offshore windpark egmond aan zee

22
Offshore Windpark Egmond aan Zee Monitoring program and international collaboration Henk Kouwenhoven Monitoring and WTG package manager www.noordzeewind.nl 22 February 2007 EU Policy Workshop on offshore wind power deployment 1

Upload: others

Post on 23-Nov-2021

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Offshore Windpark Egmond aan Zee

Offshore Windpark Egmond aan ZeeMonitoring program and international collaboration

Henk KouwenhovenMonitoring and WTG package manager

www.noordzeewind.nl

22 February 2007 EU Policy Workshop on offshore wind power deployment 1

Page 2: Offshore Windpark Egmond aan Zee

Contents:

• Project introduction

• Monitoring program

• International collaboration

22 February 2007 EU Policy Workshop on offshore wind power deployment 2

Page 3: Offshore Windpark Egmond aan Zee

Main project data:– 1 meteo mast, 116 m high– 36 Vestas V90 windturbines– 3 MW per turbine– Hub height 70 m, diameter 90 m– Project duration 20 years– Three 34 kV power cables to shore– 34/150 kV substation on land– Grid connection in Velsen– Renewable energy for at least 100.000

households

22 February 2007 EU Policy Workshop on offshore wind power deployment 3

Page 4: Offshore Windpark Egmond aan Zee

Concession area

22 February 2007 EU Policy Workshop on offshore wind power deployment 4

Page 5: Offshore Windpark Egmond aan Zee

22 February 2007 EU Policy Workshop on offshore wind power deployment 5

Shell Nuon

Power purchase Project management

Government

PermitsLegislation

Financial support

Independent research institutes

Research programmeNoordzeeWind

Shell Nuon

shareholders

EPC contract

Bouwcombinatie Egmond

Ballast Nedam Vestas

construction turbine

Continuon

grid connection

Stakeholder group (NGO’s)

Page 6: Offshore Windpark Egmond aan Zee

Interest of government atoffshore Windpark Egmond aan Zee•Goal

Collect knowledge about windenergy at sea:

•Effects on nature and environment

•Technology

•Economy (efficient windpark)

•Therefore: Monitoring and Evaluation program

22 February 2007 EU Policy Workshop on offshore wind power deployment 6

Page 7: Offshore Windpark Egmond aan Zee

Monitoring en Evaluation Program / Research institutes working

•Birds

•Sea mammals, fish and benthos

•Landscape (societal aspects)

•Shipping and Safety

•Energy production

•Technical and economical aspects

* Alterra and Rivo are currently known as Wageningen IMARES

*

Tech

nolo

gy

E

nviro

nmen

t

22 February 2007 EU Policy Workshop on offshore wind power deployment 7

Page 8: Offshore Windpark Egmond aan Zee

Expected results bird investigation program:

• Order of magnitude for disruption of flight pattern, collision and barrier effect

• Comparison with on shore and extrapolation to further off shore possible

• Effect evaluation enabled and designparameters developed

22 February 2007 EU Policy Workshop on offshore wind power deployment 8

Page 9: Offshore Windpark Egmond aan Zee

Expected results seals:

• Extra information about the use of the habitat

• Knowledge if the wind farm attracts or disturbs seals

22 February 2007 EU Policy Workshop on offshore wind power deployment 9

Page 10: Offshore Windpark Egmond aan Zee

Expected results harbour porpoises:

• Information about the use of the wind farm area

• Reference data influence of wind farms

22 February 2007 EU Policy Workshop on offshore wind power deployment 10

Page 11: Offshore Windpark Egmond aan Zee

Expected results benthos:

• Better understanding of underlying processes

• Effects of fishing stop on:– bottom fauna– refuge function– food production– Population set up in terms of age and species

22 February 2007 EU Policy Workshop on offshore wind power deployment 11

Page 12: Offshore Windpark Egmond aan Zee

Expected results fish:

• Effects of the wind farm will be known

• Refuge function established or not

• Relevant processes known

22 February 2007 EU Policy Workshop on offshore wind power deployment 12

Page 13: Offshore Windpark Egmond aan Zee

Expected results public opinion:

• Clear view on people´s opiniontowards the OWEZ

• Impression on influence of thewind farm on attractiveness ofEgmond aan Zee

22 February 2007 EU Policy Workshop on offshore wind power deployment 13

Page 14: Offshore Windpark Egmond aan Zee

Expected results safety and ships:

• Insight in collision risks andconsequences of oil spills

• Insight in effects onshipping radar

22 February 2007 EU Policy Workshop on offshore wind power deployment 14

Page 15: Offshore Windpark Egmond aan Zee

First results Monitoring program•Public opinion moving towards far more positive attitude

•No negative influence of OWEZ on tourists on the beach

•Piling caused no disturbance of birds

•Under water noise level during piling is known

•Wind resource available through measurements

•Zero measurements on seals finished

•Risks for vessels very limited

•Results available on www.noordzeewind.nl

22 February 2007 EU Policy Workshop on offshore wind power deployment 15

Page 16: Offshore Windpark Egmond aan Zee

International collaboration:

•Easy accessible database with results

22 February 2007 EU Policy Workshop on offshore wind power deployment 16

Page 17: Offshore Windpark Egmond aan Zee

International collaboration:

•Easy accessible database with results

•Cumulative effects

22 February 2007 EU Policy Workshop on offshore wind power deployment 17

Page 18: Offshore Windpark Egmond aan Zee

International collaboration:

•Easy accessible database with results

•Cumulative effects

•Define potentials and threats

22 February 2007 EU Policy Workshop on offshore wind power deployment 18

Page 19: Offshore Windpark Egmond aan Zee

International collaboration:

•Easy accessible database with results

•Cumulative effects

•Define potentials and threats

•Disconnection of results and site

22 February 2007 EU Policy Workshop on offshore wind power deployment 19

Page 20: Offshore Windpark Egmond aan Zee

International collaboration:

•Easy accessible database with results

•Cumulative effects

•Define potentials and threats

•Disconnection of results and site

•EU Standard for research methods

22 February 2007 EU Policy Workshop on offshore wind power deployment 20

Page 21: Offshore Windpark Egmond aan Zee

International collaboration:

•Easy accessible database with results

•Cumulative effects

•Define potentials and threats

•Disconnection of results and site

•EU Standard for research methods

•Define level of sufficient knowledge

22 February 2007 EU Policy Workshop on offshore wind power deployment 21

Page 22: Offshore Windpark Egmond aan Zee

Thank you for your attention

22 February 2007 EU Policy Workshop on offshore wind power deployment 22