loading/Time counting
21-Feb Saturday 08:00 10:00 00-01-00 Loading resumed/Half time counting
21-Feb Saturday 10:00 11:20 - Rain/Loading stopped/Time not counting
21-Feb Saturday 11:20 12:00 00-00-20 Loading resumed/Half laytime counting
21-Feb Saturday 13:00 18:00 00-02-30 Loading/Half laytime counting
22-Feb Sunday 10:00 12:00 00-01-00 Loading/Half laytime counting
22-Feb Sunday 13:00 13:30 00-00-15 Loading/Half laytime counting
22-Feb Sunday 13:30 15:45 - Crane breakdown
Copyright © 2020 ShipScope Sam
ple
Copy
Onl
y
Slide Number 1Slide Number 2Slide Number 3Slide Number 4Slide Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 11Slide Number 12Slide Number 13Slide Number 14Slide Number 15Slide Number 16Slide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24Slide Number 25Slide Number 26Slide Number 27Slide Number 28