Contents:
• Project introduction
• Monitoring program
• International collaboration
22 February 2007 EU Policy Workshop on offshore wind power deployment 2
Main project data:– 1 meteo mast, 116 m high– 36 Vestas V90 windturbines– 3 MW per turbine– Hub height 70 m, diameter 90 m– Project duration 20 years– Three 34 kV power cables to shore– 34/150 kV substation on land– Grid connection in Velsen– Renewable energy for at least 100.000
households
22 February 2007 EU Policy Workshop on offshore wind power deployment 3
Concession area
22 February 2007 EU Policy Workshop on offshore wind power deployment 4
22 February 2007 EU Policy Workshop on offshore wind power deployment 5
Shell Nuon
Power purchase Project management
Government
PermitsLegislation
Financial support
Independent research institutes
Research programmeNoordzeeWind
Shell Nuon
shareholders
EPC contract
Bouwcombinatie Egmond
Ballast Nedam Vestas
construction turbine
Continuon
grid connection
Stakeholder group (NGO’s)
Interest of government atoffshore Windpark Egmond aan Zee•Goal
Collect knowledge about windenergy at sea:
•Effects on nature and environment
•Technology
•Economy (efficient windpark)
•Therefore: Monitoring and Evaluation program
22 February 2007 EU Policy Workshop on offshore wind power deployment 6
Monitoring en Evaluation Program / Research institutes working
•Birds
•Sea mammals, fish and benthos
•Landscape (societal aspects)
•Shipping and Safety
•Energy production
•Technical and economical aspects
* Alterra and Rivo are currently known as Wageningen IMARES
*
Tech
nolo
gy
E
nviro
nmen
t
22 February 2007 EU Policy Workshop on offshore wind power deployment 7
Expected results bird investigation program:
• Order of magnitude for disruption of flight pattern, collision and barrier effect
• Comparison with on shore and extrapolation to further off shore possible
• Effect evaluation enabled and designparameters developed
22 February 2007 EU Policy Workshop on offshore wind power deployment 8
Expected results seals:
• Extra information about the use of the habitat
• Knowledge if the wind farm attracts or disturbs seals
22 February 2007 EU Policy Workshop on offshore wind power deployment 9
Expected results harbour porpoises:
• Information about the use of the wind farm area
• Reference data influence of wind farms
22 February 2007 EU Policy Workshop on offshore wind power deployment 10
Expected results benthos:
• Better understanding of underlying processes
• Effects of fishing stop on:– bottom fauna– refuge function– food production– Population set up in terms of age and species
22 February 2007 EU Policy Workshop on offshore wind power deployment 11
Expected results fish:
• Effects of the wind farm will be known
• Refuge function established or not
• Relevant processes known
22 February 2007 EU Policy Workshop on offshore wind power deployment 12
Expected results public opinion:
• Clear view on people´s opiniontowards the OWEZ
• Impression on influence of thewind farm on attractiveness ofEgmond aan Zee
22 February 2007 EU Policy Workshop on offshore wind power deployment 13
Expected results safety and ships:
• Insight in collision risks andconsequences of oil spills
• Insight in effects onshipping radar
22 February 2007 EU Policy Workshop on offshore wind power deployment 14
First results Monitoring program•Public opinion moving towards far more positive attitude
•No negative influence of OWEZ on tourists on the beach
•Piling caused no disturbance of birds
•Under water noise level during piling is known
•Wind resource available through measurements
•Zero measurements on seals finished
•Risks for vessels very limited
•Results available on www.noordzeewind.nl
22 February 2007 EU Policy Workshop on offshore wind power deployment 15
International collaboration:
•Easy accessible database with results
22 February 2007 EU Policy Workshop on offshore wind power deployment 16
International collaboration:
•Easy accessible database with results
•Cumulative effects
22 February 2007 EU Policy Workshop on offshore wind power deployment 17
International collaboration:
•Easy accessible database with results
•Cumulative effects
•Define potentials and threats
22 February 2007 EU Policy Workshop on offshore wind power deployment 18
International collaboration:
•Easy accessible database with results
•Cumulative effects
•Define potentials and threats
•Disconnection of results and site
22 February 2007 EU Policy Workshop on offshore wind power deployment 19
International collaboration:
•Easy accessible database with results
•Cumulative effects
•Define potentials and threats
•Disconnection of results and site
•EU Standard for research methods
22 February 2007 EU Policy Workshop on offshore wind power deployment 20
International collaboration:
•Easy accessible database with results
•Cumulative effects
•Define potentials and threats
•Disconnection of results and site
•EU Standard for research methods
•Define level of sufficient knowledge
22 February 2007 EU Policy Workshop on offshore wind power deployment 21