![Page 1: On right a lorry forwarding fresh concrete from the … courses/0_fundamentals of... · Construction site visit to Dunapart project 12. 04. 2018 Underground levels construction of](https://reader031.vdocuments.mx/reader031/viewer/2022022610/5b95039409d3f27f5b8bf461/html5/thumbnails/1.jpg)
Construction site visit to Dunapart project 12. 04. 2018
Underground levels construction of a burohause. Surraounding reinforced concrete slurry
walls were consrtucted first: excavated about 12 m deep ditch was filled first with bentonit
(fluid heavier then water) and concreted after placing the reinforcement. Parallel to the
axcavation of the trench (space volume of the underground levels) the slurry walls were tied
back by prestressed steel tendons, to equilibrate the earth pressure acting horizontally onto
the backside of the slurry walls. On bottom of the trench about 2x2 m squares of the
reinforced concrete pile heads can be seen. (Below them four, about 8 to 12 m long reinforced
concrete piles – of about 50 cm diameter - were constructed to support the interior reinforced
concrete columns of the buiding. Reinforced concrete columns will start upward from centre
of the pile heads. On the right of the photo staicase and elevator surrounding reinforced
concrete walls' constructioon have already been begun.
Deformed plastic sheets in black atteched to the walls are parts of underground water
insulation. (The cellar levels' perimeter loadbearing reinforced concrete walls will be
constructed on interior side of the surrounding slurry walls.) In back provisory steel tubes can
be seen at corner junctions of the slurry walls to strengthen the connection till constructon of
the underground cellar walls and floors.
![Page 2: On right a lorry forwarding fresh concrete from the … courses/0_fundamentals of... · Construction site visit to Dunapart project 12. 04. 2018 Underground levels construction of](https://reader031.vdocuments.mx/reader031/viewer/2022022610/5b95039409d3f27f5b8bf461/html5/thumbnails/2.jpg)
Another view of the foundation works of one of the burohouse of the project.
Below the construction of two multiszorey houses of flats interconnected on ground floor – and very
probably on the underground garage level – can be seen. On the right the formwork of the reinforced
concrete floor above the third level can be seen. Observe provisory timber safety barriers along the
facade door openings. In back shear walls – walls supporting the whoole construction against
horizontal actions (wind, earthquake) of an other building can be seen, which are arranged around
the staircase and elevator shafts of the house, and were constructed in a phase after finishing the
foundation and before the construction of columns and floors of the building by use of so called
sliding formwork, which allowes continuous construction upward. In front a crane can be seen.
![Page 3: On right a lorry forwarding fresh concrete from the … courses/0_fundamentals of... · Construction site visit to Dunapart project 12. 04. 2018 Underground levels construction of](https://reader031.vdocuments.mx/reader031/viewer/2022022610/5b95039409d3f27f5b8bf461/html5/thumbnails/3.jpg)
On right a lorry forwarding fresh concrete from the nearby concrete plant can be seen. Concrete is
placed by pumping through flexible tube system. First phase shear walls of an adjacent building can
be better seen here.
Participants seem to have enjoyed the visit.