Know the flow of radio network planning Grasp the key parts of the stages of radio network planning Make the radio network planning be more standard and controllable

TRANSCRIPT

Page 1: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD.

www.huawei.com

HUAWEI Confidential

Security Level:

Service Flow of Radio Network Planning

Radio Cases training Center

ISSUE 1.1

Page 2: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 2HUAWEI Confidential

Objective

Know the flow of radio network planning

Grasp the key parts of the stages of radio network planning

Make the radio network planning be more standard and controllable

Page 3: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 3HUAWEI Confidential

Building up Mobile Network

Network Planning

Project Execution

Network Optimization

Network Objective

Page 4: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 4HUAWEI Confidential

Introduction to Radio Network Planning Flow

Page 5: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 5HUAWEI Confidential

Overview of radio Network Planning Flow

Page 6: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 6HUAWEI Confidential

Attention:• Before the project is started,

be acquainted with related

information• Confirm the information with

the users for several times• Pay attention to VIPs

• Related information from the marketRelated information from the market• Project documents output before theProject documents output before the

network planning is sold network planning is sold• Information about destination areaInformation about destination area• Object of network constructionObject of network construction• Plan of network scale and stage Plan of network scale and stage

construction construction• Available sites and frequencies toAvailable sites and frequencies to

the carriers the carriers• Digital mapDigital map• MapInfo mapMapInfo map• VIP user surveyVIP user survey

Collects detailed information about the network planning to meet the requirements of network estimation and emulation input. It prepares for satisfactory planning result.

Collects detailed information about the network planning to meet the requirements of network estimation and emulation input. It prepares for satisfactory planning result.

001 Information Collection Confirmation/Analysis

OutputNetwork Planning Information

Collection CHECKLIST

• Recent optimization report

• Carrier’s network configur

ation information• Carrier’s drive test analysi

s• Carrier’s network traffic a

nalysis• User complaint analysis• Related guide

For expansion, move or change, the collected information includes

Page 7: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 7HUAWEI Confidential

Overview of radio Network Planning Flow

Page 8: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 8HUAWEI Confidential

Output

• Link budget result• Works out the iterative result based on the capacity and coverage• Network estimation report

002 radio Network Estimation

Through the estimation, to perform a quantitative analysis and know the construction scale. Thus, the construction period and cost budget can be worked out.

• Scenario division and transmit mod

el confirmation• Quality of the capacity of scenario

s’ coverage• Traffic model and service model• Other related parameters• Estimation tool software• Related guide

Monitors the Following:Network input parameters, estimation RND documents and the result of the estimation.

The network estimation report needs to be reviewed.

Attention:• When the parameters cannot be typed, refer to the

company planning principle to provide values for the

carrier to confirm• For improper parameters, communicate with and

guide the carrier on site. Besides, notify the

customer service center and market of the regional

office. The result need to be reviewed.

Page 9: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 9HUAWEI Confidential

Overview of radio Network Planning Flow

Page 10: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 10HUAWEI Confidential

CW Test and Model Rectification (Optional) The transmit model is the basis of the cell planning. Whether the m

odel is correct affects the planning and affects whether the needs of the users can be met in an economic and proper investment.

• Scenario division and classification confirmation

• Selecting typical test points

• Testing instrument and

related software

• Related guide

•Adjusting Report of Transmit ModelOutput

Attention:• For years’ development,

the company has a complete

model library. It is

recommended to obtain the

model from the model

library.• For the needs of the market

or customers, you can test

the typical area based on the

actual reconnaissance. Then,

rectify the model based on

the test result.

Page 11: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 11HUAWEI Confidential

Overview of Radio Network Planning Flow

Page 12: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 12HUAWEI Confidential

Network base station topology

• Network estimation result• Available site resources• Electronic map• Local administrative map (Paper)• Related guide

003 Map Assistant Planning and Original Site Selection

Select and plan the area on the map based on the available site resources of the carrier, destination coverage need, the carrier’s network analysis and network estimation result.

Attention:• Set the theoretic site

as the center and R/8

as the semidiameter to

search. Besides, there

are some restriction o

n the height.• It is recommended t

o mark the to-be recon

noitered on the paper

map.

Page 13: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 13HUAWEI Confidential

Overview of Radio Network Planning Flow

Page 14: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 14HUAWEI Confidential

004 Reconnoitering Base StationCollect network planning information and environment description to confirm whether the site meet the requirements

• Topology and map

of network base

stations• Reconnaissance tool• Related guide

Monitoring point:• The following needed to be reviewed: project parameter table, base station topology, device setting, antenna feeder• Check some base station reconnaissance

• Project parameter table• Radio on site reconnaissance report (xxx base station)• On site reconnaissance table• Base station reconnaissance memo

Attention:• For proper sites, confirm the project parameters; for improper sites, give the replacing suggestion and verify the emulation• For sites cannot be reconnoitered caused by customers, sign the reconnaissance memo• For sites have the same addresses, guarantee the independence• Factors of on site reconnaissance

Page 15: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 15HUAWEI Confidential

Overview of Radio Network Planning Flow

Page 16: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 16HUAWEI Confidential

Testing Electromagnetic Background (Optional) To make sure that the electromagnetic background of the selected site is available, you need to test on site by using electromagnetic interference device. Generally, the network planning reconnaissance personnel test it.

• Test instruments and fittings

• Related guide

•EM Interference Test Table•EM Background Test ReportOutput

Attention:• For experiment network

of large scale, you can

select and test sites based

on the actual work volume.

• The downlink band of

the area needs to be tested.

You need to arrange the

vehicles to test the road.

Page 17: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 17HUAWEI Confidential

Overview of Radio Planning Flow

Page 18: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 18HUAWEI Confidential

005 System Emulation Based on the previous information, you need to emulate the system of the reconnoitered site. The emulation is a process to adjust the planning configuration to meet the needs of the customers.

• Project parameter table• Transmit model• Parameters needed in emulation• Emulation software• Digital map• Related guide

XXX Project Network Emulation ReportXXX Project Network Emulation Report

Attention:• When the theoretical site do not meet the requirements, you need to determine whether to select a new site.• When the emulation does not meet the needs of the customer. Reconnoiter and emulate the system again to achieve the goal and export the network emulation report.

Page 19: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 19HUAWEI Confidential

Overview of Radio Planning Flow

Page 20: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 20HUAWEI Confidential

XXX Project Network Preplanning Report

W Network Pre-planning Scheme and Report Review Self-Checking

Input

• Template of the network pre-planning report• Input information of the network planning• Network estimation report• Reconnaissance report of the base station• Output information of the system emulation

006 Pre-Planning of Radio Network Based on the previous collected information, network estimation, site selection, and system emulation to summarize the network pre-planning.

Attention:• The pre-planning report after

review needs to be submit to the

market of the regional office for

improvement. Then, it can be

submitted to the customer.• When exporting the emulation

result, submitting the result in the

report template as soon as possible

to promote the progress of the

project.

The following needs to be monitored:Pre-planning result and pre-planning report review

Page 21: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 21HUAWEI Confidential

Overview of Radio Network Planning Flow

Page 22: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 22HUAWEI Confidential

Cell Parameter Design Report or Network Design Report

Output

007 Designing Cell Parameter Set the base stations and cells exported from thepreplanning into a connected network to guide the later project

• Network pre-planning report• Project parameter table• Table of network planning information collection• Default parameter comparison table• For GSM, Important Parameter Comparison Table of Dual Band Network• Related guide

Attention:• The cell naming rule and coding rule, frequency

range, multiplexing mode and code planning rule• For the GSM network, focus on the cooperation of

the dual band data• For the network supports both 2G and 3G, focus on

the cooperation of mutual operation of different

system parameters

The cell parameters include the following:LAC/RAC RNC area, neighborhood tables, frequency/scramble,

power division, switchover and permitted parameters

Page 23: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 23HUAWEI Confidential

Overview of Radio Network Planning Flow

Page 24: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 24HUAWEI Confidential

008 Processing Office Data Send the parameter designing data of the network planning cell to the data center. Combine the designing data with the project parameters to generate DBF data

• Cell Parameter Design

Report or Network Planning

Design Report

• DBF file or the script file that can be loaded

Attention:• The generated DBF file or the script file that can be loaded must be consistent with the network planning parameters

Page 25: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 25HUAWEI Confidential

Overview of Radio Network Planning Flow

Page 26: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 26HUAWEI Confidential

009 Radio Network Planning Based on the integrated network planning report and the cell parameter design, write the Network Planning Report. Submit the report to the regional office of the technical support for users to exchange and report ideas.

• Radio Network Pre-Planning Report• Cell Parameter planning Report or Radio

Network Planning Report • Radio Network Planning Report

• Network Planning Scheme

• Radio Network Planning

Communication Report

Attention:• The planning rule of all

parameters must be embodied in the

Planning Scheme for the

convenience of other person and

guide the later network

optimization.

The following needs to be monitored:Review the report of the radio network planning

and planning scheme

Page 27: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 27HUAWEI Confidential

Retrospect of Radio Network Planning Flow

Page 28: Og 002 service flow of radio network planning issue1.1

HUAWEI TECHNOLOGIES CO., LTD. Page 28HUAWEI Confidential

Case Analysis

A carrier bided for setting up a new radio network. Our company received the bidding on Sep.24, and asked to on Oct.2. The market personnel sent the to a network planning pre-sales engineer on Sep.29 and required them to complete the pre-planning and post-planning of the network based on the bidding. The pre-sales engineer found out that the traffic model condition and network quality requirements are not clear. Besides, the on-site market personnel cannot provide the correct information about the local geographical environment, economy, population, mobile market, customer and market strategy. The pre-sales engineer finished the base station estimation and network planning construction suggestions on Oct.2. The engineer made the estimation of 45 base stations in the first period and 80 base stations in the second period for the market to quote. The market personnel denied the estimation and thought that the estimations do not accord with the actual situation because the number of the base stations are too many, the pressure of the service is heavy and the customers do not accept the estimation. Besides, the estimation does not adapt to the economy development of the country and the actual situation of the customers is not taken into account. The technical suggestions had not embody the network planning scheme.